SCHOOL BUDGET
PROJECT PERSON(S) BUDGET
IMPROVEMENT OUTPUT FOR THE YEAR ACTIVITIES SCHEDULE/ VENUE PER
OBJECTIVE RESPONSIBLE SOURCE
PROJECT TITLE ACTIVITY
Project SOLAR Alternate Source of Energy to Met the Teachers Set a meeting with the School Principal, Asst. JAN. 2023 / SHS 500.00 MOOE
attain power stability in the TVL/EIM Teachers involved School Principal, TVL/EIM Faculty Room
Training Implementations Teachers
Organized project team Organize a project team School Principal, Asst. JAN. 2023 / SHS 1000.00 MOOE
School Principal, TVL/EIM Faculty Room
Teachers
Designed electrical schedule of Design the electrical Project Team (i.e. the FEB. 2023 / SHS TVL 1500.00 MOOE / School Fund
loads for the TVL/EIM building schedule of loads for the proponent, ASP-SHS, EIM Laboratory
TVL/EIM building LGU & Brgy. Reps.)
Estimated all materials needed Estimate the materials Project Team MARCH 2023 / SHS 1500.00 MOOE / School Fund
needed Faculty Room
Requested and canvassed all Request and canvass the Project Team APRIL 2023 / SHS 1500.00 MOOE / School Fund
materials needed materials needed Faculty Room; Tac. City
- Hardwares
Purchased all materials needed Purchased the materials Project Team APRIL 2023 / SHS 50000.00 MOOE / School Fund /
needed Faculty Room; Tac. City Solicitations
- Hardwares
Installed SOLAR Power Sytems Install SOLAR Power EIM Trainers, and selected JUNE 2023 / EIM 2000.00 MOOE / School Fund
completely for SHS TVL Sytems project EIM G12 students Laboratory
Laboratory
APPROVED BY:
JEANIA M. TISTON
SCHOOL HEAD, P II