Jawa 9&10 Coal Fired Steam Power Plant_Design Review Comment Sheet
From : DHI Document Controller
To : IRT Mr. Salam Syah Comment Sheet Document No : J910-YQ02-P0ZEN-140941_CS
Cc : TEPSCO Mr. Kubota Hiroshi
Dwg Title : TYPICAL INSTALLATION DRAWING_CABLE RACEWAY
Dwg No : J910-YQ02-P0ZEN-140941
Purpose : FC
Review Category
A = Approved
B = Approved with comments, forward final document B
C = Not Approved
I = Accepted for reference (For information only)
No. Rev. Sheet/ Page/ Sect. O/E Comments Consortium Response Status
Please equlize item 1-9 with Equipment Numbering
System(KKS) "J910-DA01-P0ZEN-020002 page 20 Item
6.2 Cable Raceway Numbering system Noted.
1 A Sheet 1 of 6 It was modified to match the document number J910-DA01-P0ZEN- CLOSED
No tray iser? 020002.

Noted.
2 A Sheet 1 of 6 Not listed in J910-DA01-P0ZEN-020002 It was modified to match the document number J910-DA01-P0ZEN- CLOSED
020002.
Noted.
Please equlize with Equipment Numbering
3 A Sheet 1 of 6 It was modified to match the document number J910-DA01-P0ZEN- CLOSED
System(KKS)"J910-DA01-P0ZEN-020002
020002.
The application of cable tray cover depend on each installation
4 A Sheet 1 of 6 Please add necessary area according to the condition condition. The application of the cable tray cover per each installation CLOSED
added in detail.
The application of cable tray cover depend on each installation
5 A Sheet 1 of 6 All area of cable tray must be equiped with cover. condition. The application of the cable tray cover per each installation CLOSED
added in detail.
Noted.
I prefer this arrangement but different from the
6 A Sheet 2 of 6 It was modified to match the document number J910-XW01-P0ZEN- CLOSED
document 140005.
140005.

Noted.
Provide edge protecting rubber on the cable raceway
7 A Sheet 2 of 6 The cable is protected by using blind end plate or drop out material CLOSED
ends to protect the cables damage
at the end of cable tray. The detail was added. (Sheet 4 of 6)

and not a single phase cable which forms a three-phase


Except for the main cable route (EDB) section, each conduit connected
8 B Sheet 1 of 6 line shall be installed separately in another conduit for CLOSED
to the equipment (Motro T/B, D/B, etc) is connected separately.
avoiding unexpected heating

The cable tray cover installation is indicated of each of case 1~4,


The cover shall be provided where foreign materials can
9 B Sheet 1 of 6 and Case 2 is included in the application of the cable tray cover on CLOSED
be dropped on the cable tray
the top of the part where foreign material fall.
The cable tray cover installation is indicated of each of case 1~4,
The cover shall be provided for all level, not the
10 B Sheet 1 of 6 and Case 4 is included in the application of the cable tray cover CLOSED
uppormost level only.
preventing coal dust.
In the cable trench, the walkway shall be kept at least The space of the cable trench's walkway is indicated in detail in the
11 B Sheet 2 of 6 CLOSED
600mm. Support type "AH" section. (sheet 3 of 6)

Follow PUIL or page 5 of DESIGN CRITERIA_POWER The general descriptions of “Design Criteria_Power Cable and Cable
12 B Sheet 4 of 6 CABLE & CABLE RACEWAY J910-XW01-P0ZEN-140005 Raceway” and “Typical Installation Drawing _ Cable Raceway” apply CLOSED
the same.

Noted.
13 C Sheet 1 of 6 mention about bonding jumper. CLOSED
It was added in sheet 1,4,5, of 6.

[Self Revsion]
14 0 Sheet 1 of 6 In the cable tray cover of the General Note, the item of Coal Handing CLOSED
Area has been added to Case 4.

[Self Revsion]
15 0 Sheet 6 of 6 CLOSED
The HDPE Conduit Detail to Duct bank installation added.

[Self Revsion]
16 0 Sheet 6 of 6 In the Fixing Method of power cable part, the fixing method of the CLOSED
multi-core cable was modified with a cable tie.

Noted.
To be specific. Especially connecting point of steal pipe
17 1 Sheet 5 of 6 The detail connected between HDPE pipe and steel conduit has been
and PVC or HDPE if you plan to use.
added.

[Self Revsion]
18 1 Sheet 6 of 6 In the Fixing Method of power cable part, the fixing method of the
multi-core cable was modified with a cable tie.