Pipeline Rate of Work Calculations
Pipeline Rate of Work Calculations
Rate of Work for Regular Ground ¿ 12 pipes∈a day=12 x 6 m=72m per day
Rate of Work for Hard Rock ¿ 3 pipes∈a day ¿ 3 x 6 m=18 m per day
1 430.62
Expected duration if route has no Hard Rock ¿ ≈ 20 Days
72
1041.62 389
Duration of works including Hard Rock ¿ + ≈ 36 Days
72 18
No. of Day of Extra Work ¿ 36 Days−20 Days=16 Days