Schedule Narration

1. Material receipt dates considered


 Flanges @ Port Receipt at QICL: 13-July-2022 [ Lot-1]
 Pipes @ Port Receipt at QICL: 13-July-2022[ All Lots]
 Flanges from Korea Receipt at QICL : 5 Weeks from payment release assumed date (@
QICL 14th August)
 Refractory Material receipt at QICL : 28th August
2. Lot-1 Critical Path activities:
 PAUT completion
 Bottom Dish welding with shell completion
 Skirt Fabrication completion
 Nozzle preparation

3. Lot-2 Critical Path Activities


 Receipt of flanges
 Bottom dish welding with shell
 PAUT of LS & CS

4. Lot-2 Critical Path Activities


 Receipt of Flanges
 CS fit up and welding
 Readiness of bottom dish
 Skirt Fabrication
 Nozzle preparation

5. Lot -3 Critical Path Activities