C&S Weekly Meeting

(22/12/13)
1. Design Issue
Item 1.1 Working Bore Pile Method of Statement
Item 1.3 CCM to resubmit
CCM will find the solution by today or tomorrow first…. And then will resubmit
BV: If it’s not approved, the Feng Shui Pile won’t start
BV: How about the welded stud
CCM: Explained about writing RFA again with respecting the spec of welding test and submit to
do it on site
BV: When to start with Feng Shui Pile
BV: MHT increase the rebar of Feng Shui Pile
CCM: We already relied on MHT comment…on site already prepare to fabricate based on MHT
And today morning already have rebar cage fabricated
BV: Chase CCM to talk to MHT
2. Site Construction Issue
Item 1. 1/ No more monitoring and installation work
2/ BV: CCM need to submit monitoring report…..
CCM: Submit on Thursday
Item 1 : Piling Coordinates
CCM: At of the meeting...will submit
BV: When CCM plan to start feng shui pile number 1?
CCM: By Friday, complete the material testing… and then submit RFA….(Mid of next
week…start FS pile) proposed 2 weeks look ahead (Piling construction activities)
BV: Just rebar installation, not construction
3. Schedule
Item 1 :
Item 2:
Item 3: BV: Last week we received the table of 1, 2 , 3, 4
CCM: We submit Feng Shui pile Rev01 and 02….
I
Any Other Business
CCM: We get rid of the sticky issues and will start Feng Shui Pile