You are on page 1of 3

Progress Report of Augmentation & Strengthening of Adityapur Water Supply Scheme under Adityapur Municipal

Corporation Urban Water Supply


Agency :- JWIL Infra Ltd. ; Project Cost :- 395.14 Cr (Capex- 326.55 cr. Opex -68.59 Cr)
Agreement no :- JUIDCO/NIT/Adityapur WSS/2018/185; Funding Source :- AMRUT ; Name of PMC:-iDeCK Ltd.; Contractor:- JWIL- SPML (JV)

Daily Progress Report for 01.07.2021


Sl. Location Description of job Man Power % of work & job Equipment Engased Job Progress Cumulative Progress till
No. Engased in done as on as on 30.06.2021
Nos 30.06.2021 30.06.2021

1 ESR.-2 (Bhatiya Basti); (1.6-ML)- No work 0 10-25 %


Staging
Ht.- 25 M.
2 ESR.-3 (Hariom Nagar Rd.No.1,Durga Curing; Removing of formwork 8 25-30 %
Puja Maidan for 1st lift column above Plinth
(2.4-ML) -Staging Ht.- 25.0 M. Beam and Fixing of Dowel bar in
strair landing beam.

3 ESR.-4 (Near Railway Yard)ML-


1.9 ;Staging Ht.- 25 M. No work 0 25%

4 ESR.-5 (Near Railway Yard)ML- (1.5 Reinforcement work of Dome


ML);Staging Ht.- 20 M. bottom Slab. 22 40-45 %

5 ESR.-6 (Near Block Office


,Gamharia;(1.5-ML) ;Staging Ht.- 20 No work 0 35-40 %
M.
6 ESR.-7 (Near old stn.rd.Govt.School);
(2- ML)-;Staging Ht.-25 M. No work 0 25-30 %

7 ESR-No.8 (Mirudih);(1.0-ML); Staging Formwork and alignment of 17 50-57 % D.G. set- 1 No, Gas
Ht.- 22 M. Dome Wall. cutting set-1 No,
Welding set- 1 No.

8 ESR-No.9 (Banta Nagar);(2.1 ML)


;Staging Ht.-15 M. No work 0 25-30 %

9 ESR.-10 (Banta Nagar);(1.6-ML) 0 25-30 %


Staging Ht.- 15 M. No work

10 ESR.-11 (Kuluptanga); (2.5-ML ; Curing of footings; Formwork of Tanker- 1 No


Staging Ht.-15.0 M. 1st lift column below Plinth 10 10-25 %
beam.
11 DN Zone 1,DMA-1-Ward No-2; Bustee- Reinforcement & Formwork of Mixer Machine- 1
Near Dheeraj ganj. sluice valve chamber raft-100 3 No.
mm dia.
12 DN Zone 1,DMA-1 & Zone-3, DMA-5; Curing & Road Restoration by JCB-2 No, Tractor-1
Ward-2 & Phase-6 PCC M15 & M40. 17 No, Miller- 1 No, Flori-
1 No
13 DN Zone 1,DMA-1-Ward No-6; Bustee- Approx. Length- Mixer Machine- 1
Near Birsa chowk Road Restoration by PCC M15. 6 90.0 Mtr No; Miller- 1 No.

14 DN Zone 3,DMA-5-Ward No-2; Bustee- Dismantling of concrete road JCB-1 No, Breaker- 1
Near Sudha Dairy. and Earth work excavation and No.
13 184.90 m 296232.50 M
D.I.pipe laying 100 & 150 mm
dia.
15 DN Zone 3,DMA-5-; Phase-6, RCC M25 of sluice valve Flori- 1 No.
industrial area. chamber wall-150 mm dia & PCC
2
M10 for sluice valve chamber-
100 mm dia-2 Nos.
16 DN Zone 6,DMA-1(O & M);- House service connection. 8 Approx. 53 Nos House Service
Ward No-17 ; Basti-Hariom Connection-4 Nos Connection
nagar,Road No-4. - 6118 Nos
17 DN Zone 6,DMA-4 (O House service connection. 11 Approx.
& M);-Ward No-14 ; Near hari mandir Connection-12 Nos

18 DN Zone 6,DMA-4 :-Ward No-14 &15 ; Earth work excavation and 25 Breaker-1 No
Champai nagar & imli chowk D.I.pipe laying 300 mm dia and
Dismantling of concrete road.

19 DN Zone 6,DMA-4 & 5 ;-Ward No-15 ; Earth work excavation and 7 JCB- 1
Near srinath collage & Champai D.I.pipe laying 300 mm dia No.
nagar.
20 DN Zone 6,DMA-5 (O House service connection. 8
& M);-Ward No-12 ; Near tripura
colony.
21 DN Zone-8,DMA-2;-Phase-2, Tanker- 1 No
Preparation of Hydrotest (L=0.25
Aiada Road, Near Nagar Nigam 4
KM; Dia-100 mm) .
Office.
22 DN Zone-8,DMA-2;-Phase-2, JCB-1 No,Tractor-1
Road Restoration by PCC M15 at
Aiada Road, Near Nagar Nigam 11 No, Miller- 1No.
AIADA Road.
Office.
23 DN Zone-8,DMA-3;-Phase-2, Earth work excavation and 14 Approx. Length- JCB- 1
Industrial area. D.I.pipe laying 100 & 150 mm dia 55.0 Mtr No; Flori - 1 No.
and Reinforcement, formwork &
RCC M25 of sluice valve
chamber raft-150 mm dia-1 No.

24 DN Zone-8,DMA-4;-Phase-2, 3 Tanker- 1 No
Preparation of Hydrotest (L=0.12
Industrial area.
KM; Dia-100 mm) .
25 DN Zone-9,DMA-1;-Ward No-33; Preparation of Hydrotest. 4 Tanker-1 No.

26 DN Zone-9,DMA-2;-Ward No-27; Earth work excavation and Approx. Length-


Bustee- Near Baba ashram D.I.pipe laying 300 mm dia. 7 24.90 Mtr JCB-1 No

27 DN Zone-9,DMA-2;-Ward No-26; Approx.


Bustee-Near baba ashram. House service connection. 5 Connection-11 Nos

28 DN Zone-9,DMA-4 & ZONE-10, DMA-2


Ward No-27
Bustee-Near JMT indusrty. Dismantling of Concrete road 2 Breaker-1 No

29 DN Zone-9,DMA-4; Earth work excavation and Approx. Length- JCB-1


Ward No-24; Industrial area. D.I.pipe laying 100 mm 7 55.0 Mtr No.
dia.
30 DN Zone-10,DMA- 2;-Ward No- Earth work excavation and JCB-1 No,
30;MIG colony-144 D.I.pipe laying 150mm dia. 8

31 DN Zone-10,DMA- 2;-Ward No- Earth work excavation and Approx. Length- JCB-1 No,
30; LIG colony-220. D.I.pipe laying 350mm dia. 50.0 Mtr
7

32 DN Zone-10,DMA- 2;-Ward No-30; House service connection. 7 Approx.


MIG Connection-6 Nos
Colony.

33 DN Zone-10,DMA- 2;-Ward No-30; Preparation for Road 2 JCB-1 No.


MIG colony, LIG Colony. Restoration.

34 DN Zone-10,DMA- 3;-Ward No-32; Road restoration by PCC M15. 10 Miller- 1 No.


LIG Colony.

35 DN Zone-10,DMA- 3;-Ward No-6; House service connection. 10


Road No-5

36 DN Zone-10 & 11,DMA- 3; Ward No- Removing of Debris from site. 5 JCB-1No
28

37 DN Zone-11,DMA- 1;-Ward No- Reinforcement; Form work & Mixer machine- 1 No.
35 & 32; Bustee-Kulaptanga & Road RCC M25 of Sluice Valve
6
No- 15. chamber slab-100 mm dia- 1 No .

38 DN Zone-11,DMA- 1(O&M);- Approx.


Ward No-31& 32; Bustee--Road No- House service connection. 4 Connection-12 Nos
13,14
, 15Zone-11,DMA-
39 DN & 16. 1 & 4(O&M);-
Ward No-30 & 25; Road No- 16,17 & House service connection. 8
31
40 DN Zone-11,DMA- 4;-Ward No- Approx. Length- Miller- 1 No.
28 ; Road No-05 Road Restoration by PCC M15. 8 122.0 Mtr

41 DN Zone-11,DMA- 4;-Ward No- Approx.


28 ; Bustee-Road No-31 House service connection. 13 Connection-8 Nos

TOTAL 302 Nos


Note: 1. 6o MLD Forest Clearance: - NOC Forest Clearance proposal pending with forest secretary Nepal house .2.FRA /NOC certificate is pending with
D.C.Saraikela.(Nazri naksha required from Block office gamhariya)
2.Land schedule of Entire network of Water pipeline: Land schedule received on 07.07.2020 from C.O. Gamaharia Office. For tattered khata khatiyan pending with Rajkiya
Mundralay Patna and Abhilekhagar Officer, Chaibasa although two letters we have received for nonavailability of khata khatiyan from Land Reform Department Saraikela
Kharsawan & Settelemet department East Singhbhum, Jamshrdpur.We received some record of Khata Khatian from Chaibasa and same has been submitted to
C.O.Gamharia.CO gamhariya send the fiel to the DC seraikela on 27.03.2021 after that DC seraikela return file (khata khatiyan ) to the Co sir ,now it is pending with
C.O.Gamharia.
3.NOC for laying of pipeline in the area of RCD: NOC received from RCD Saraikela on 13.03.2020. Now the job is in progress. But permission for laying D.I.Pipe in- service
road at Tata Kandra Road received on 04.11.2020.Now JARDCL ask to submit the estimate and estimated amount to be
paid by JUIDCO for security purpose.