Pipeline Rate of Work Calculations

Length of Route ¿ 1430.62 m

Length of Hard Rock Encountered ¿ 389 m

Length of Area Unaffected ¿ 1430.62 m – 389 m=1041.62 m

Rate of Work for Regular Ground ¿ 12 pipes∈a day=12 x 6 m=72m per day

Rate of Work for Hard Rock ¿ 3 pipes∈a day ¿ 3 x 6 m=18 m per day

1 430.62
Expected duration if route has no Hard Rock ¿ ≈ 20 Days
72
1041.62 389
Duration of works including Hard Rock ¿ + ≈ 36 Days
72 18
No. of Day of Extra Work ¿ 36 Days−20 Days=16 Days