EPC of Pump station, Pipeline of water Transmission


Power Line, Road and Facilities

Document Title
Site Progress Sheet

Document Title:

Site Progress Sheet

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED


Contractor Owner MC

EPC of Pump station, Pipeline of water Transmission


Power Line, Road and Facilities

Document Title 0
Site Progress Sheet 0

REVISION
PAGE D0 D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17
1 X X X X X
2 X X X X
3 X X X X X
4 X X X X X
5 X X X X X
6 X X X X X
7 X X X X X
8 X X X X X
9 X X X X X
10 X X X X
11 X X X X
12 X X X X
13 X X X X
14 X X X X
15 X X X X
16 X X X X
17 X X X X
18 X X X X
19 X X X X
20 X X X X
21 X X X X
22 X X X X
23 X X X X
24 X X X X
25 X X X X
26 X X X X
27 X X X X
28 X X X X
29 X X
30 X X
31 X
32 X
33 X X
34 X
35 X
36 X
37 X
38
39
40
41
42
43
44
45
46
47
47
49
50
51
52
53
54
55
56
Contractor Owner MC

EPC of Pump station, Pipeline of water


Transmission Power Line, Road and Facilities

Document Title
Site Progress Sheet
Capacity
Project W.F
WBS Code Activities %
Remarks
Unit Total

Project 100.00%
1.4 Construction 99.41%
1.4.1 Pipe Line & Power Line 99.41%
1.4.1.1 Pipe Line 99.41%
1.4.1.1.1 R.O.W & Channel Construction 54.79%
1.4.1.1.1.1 Primary Surveying M 10470 0.29%
1.4.1.1.1.2 Excavation M3 237392 35.18%
1.4.1.1.1.3 Leveling M3 237392 0.58%
1.4.1.1.1.4 Secondary Surveying M3 237392 0.29%
1.4.1.1.1.5 Road Crossings 1.73%
1.4.1.1.1.5.1 Road Crossings #01 0.43%
1.4.1.1.1.5.2 Road Crossings #02 0.43%
1.4.1.1.1.5.3 Road Crossings #03 0.43%
1.4.1.1.1.5.4 Road Crossings #04 0.43%
1.4.1.1.1.6 GAS Line Crossings 1.73%
1.4.1.1.1.6.1 GAS Line Crossings #01 0.22%
1.4.1.1.1.6.2 GAS Line Crossings #02 0.22%
1.4.1.1.1.6.3 GAS Line Crossings #03 0.22%
1.4.1.1.1.6.4 GAS Line Crossings #04 0.22%
1.4.1.1.1.6.5 GAS Line Crossings #05 0.22%
1.4.1.1.1.6.6 GAS Line Crossings #06 0.22%
1.4.1.1.1.6.7 GAS Line Crossings #07 0.22%
1.4.1.1.1.6.8 GAS Line Crossings #08 0.22%
1.4.1.1.1.7 Petroleum Line Crossings 0.58%
1.4.1.1.1.7.1 Line Crossings #01 0.29%
1.4.1.1.1.7.2 Line Crossings #02 0.29%
1.4.1.1.1.8 River Crossings ( Culvert ) 0.00%
1.4.1.1.1.8.1 Crossings #01 km 1+609 0.00%
1.4.1.1.1.8.2 Crossings #02 km 3+758 0.00%
1.4.1.1.1.8.3 Crossings #03 km 4+208 0.00%
1.4.1.1.1.8.4 Crossings #04 km 5+476 0.00%
1.4.1.1.1.8.5 Crossings #05 km 5+620 0.00%
1.4.1.1.1.8.6 Crossings #06 km 6+070 0.00%
1.4.1.1.1.8.7 Crossings #07 km 6+710 0.00%
1.4.1.1.1.8.8 Crossings #08 km 7+862 0.00%
1.4.1.1.1.8.9 Crossings #09 km 7+953 0.00%
1.4.1.1.1.8.10 Crossings #10 km 9+020 0.00%
1.4.1.1.1.9 River Crossings ( Bridge ) 0.00%
1.4.1.1.1.9.1 Crossings #01 km-1+396 0.00%

Page 4
Contractor Owner MC

EPC of Pump station, Pipeline of water


Transmission Power Line, Road and Facilities

Document Title
Site Progress Sheet
Capacity
Project W.F
WBS Code Activities %
Remarks
Unit Total

1.4.1.1.1.9.2 Crossings #02 km-2+273 0.00%


1.4.1.1.1.9.3 Crossings #03 km 2+311 0.00%
1.4.1.1.1.9.4 Crossings #04 km-3-116 0.00%
1.4.1.1.1.9.5 Crossings #05 km-6+860 0.00%
1.4.1.1.1.9.6 Crossings #06 km-9+536 0.00%
1.4.1.1.1.9.7 Crossings #07 km-9+730 0.00%
1.4.1.1.1.9.8 Crossings #08 km-2+380 - Steel Structure Bridge 0.00%
1.4.1.1.1.10 River Crossings ( Water Course and Paving) 0.00%
1.4.1.1.1.10.1 Crossings #01 km 1+700 0.00%
1.4.1.1.1.10.2 Crossings #02 km 1+880 0.00%
1.4.1.1.1.10.3 Crossings #03 km 2+953 0.00%
1.4.1.1.1.10.4 Crossings #04 km 3+699 0.00%
1.4.1.1.1.10.5 Crossings #05 km 5+700 0.00%
1.4.1.1.1.10.6 Crossings #06 km 8+200 0.00%
1.4.1.1.1.10.7 Crossings #07 km 8+860 0.00%
1.4.1.1.1.10 Soil Movement 2.31%
1.4.1.1.1.11 Final Modification 2.31%
1.4.1.1.1.12 Channel Works 9.81%
1.4.1.1.1.12.1 Excavation 8.33%
1.4.1.1.1.12.2 Substructure 0.20%
1.4.1.1.1.12.3 Embankment 0.29%
1.4.1.1.1.12.4 Sand Fill ( After Piping ) 0.49%
1.4.1.1.1.12.5 Back Fill ( After Piping ) 0.49%
1.4.1.1.2 Mechanical & Piping Completion and Tests 8.40%
1.4.1.1.2.1 Pipes Handling 0.42%
1.4.1.1.2.2 Line Up 0.42%
1.4.1.1.2.3 Fit-Up 1.26%
1.4.1.1.2.4 Welding 1.68%
1.4.1.1.2.5 Joint Lining Repair 0.42%
1.4.1.1.2.6 Joit Wrapping 0.42%
1.4.1.1.2.7 Lay-Up Channel 0.84%
1.4.1.1.2.8 Wraping Repair & Holiday Test 0.42%
1.4.1.1.2.9 Hydrostatic Test 1.26%
1.4.1.1.2.10 Flushing 0.34%
1.4.1.1.2.11 Valve Installation 0.42%
1.4.1.1.2.12 Vents & Drains 0.42%
1.4.1.1.2.13 Box-Up 0.08%
1.4.1.1.3 Valve Pits 2.54%
1.4.1.1.3.1 Surveying 0.05%

Page 5
Contractor Owner MC

EPC of Pump station, Pipeline of water


Transmission Power Line, Road and Facilities

Document Title
Site Progress Sheet
Capacity
Project W.F
WBS Code Activities %
Remarks
Unit Total

1.4.1.1.3.2 Excavation & Leveling 0.43%


1.4.1.1.3.3 Lean Concreate 0.20%
1.4.1.1.3.4 Bar Bending 0.51%
1.4.1.1.3.5 Form Work 0.53%
1.4.1.1.3.6 Main Concrete 0.69%
1.4.1.1.3.7 Coating 0.13%
1.4.1.1.4 Cathodic Protection 1.90%
1.4.1.1.4.1 Transformer Rectifier Installation 0.29%
1.4.1.1.4.2 AC Box Installation 0.19%
1.4.1.1.4.3 High Silicon Cast Iron Anode (HSCI) 0.38%
1.4.1.1.4.4 Anode Junction Box (AJB) 0.38%
1.4.1.1.4.5 Negative Junction Box (NBB) 0.19%
1.4.1.1.4.6 Test Point Marker 0.10%
1.4.1.1.4.7 Cabling & Connections 0.38%
1.4.1.1.5 Power Line 33 KV 31.77%
1.4.1.1.5.1 Civil Works 12.74%

1.4.1.1.5.1.1 Survey Checking ( Towers ) PCS 44 1.27%

1.4.1.1.5.1.2 Foundation ( Towers & Gantry ) 4.46%

1.4.1.1.5.1.3 Access Roads 7.01%

1.4.1.1.5.2 Steel Works 15.66%

1.4.1.1.5.2.1 Structure Sorting PCS 44 3.13%

1.4.1.1.5.2.2 Tower & Gantry Assembly PCS 44 10.96%

1.4.1.1.5.2.3 Full Bolting & Name Plate PCS 44 0.78%

1.4.1.1.5.2.4 Bolt Welding PCS 44 0.78%

1.4.1.1.5.3 Electrical Works 3.37%

1.4.1.1.5.3.1 Guard Caballing PCS 44 0.51%

1.4.1.1.5.3.2 Phase cabling PCS 44 1.52%

1.4.1.1.5.3.3 Insulator Installation PCS 44 0.51%

1.4.1.1.5.3.4 Sectionner Installation PCS 44 0.51%

1.4.1.1.5.3.5 Lightning Arrester Installation PCS 44 0.34%


1.5 Precommisionning, Commisionning and Client Training 0.59%
1.5.1 PreCommisionning 0.59%
1.5.1.2 Pipe Line 0.59%

1.5.1.2.1 Piping Activities 0.52%

1.5.1.2.1.1 Temporary Spades / Blinds Removing 0.02%

1.5.1.2.1.2 Temporary Spools Removing 0.02%

1.5.1.2.1.3 Check-Valves Flappers Installing / Locking Device Removing 0.02%

Page 6
Contractor Owner MC

EPC of Pump station, Pipeline of water


Transmission Power Line, Road and Facilities

Document Title
Site Progress Sheet
Capacity
Project W.F
WBS Code Activities %
Remarks
Unit Total

1.5.1.2.1.4 Bellow Units Installing 0.05%

1.5.1.2.1.5 Correct Nuts & Bolts Installing 0.02%

1.5.1.2.1.6 Temporary Strainers Removing 0.02%

1.5.1.2.1.7 Main Gaskets Installing 0.07%

1.5.1.2.1.8 Checking Valves Tag No's. Correct 0.02%

1.5.1.2.1.9 Checking Flow Direction Of Valves 0.02%

1.5.1.2.1.10 Checking Valves Stems & Valves Orientation Correct 0.02%

1.5.1.2.1.11 Insulation Kits Installing 0.11%

1.5.1.2.1.12 Water Filling 0.10%

1.5.1.2.2 Cathodic Protection Tests & Operation 0.07%

1.5.1.2.2.1 Cathodic Protection Tests & Operation 0.07%