Professional Documents
Culture Documents
MET
METHOD STATEMENT
MOCK
MOCK-UP SPAN WORKS
AMENDMENT HISTORY
TABLE OF CONTENTS
5.0 APPENDICES 35
1.2 Reference
Relevant documents associate with this Scope of Work are as follows;
No. Document/Drawing No. Description
1. SSP-AZSB-PKG2-OVPR-PLN- Project Execution Plan, Ahmad Zaki Sdn Bhd
00010 for Projek Mass Rapid Transit Lembah Kelang
Sungai Buloh – Serdang – Putrajaya
(Package V202)
2. SSP-AZSB-PKG2-OVPR-PLN- Project Quality Plan, Ahmad Zaki Sdn Bhd for
00008 Projek Mass Rapid Transit Lembah Kelang
Sungai Buloh – Serdang - Putrajaya
(Package V202)
3. SSP-AZSB-PKG2-OVPR-PLN- Safety & Health Management Plan Ahmad
00002 Zaki Sdn Bhd for Projek Mass Rapid Transit
Lembah Kelang Sungai Buloh – Serdang –
Putrajaya (Package V202)
4. SSP-AZSB-PKG2-OVPR-PLN- Environmental Management Plan (Selangor)
00003 Ahmad Zaki Sdn Bhd for Projek Mass Rapid
Transit Lembah Kelang Sungai Buloh –
Serdang – Putrajaya (Package V202)
5. SSP-AZSB-PKG2-OVPR-PLN- Environmental Management Plan (Wilayah
00009 Persekutuan) Ahmad Zaki Sdn Bhd for Projek
Mass Rapid Transit Lembah Kelang Sungai
Buloh – Serdang – Putrajaya (Package V202)
6. SSP-AZSB-PKG2-OVPR-PLN- Emergency Preparedness and Response
00001 Plan Ahmad Zaki Sdn Bhd for Projek Mass
Rapid Transit Lembah Kelang Sungai Buloh –
Serdang – Putrajaya (Package V202)
7. SSP-AZSB-PKG2-OVPR-PLN- Survey Quality Plan Ahmad Zaki Sdn Bhd for
00012 Projek Mass Rapid Transit Lembah Kelang
Sungai Buloh – Serdang – Putrajaya
(Package V202)
8. SSP-AZSB-PKG2-OVPR-PLN- Risk Management Plan Ahmad Zaki Sdn Bhd
00013 for Projek Mass Rapid Transit Lembah Kelang
Sungai Buloh – Serdang – Putrajaya
1.3 Materials
Schedule of material for activities associated with this method statement are as
follows;
No. Materials Description
a. 0.6” Wedges Post Tensioning works
b. HDPE Pipe Post Tensioning works
1.5 Manpower
Persons directly involve with site activities stated in this MS are as follows;
No. Descriptions No. of Person
a. Construction Manager 1 person
b. Project Engineer 1 Person
c. Supervisor 1 Supervisor
Survey Team: 1 teams consist of 1
d. Surveyor / Chainman surveyor and 3
chainman
e. Skilled Workers 10 person
c) At each end of the span, the pier segment will be supported by two (2) numbers
of 250 ton flat jacks (with adjustable jack bases) and two (2) numbers of 100 ton
flat jacks (with adjustable jack bases) which are placed on top of the UC steel
beam (Figure 1.6.3 (a) and Figure 1.6.3 (b)).
d) The 250 ton flat jacks are located at the same location of the permanent
bearings location. They are equipped with sliding jack bases to allow
longitudinal movement during tendons stressing. The position of these flat jack
must follow as per stated in the construction drawing.
e) The UC steel beam will be equipped with 28 nos beam clamp to ensure the UC
steel beam is firm (Figure 1.6.3 (h), Figure 1.6.3 (i), Figure 1.6.3 (l) and Figure
1.6.3 (m)).
f) Steel frame is used to strut the first pier segment for stability during erection.
g) Vertical access is placed at the side of pier segment.
i) Adjust the segment top level to horizontal level with spirit level and chain
block attached to lifting beam and mobile crane lifting hook (Figure 1.6.4
(c)).
j) Once pier segment is in target position and level, the two 250 ton flat jacks
and two 100 ton flat jacks are jacked up gently to bring into contact with the
soffit of the segment by applying nominal pressure, but not to push up the
segment.
k) The mobile crane then gradually releases the force to transfer the load onto
the jacks. Monitor the pressure gauge of each jack. The increase in pressure
for the jacks will indicate the load of the segment being transferred from the
mobile crane to the jacks.
l) The Surveyor shall take levels, position and alignment of the pier segment.
m) The survey information is used to adjust the segment using the flat jacks
with adjustable jack bases. After resurvey and confirmed by Surveyor, the
lock nuts of the jacks shall be turned up to mechanically lock the jacks.
d) Segment is lifted close to the final position. Two number of temporary tie
(lever block) installed at top and bottom of segment are used to secure the
segment to the erected segment (Figure 1.6.5 (c)). Adjust the segment top
level to horizontal level with spirit level and chain blocks attached to lifting
beam and mobile crane lifting hook.
e) The 100 ton flat jacks (C) sliding base must be pre-set at least 40mm to
50mm clearance to allow horizontal movement during jointing process
(Figure 1.6.5 (e)). Next, the 100 ton flat jacks (B and C) are then brought into
contact with the soffit of the segment by applying nominal pressure, but not
to push up the segment (Figure 1.6.5 (f)).
f) The mobile crane then gradually releases and transfers the load onto the flat
jacks (Figure 1.6.5 (g)). Monitor the pressure gauges of each jack. The
increase in pressure for the jacks will indicate the load of the segment being
transferred from the mobile crane to the jacks. The segment jointing shall be
carried out by sliding the segment. The screw nuts securing the 100 ton flat
jacks (C) must be release before sliding the segment (Figure 1.6.5 (h)).
Segment shall be slide by using 30 ton Baby Jack (Figure 1.6.5 (i) and
Figure 1.6.5 (j)). WPC must ensure there is no gap between segments. Gap
between segments will affect elongation of the tendons stressing. Release
the mobile crane hook from the lifting beam. Sliding mechanism is then
being removed and shall be used for subsequent segment.
g) Surveyor rechecks the levels while jacks pistons were jacked up or down
until correct levels is achieved. Turn up the lock nuts to mechanically lock
the jacks. Then release the hydraulic pressures in the jacks.
h) Repeat steps a to g for the erection of next segment until all remaining
segments for the span are completed. Recheck the direction of each
segment to be launched before launching.
i) For the last pier segment, it will rest on two number of 250 ton and two
number of 100 ton flat jacks. The last pier segment is equipped with
instrumentation. Thus, care should be taken to ensure no damaged to any of
the instrumentation cabling during erection and stressing works.
j) Calibration certificates for the stressing jacks and pressure gauges shall be
provided prior to the commencement of the stressing operations.
k) No person shall be allowed to stand behind the stressing jack during
stressing in case of accidental breakage of strands which may cause injury.
l) For Double Track Span DS39.8, tendons T7 shall be stressed inside the box
girder. A stressing jack shall be lifted and brought into the box girder by
trolley. It is then hung by chain blocks (Figure 1.6.6 (a)).
m) Due to space constraint, tendons T7 to be stressed using single stressing
jack where the stressing sequence should follow as per construction drawing
reference no. SSP-H-AZSB-PKG2-OVPR-CNS-VSR-000311. Tendons T7 to
be stressed in stages as follow;
1.6.7 Monitoring
a) After completion of tendons stressing, the entire span shall be left
undisturbed for one month for monitoring purposes. The monitoring
processes include deflection of span, coefficient of losses, elongation and
concrete stress.
b) As the footing foundation is not supported on piles, there will be a little
settlement of the footings due to consolidation and compression of layers
underneath the footing. For monitoring of levels and deflection, the net
movement after deducting settlement effects at the end footings shall be
considered.
c) There is the option of jacking up the flat jacks to bring back the levels to
levels immediately after stressing.
1. De-tensioned T7 L – 1 strand.
2. De-tensioned T7 R – 2 strands.
3. De-tensioned T7 L – 2 strands.
4. De-tensioned T7 R – strands, and so on until completion.
h) Use a hook to pull out and remove the wedges from the anchor head.
i) Release the force in the strand to zero.
j) Repeat the de-tensioning cycle to each strand one by one. The de-
tensioning sequence shall be in the reverse order of stressing tendons.
c) Gradually releases and transfers the load from 100 ton flat jacks (B) to the
100 ton flat jacks (A) (Figure 1.6.9 (b)). The segment dismantling shall be
carried out by sliding the segment. The screw nuts securing the 100 ton flat
jacks (C) must be release before sliding the segment (Figure 1.6.9 (c)).
Segment shall be dismantled by using 30 ton Baby Jack (Figure 1.6.9 (d)
and Figure 1.6.9 (e)).
d) Gradually lifted up the pier segment and lifted to the temporary storage area.
e) Repeat steps a to d for the dismantling of next segment for all remaining
segments.
Hazards, risk and associated control measures associated with activities stated
in this MS are detailed in the Job Safety Analysis (JSA) as per Appendix 5.2.
5.0 APPENDICES
Appendix 5.1- Work Sequence Flowchart
Appendix 5.2 - Job Safety & Health Analysis
Appendix 5.3 - Environmental Aspect & Impact Register
Appendix 5.4 - Inspection and Test Plan
Appendix 5.5 - Quality Control Inspection Checklist
Appendix 5.6 - Flat Jack Info
Appendix 5.7 - Stressing Jack & Pressure Gauge Calibration Certificate
Appendix 5.8 - Temporary Footing Foundation Design Calculation
Appendix 5.1
Work Sequence Flowchart
Installation of Jacks
Stressing tendons
Monitoring
De-tensioning work
MOCK-UP SPAN WORKS Revision: 01
Appendix 5.2
Job Safety & Health Analysis
ISSUANCE AUTHORITY
We hereby undertake the accountability to ensure the work activities approved under this permit are executed safely in
accordance to conditions of contract, Malaysia legal requirements, standards, code of practice and AZSB safety
requirements.
In the event of non-compliance, this permit is automatically invalid and AZSB reserves the right to stop work. AZSB HSE
Department will not be responsible for any inconvenience caused by the stop work order.
PERSON IN CHARGE SIGNATURE DATE
CRANE OPERATOR
SUBCONTRACTOR :
PICOW/ SSS/ SHO/ SHM
AZSB :
SSS/ SHO/ SHM
AZSB :
CM/ PM/ PD
Time of inspection:
SUBCONTRACTOR : SIGNATURE
PICOW/ SSS/ SHO/ SHM
AZSB : SIGNATURE
SSS/ SHO/ SHM/ PM/ PD
WORK AT HEIGHT PERMIT SH Form No. MRT-SHE-020
Revision No. 0
Revision Date 0
Issue Date 10 June 2015
Page 1 of 1
ISSUANCE AUTHORITY
We hereby undertake the accountability to ensure the work activities approved under this permit are executed safely in
accordance to conditions of contract, Malaysia legal requirements, standards, code of practice and AZSB safety
requirements.
In the event of non-compliance, this permit is automatically invalid and AZSB reserves the right to stop work. AZSB HSE
Department will not be responsible for any inconvenience caused by the stop work order.
PERSON IN CHARGE SIGNATURE DATE
SUBCONTRACTOR :
PICOW/ SSS/ SHO/ SHM
AZSB :
SSS/ SHO/ SHM
AZSB :
CM/ PM/ PD
Time of inspection:
SUBCONTRACTOR : SIGNATURE
PICOW/ SSS/ SHO/ SHM
AZSB : SIGNATURE
SSS/ SHO/ SHM/ PM/ PD
MOCK-UP SPAN WORKS Revision: 01
Appendix 5.3
Environmental Aspect & Impact
Register
Discharge to land - Silt on road Public/community concern (Road Construction of wash through to clean up the tyres prior
surface dirty) Project Manager, Construction moving onto public road
Manager, Environmental Standby workers for road cleaning
4 2 8 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Discharge to water -Oil leaking from Reduce water quality and aquatic All construction machineries and vehicles must be
vehicles habitat – contaminant in term of properly serviced and maintained to ensure that they are
sediment, diesel and hydraulic fluid. Project Manager, Construction in good working condition.
Manager, Environmental
Manager, Environmental
Officer, Site Engineer, Site Provide of drip tray - oil and grease is prohibited from
Supervisor being disposed on-site or discharged into any
3 2 6 Yes watercourse
Appendix A
Discharge to soil -Oil leaking from Land Pollution/contamination Regular inspection and maintenance for vehicles and
vehicles Project Manager, Construction machineries
Manager, Environmental
Contaminated soil must be collected in drums,
Manager, Environmental
transported and disposed off-site by licensed contractor
Officer, Site Engineer, Site
3 2 6 Yes (treated as scheduled waste, EQA 1974 (SW) 2005
Supervisor
Generation / disposal of Scheduled Land contamination Scheduled waste must be collected in proper container,
waste Project Manager, Construction transported and disposed off-site by licensed contractor
Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Consumption of raw material and Depletion of non-renewable All construction machineries and vehicles must be
natural resources resources Project Manager, Construction properly serviced and maintained to ensure that they are
Manager, Environmental in good working condition.
2 2 4 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Discharge to water -Water runoff Water pollution - Reduce water Construction of silt fence / check dam / silt trap and
from site carrying silt quality and aquatic habitat 4 3 12 Yes Project Manager, Construction temporary sump
Manager, Environmental
Officer, Site Engineer, Site Daily inspection and weekly maintenance of BMPs stated
Supervisor in EMP and ESCP
Discharge to water -Oil leaking from Reduce water quality and aquatic Project Manager, Construction All construction machineries and vehicles must be
vehicles habitat – contaminant in term of Manager, Environmental properly serviced and maintained to ensure that they are
sediment, diesel and hydraulic fluid. Officer, Site Engineer, Site in good working condition.
Supervisor
Provide of drip tray - oil and grease is prohibited from
being disposed on-site or discharged into any
3 2 6 Yes watercourse
Discharge to land - Silt on road Public/community concern (Road Construction of wash through to clean up the tyres prior
surface dirty) Project Manager, Construction moving onto public road
Manager, Environmental
5 3 15 Yes
Officer, Site Engineer, Site Standby workers for road cleaning
Supervisor
Generation of noise and vibration Public/community concern (Noise Working within the approved limit hours.
pollution and vibration) 3 2 6 Yes Project Manager, Construction
Manager, Environmental
Officer, Site Engineer, Site Regular inspection and maintenance for vehicles and
Supervisor machineries
Generation / disposal of construction Depletion of available landfill Disposed at approved designated dump area.
waste 5 3 15 Yes Project Manager, Construction
Manager, Environmental
Manager, Environmental Temporary stockpile at predetermine area.
Officer, Site Engineer, Site
Supervisor
Generation / disposal of Scheduled Land and water contamination Scheduled waste must be collected in proper container,
waste Project Manager, Construction transported and disposed off-site by licensed contractor
Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Appendix A
3. Survey and setting Release to air - Release of CO, dust, Air pollution All construction machineries and vehicles must be
out SOX, NOx, PM10 properly serviced and maintained to ensure that they are
in good working condition.
Project Manager, Construction
Manager, Environmental
2 2 4 Yes Manager, Environmental All trucks / lorries / machinery shall turn off their engine
Officer, Site Engineer, Site during rest or idling time
Supervisor
Using of water browser to wet access road to minimize
dust dispersion
Discharge to water - Oil leaking from Water pollution - Reduce water All construction machineries and vehicles must be
vehicles quality and aquatic habitat – properly serviced and maintained to ensure that they are
Project Manager, Construction
contaminant in term of sediment, in good working condition.
Manager, Environmental
diesel and hydraulic fluid.
Manager, Environmental
Officer, Site Engineer, Site Provide of drip tray - oil and grease is prohibited from
Supervisor being disposed on-site or discharged into any
2 2 4 Yes watercourse
Spent oil and grease from machines and generators
must be collected in drums, transported and disposed off-
site by licensed contractor (treated as scheduled waste,
EQA 1974 (SW) 2005
Discharge to soil - Oil leaking from Land Pollution / contamination Project Manager, Construction Provide of drip tray to avoid spillage
vehicles Manager, Environmental
Manager, Environmental
Officer, Site Engineer, Site Contaminated soil must be collected in drums,
Supervisor transported and disposed off-site by licensed contractor
2 2 4 Yes (treated as scheduled waste, EQA 1974 (SW) 2005
Generation / disposal of Scheduled Land and water contamination Scheduled waste must be collected in proper container,
waste Project Manager, Construction transported and disposed off-site by licensed contractor
Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
2 2 4 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Consumption of raw material and Depletion of non-renewable Project Manager, Construction All construction machineries and vehicles must be
natural resources resources Manager, Environmental properly serviced and maintained to ensure that they are
2 2 4 Yes Manager, Environmental in good working condition.
Officer, Site Engineer, Site
Supervisor
Estimate the right quantity of the resources usage and
consumption
Appendix A
Generation / disposal of Scheduled Land/ ground water contamination Scheduled waste must be collected in proper container,
waste transported and disposed off-site by licensed contractor
Project Manager, Construction
(treated as scheduled waste, EQA 1974 (SW) 2005
Manager, Environmental
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Consumption of natural resources Depletion of non-renewable All construction machineries and vehicles must be
and raw material resources Project Manager, Construction properly serviced and maintained to ensure that they are
2 2 4 Yes Manager, Environmental in good working condition.
Manager, Environmental
Officer, Site Engineer, Site
Supervisor Estimate the right quantity of the resources usage and
consumption
Discharge to land - Silt on road Public/community concern Standby workers for road cleaning and spray water with
surface Project Manager, Construction water bowser lorry
Manager,Environmental
Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Generation of noise Noise pollution, public/community Working within the approved limit hours
3 2 6 Yes
concern Project Manager, Construction
Manager,Environmental Regular inspection and maintenance for vehicles and
Manager, Environmental machineries
Officer, Site Engineer, Site
Supervisor
Appendix A
Discharge to soil -Oil leaking from Land contamination Use manual transfer pump to ensure proper transferring
vehicles of fuel
Generation / disposal of Scheduled Land/ ground water contamination Scheduled waste must be collected in proper container,
waste Project Manager, Construction transported and disposed off-site by licensed contractor
Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
6. Installation of flat Release to air - Release of CO, dust, Reduce air quality – emission of air Project Manager, Construction All construction machineries and vehicles must be
jacks SOX, NOx, PM10 pollutant / dust. Manager, Environmental properly serviced and maintained to ensure that they are
Officer, Site Engineer, Site in good working condition.
5 3 15 Yes Supervisor
All trucks / lorries / machinery shall turn off their engine
during rest or idling time
Generation / disposal of construction Depletion of available landfill Disposed at approved designated dump area.
waste
5 3 15 Yes
Project Manager, Construction
Manager, Environmental
Manager, Environmental
Temporary stockpile at predetermine area.
Officer, Site Engineer, Site
Supervisor
Appendix A
7. Erection of pier Release to air - Release of CO, dust, Reduce air quality – emission of air All construction machineries and vehicles must be
Project Manager, Construction
segment ans SOX, NOx, PM10 pollutant / dust. properly serviced and maintained to ensure that they are
Manager, Environmental
sunsequent segment in good working condition.
Officer, Site Engineer, Site
5 3 15 Yes Supervisor
All trucks / lorries / machinery shall turn off their engine
during rest or idling time
Using of water browser to wet access road to minimize
dust dispersion
Regular inspection and maintenance for vehicles and
machineries
Discharge to water -Oil leaking from Reduce water quality and aquatic Project Manager, Construction All construction machineries and vehicles must be
vehicles habitat – contaminant in term of Manager, Environmental properly serviced and maintained to ensure that they are
sediment, diesel and hydraulic fluid. Officer, Site Engineer, Site in good working condition.
Supervisor
Generation / disposal of Scheduled Land and water contamination Scheduled waste must be collected in proper container,
waste Project Manager, Construction transported and disposed off-site by licensed contractor
Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Appendix A
8. Stressing tendons Release to air - Release of CO, dust, Reduce air quality – emission of air All construction machineries and vehicles must be
Project Manager, Construction
SOX, NOx, PM10 pollutant / dust. properly serviced and maintained to ensure that they are
Manager, Environmental
in good working condition.
Officer, Site Engineer, Site
5 3 15 Yes Supervisor
All trucks / lorries / machinery shall turn off their engine
during rest or idling time
Using of water browser to wet access road to minimize
dust dispersion
Discharge to water -Oil leaking from Reduce water quality and aquatic Project Manager, Construction All construction machineries and vehicles must be
vehicles habitat – contaminant in term of Manager, Environmental properly serviced and maintained to ensure that they are
sediment, diesel and hydraulic fluid. Officer, Site Engineer, Site in good working condition.
Supervisor
Discharge to soil -Oil leaking from Land Pollution/contamination Project Manager, Construction Provide of drip tray to avoid spillage
vehicles Manager, Environmental
3 2 6 Yes Manager, Environmental
Officer, Site Engineer, Site
Supervisor
Appendix A
Generation / disposal of Scheduled Land and water contamination Project Manager, Construction Scheduled waste must be collected in proper container,
waste Manager, Environmental transported and disposed off-site by licensed contractor
3 2 6 Yes Manager, Environmental (treated as scheduled waste, EQA 1974 (SW) 2005
Officer, Site Engineer, Site
Supervisor
Consumption of raw material and Depletion of non-renewable Project Manager, Construction All construction machineries and vehicles must be
natural resources resources Manager, Environmental properly serviced and maintained to ensure that they are
2 2 4 Yes Manager, Environmental in good working condition.
Officer, Site Engineer, Site
Supervisor
Estimate the right quantity of the resources usage and
consumption
Signature
Risk Rating
Rating Significant
1-2 No
3 -25 Yes
MOCK-UP SPAN WORKS Revision: 01
Appendix 5.4
Inspection & Test Plan
AHMAD ZAKI SDN. BHD. ITP for: MOCK-UP SPAN WORKS Date: 04.02.2017
Prior to 1. Approved
1. Project Quality Plan 1. General Specification
1.0 Method Statement commencement of Method H R R
PLN-00008 G4.2.1
work Statement
AHMAD ZAKI SDN. BHD. ITP for: MOCK-UP SPAN WORKS Date: 04.02.2017
• Erection of
During Segment
subsequent
Launching
Segments
1. Construction Drawing 1. Request for
1. Method Statement 2. Material & Workmanship Inspection
• Stressing After Segment H H W
MST-00043 Specification 2. Checklist
Tendons Cl. 232 & Cl. 233 Launching (AZ/CL/MUS)
After stressing
• Monitoring
works
Prior to
• De-tensioning commencement of
works
Appendix 5.5
Quality Control Inspection Forms and
Checklist
Date of Inspection:
Item Description WPC SC PDP
Yes No Yes No Yes No
1 FOOTING FOUNDATION
• Is Plate Bearing Test conducted accordingly?
• Has ground or foundations been prepared as per proposal?
• Does footing size adequate as per proposal?
• Does lean concrete applied as per proposal?
• Is minimum compressive cube strength of 35MPa achieved?
Name/Signature of
Designation: Date:
Works Package Contractor
WPC Representative
Name/Signature of
Designation: Date:
Supervising Consultant
SC Representative
Name/Signature of
Designation: Date:
Works Package Contractor
WPC Representative
Name/Signature of
Designation: Date:
Supervising Consultant
SC Representative
4 STRESSING TENDONS
• Does tendons installed correctly?
• Does stressing works done accordingly?
5 MONITORING
• Does monitoring works done as per required?
6 DE-TENSIONING TENDONS
Is de-tensioning work done properly?
Is safety precaution applied adequately?
Name/Signature of
Works Package Contractor
Designation: Date:
WPC Representative
Name/Signature of
Supervising Consultant
Designation: Date:
SC Representative
QUALITY CONTROL
INSPECTION CHECKLIST
AHMAD ZAKI SDN. BHD.
Project : Projek Mass Rapid Transit Lembah Klang - Jajaran Sungai Buloh - Doc. no. AZ/CL/MUS
Kajang Rev. 00
Date
Construction Process : MOCK-UP SPAN WORKS Page of 2
Reason for Failure/Re-inspection
ALLOWED to proceed with the next stage of work NOT ALLOWED to proceed with the next stage of work
YES NO
Non-Conformance Report Raised NCR no.:
Name/Signature of
Works Package Designation: Date:
Contractor
WPC Representative
Name/Signature of
Designation: Date:
Supervising Consultant
SC Representative
Name/Signature of
Designation: Date:
Project Delivery Partner
PDP Representative
Please off where appropriate
MOCK-UP SPAN WORKS Revision: 01
Appendix 5.6
Flat Jack Info
Appendix 5.7
Stressing Jack & Pressure Gauge
Calibration Certificate
Appendix 5.8
Temporary Footing Foundation Design
Calculation
CALCULATION
FOOTING
OTING FOR MOCK-UP SPAN
AMENDMENT HISTORY