PU_PV_TI_CL_002_007_Cabl

INSPECTION CHECKLIST / TEST FORMAT e IR Test & Hi-Pot Test _Rev


0.0

CABLE IR TEST & HI-POT TEST Dated : 10.06.2021

SCOPE OF APPLICATION : Provisions of this checklist apply to any inspector, BV employee and non-exclusive personnel, engaged in inspections
delivered by Bureau Veritas acting as second-party body performing inspections on behalf of its Client (ref. standard ISO/IEC 17000). This document is
for guideline purpose only and line with the 2nd party inspection provisions of ref. standard ISO/IEC 17000 where client or standard requirements differs
from the content of this Bureau Veritas checklist, then client/standard requirements will take precedence.

Project : Date :

Contractor: Block No:

Work Description: IR Test & Hi-Pot Test Location:

RFI No.:

Ref Drg No:

Cable Size:

SR. NO. DESCRIPTION SPECIFIED VALUE ACTUAL VALUE REMARKS

A Insulation Resistance before Hi-Pot Test >1Gohm


IR of Single Core Cable (Before Hi-pot test):
1
P-E >1Gohm
IR of 3 Core Cable (Before Hi-Pot Test):
R - Y, B & E >1Gohm
2
Y - B, R & E >1Gohm
B - R, B & E >1Gohm
B Hi-Pot test for 11kV/33kV rating cable for 1 minute 11/33 kV withstand
C Insulation Resistance after Hi-Pot Test >1Gohm
IR of Single Core Cable (After Hi-pot test):
1
P-E >1Gohm
IR of 3 Core Cable (After Hi-Pot Test):
R - Y, B & E >1Gohm
2
Y - B, R & E >1Gohm
B - R, B & E >1Gohm

Result of Testing: Satisfactory / Not Satisfactory

Observaton if any: _____________________________________________________

Non Conformities Raised:

Note:
(1) The acceptance of various parameters as above shall be as per relevant instructions & approval from client
(2) Check points shall be updated as per contractually agreed requirements with client / relevant applicable standard requirements

Bureau Veritas Vendor/Contractor


Name: Name:
Signature: Signature:
Date: Date:

DOCUMENT HISTORY Rev 0.0 ReV X.Y


Author: Rajesh Darji
Lei Tian
Reviewer Santanu Das
Frederic Paturet

Page 1 of 2
PU_PV_TI_CL_002_007_Cabl
INSPECTION CHECKLIST / TEST FORMAT e IR Test & Hi-Pot Test _Rev
0.0

CABLE IR TEST & HI-POT TEST Dated : 10.06.2021


Approver : Ulrike Therhaag
Changes: First Issue
Date: 10.06.2021