Daily Work Progress (Gas Network) 14-01-2023

Street No of No Of Excavation
Sr# Block Street Side & Pipe House Ramps Done Pipe Laid Contractor’s Machinery
Length size & Ramp demolished (Meter) (Meter) Man Power
1 C Sir Syed _ _ _ 370mtr Road Cross _
Road pending
R
2 A Lake L _ _ _ 40mtr _ 8
Road,
C Lake L _ _ _ 870mtr Road Cross _
Road, pending
6 A.I Rd _ _ _ 01 Excavator
B 1,8,9,10, L&R 4865mtr 2850mtr 33
11A,11B.
12,13,14,
15,1617,
18,19,20,
21,22,23,
24,25
Total Man 41
Overtime: Hours Time
Power
Muhammad Razwan 2 19:05

Muhammad Sajjad 0 0:00

Work Completed from 08-09-22 to till Date


Sr# Block Street Length Excavation Laying Backfilling Work status
of St of pipe
St 01 to 15
(Lake Road, J. Boulevard,
1 A 9900mtr Done Done Done Completed
Ch. Rehmat Road)
St 8 to 28, lake Road, Ring Road, Allama Iqbal
Road
2 C 14950mtr Done Done Done Completed
(St 1-29 other side of Lake Backfilling in
Progress)
Ring Road, Hafeez Jalandhri Road,
J. Boulevard, Ch. Rehmat Rd,
3 D 12100mtr Done Done Done Completed
J. Boulevard,
(St 01to 32)
4 I St 1,2,3,4,7,8 2100mtr Done Done Pending Backfilling Pending

Total Network 86840 Meter Work Done 39050 Meter 45%

Assistant Manager
Gas Net(Topcity-1)