Braced&Unbraced

H= 4 + 4 + (3 × 9) = 35 𝑚

𝐸 = 4400√𝑓𝑐𝑢 = 4400√30 = 24000 𝑁/𝑚𝑚 2

𝐸 = 24 × 105 𝑡𝑜𝑛/𝑚2
Σ𝐼𝑥 = 11.21 𝑚4
Σ𝐼𝑦 = 19.723 𝑚4

N:
Ground: 𝑭𝒛 = 𝟕𝟖𝟎 𝒕𝒐𝒏 (𝒘𝒐𝒓𝒌𝒊𝒏𝒈)

Basement: 𝑭𝒛 = 𝟏𝟎𝟎𝟎 𝒕𝒐𝒏 (𝒘𝒐𝒓𝒌𝒊𝒏𝒈)

Typical: 𝑭𝒛 = 𝟔𝟔𝟑 𝒕𝒐𝒏 (𝒘𝒐𝒓𝒌𝒊𝒏𝒈)

𝚺𝑵 = 𝟕𝟖𝟎 + 𝟏𝟎𝟎𝟎 + (𝟗 × 𝟔𝟔𝟑) = 𝟕𝟕𝟒𝟕 𝒕𝒐𝒏

𝑵 𝟕𝟕𝟒𝟕
𝜶𝒙 = 𝑯√ = 𝟑𝟓√ = 𝟎. 𝟒𝟒
𝑬𝑰𝒚 𝟐𝟒 × 𝟏𝟎𝟓 × 𝟏𝟗. 𝟕𝟐𝟑

Braced in x-dir

𝑵 𝟕𝟕𝟒𝟕
𝜶𝒚 = 𝑯 √ = 𝟑𝟓√ = 𝟎. 𝟓𝟗
𝑬𝑰𝒙 𝟐𝟒 × 𝟏𝟎𝟓 × 𝟏𝟏. 𝟐𝟏

Braced in y-dir