CMW-21034 Procurement Status for Electrical Items

Material Request with No of Days till 15-11-2022


Sr # Description of Item Material Request Reference MR Date CMW Approval Purchase Order Status Delivery Status Remarks
full quantity from Site from MR date

1 uPVC Pipes and Fittings for Telecom/Electrical Raised INR/10/CMW-21034/2022-0005-R2 06-07-2022 Approved PO Released Delivered Completed

2 PVC Conduits, Fittings and Accessories (20/25)mm Raised INR/10/CMW-21034/2022-0009-R1 14-07-2022 Approved PO Released Delivered Completed

3 GI Back Boxes Raised INR/10/CMW-21034/2022-0027-R1 01-09-2022 Approved PO Released Delivered Completed

4 Polypropylene Rope Raised INR/10/CMW-21034/2022-0027-R1 01-09-2022 Approved PO Released Not Delivered 76 Days

5 Motion Sensors Raised INR/10/CMW-21034/2022-0030-R0 16-08-2022 Approved Under Procurement Not Delivered 82 Days

6 Warning Tape for Electrical / Telecom Raised INR/10/CMW-21034/2022-0032-R1 10-10-2022 Approved Under Procurement Not Delivered 37 Days

7 Concrete Cable Tiles Raised INR/10/CMW-21034/2022-0031-R0 16-08-2022 Approved PO Released Delivered Completed

8 Low Voltage Cables Raised INR/10/CMW-21034/2022-0034-R0 25-08-2022 Approved PO Released Delivered Completed

9 Light Poles Raised INR/10/CMW-21034/2022-0040-R0 07-09-2022 Approved Under Procurement Not Delivered 82 Days

10 Electrical Isolators Raised INR/10/CMW-21034/2022-0041-R0 12-09-2022 Approved Under Procurement Not Delivered 65 Days

11 Light Fittings Raised INR/10/CMW-21034/2022-0042-R0 12-09-2022 Approved Under Procurement Not Delivered 65 Days

12 Floor Boxes Raised INR/10/CMW-21034/2022-0044-R0 12-09-2022 Under Procurement Under Procurement Not Delivered 65 Days

13 Wiring Accessories (Switches, sockets etc) Raised INR/10/CMW-21034/2022-0045-R0 12-09-2022 Approved Under Procurement Not Delivered 65 Days

14 Single Core Wires Raised INR/10/CMW-21034/2022-0046-R0 14-09-2022 Approved PO Released Delivered Completed

15 Telecom Manhole Covers Raised INR/10/CMW-21034/2022-0047-R0 23-09-2022 Under Procurement Under Procurement Not Delivered 54 Days

16 SMATV System Raised INR/10/CMW-21034/2022-0052-R0 22-09-2022 Approved PO Released Not Delivered 55 Days

17 Structured Cabling System (Tel/Data) Raised INR/10/CMW-21034/2022-0049-R0 20-09-2022 Under Procurement Under Procurement Not Delivered 57 Days

18 GI Trunkings, Conduits and Fittings Raised INR/10/CMW-21034/2022-0050-R0 20-09-2022 Approved Under Procurement Not Delivered 57 Days

Quantity & Technical


19 Gate Barrier System Under Procurement Under Procurement Not Delivered
information given
Quantity & Technical
20 Electrical Switchgear Under Procurement Under Procurement Not Delivered
information given
Quantity & Technical
21 Fire Alarm System Approved Under Procurement Not Delivered
information given
Quantity & Technical
22 Fire Alarm Cables Under Procurement Under Procurement Not Delivered
information given
Quantity & Technical
23 Lightning Protection and Earthing System Approved Under Procurement Not Delivered
information given
Quantity & Technical
24 Cable Glands and Lugs Approved IR not raised by Site team Not Delivered
information given