This document outlines the schedule and receipt dates for key materials for three lots of fabrication. It notes that flanges and pipes will be received at the port on July 13th, while flanges from Korea will arrive around August 14th and refractory material on August 28th. For Lot 1, critical path activities include PAUT completion, bottom dish welding with shell completion, skirt fabrication, and nozzle preparation. For Lot 2, critical activities are receipt of flanges, bottom dish welding with shell, and PAUT of lower and upper shells. Lot 3 does not specify critical path activities.
This document outlines the schedule and receipt dates for key materials for three lots of fabrication. It notes that flanges and pipes will be received at the port on July 13th, while flanges from Korea will arrive around August 14th and refractory material on August 28th. For Lot 1, critical path activities include PAUT completion, bottom dish welding with shell completion, skirt fabrication, and nozzle preparation. For Lot 2, critical activities are receipt of flanges, bottom dish welding with shell, and PAUT of lower and upper shells. Lot 3 does not specify critical path activities.
This document outlines the schedule and receipt dates for key materials for three lots of fabrication. It notes that flanges and pipes will be received at the port on July 13th, while flanges from Korea will arrive around August 14th and refractory material on August 28th. For Lot 1, critical path activities include PAUT completion, bottom dish welding with shell completion, skirt fabrication, and nozzle preparation. For Lot 2, critical activities are receipt of flanges, bottom dish welding with shell, and PAUT of lower and upper shells. Lot 3 does not specify critical path activities.
Flanges @ Port Receipt at QICL: 13-July-2022 [ Lot-1] Pipes @ Port Receipt at QICL: 13-July-2022[ All Lots] Flanges from Korea Receipt at QICL : 5 Weeks from payment release assumed date (@ QICL 14th August) Refractory Material receipt at QICL : 28th August 2. Lot-1 Critical Path activities: PAUT completion Bottom Dish welding with shell completion Skirt Fabrication completion Nozzle preparation
3. Lot-2 Critical Path Activities
Receipt of flanges Bottom dish welding with shell PAUT of LS & CS
4. Lot-2 Critical Path Activities
Receipt of Flanges CS fit up and welding Readiness of bottom dish Skirt Fabrication Nozzle preparation