Today’s Observation (Joint Visit of IOCL and Hill Representative with SPCPL HSE Coordinators at Site) Date: 26.10 2022
Sr Expected Date of
No. Observations to SPCPL Completion
1 Block A2 : Housekeeping for scaffolding materials pending SPCPL has taken corrective action Closed
2 Block B : Outer edge challis arrangement to be rectified SPCPL has taken corrective action Closed
3 Block B : Staircase access shall be inspected, and tagged SPCPL has taken corrective action Closed
with proper arrangement of green mesh
4 Block A2 : Wet cable near the water tank SPCPL has taken corrective action Closed
5 Block B : Hard /soft barricade required Ist casting area to SPCPL has taken corrective action Closed