From : DHI Document Controller
To : IRT Mr. Salam Syah Comment Sheet Document No : J910-XA00-P0ZEN-140074_CS
Cc : TEPSCO Mr. Kubota Hiroshi
Dwg Title : ELECTRICAL ROOM LAYOUT DRAWING_CHS JETTY LEB
Dwg No : J910-XA00-P0ZEN-140074
Purpose : FA
Review Category
A = Approved
B = Approved with comments, forward final document
C = Not Approved A
I = Accepted for reference (For information only)
IB = Accepted for reference with comment (For information only)
No. Rev. Sheet/ Page/ Sect. O/E Comments Consortium Response Status
It has been updated.
1 A 1 Add a balcony for installing or exchanging the panels outside of a door. Please refer to GA drawing for detail information. Closed
(J910-UE00-P0UCB-170002)
It is not necessary.
2 A 1 Please write the floor level,and provide the stair if necessary. Please refer to GA drawing for detail information. Closed
(J910-UE00-P0UCB-170002)
Double door is provided for gas bottle exchange.
Clarify the exchanging way of FM200 bombs. Add cross section of this
3 A 1 Please refer to GA drawing for detail information. Closed
building.
(J910-UE00-P0UCB-170002)
4 A 1 EPC shall update information LATER status on KKS Tag no It has been updated. Closed
Single door has been added.
Please provide sufficient emergency exit complying to Exh B-4.2 clause
5 B 1 Please refer to GA drawing for detail information. Closed
3.4.6 Escape and access Routes
(J910-UE00-P0UCB-170002)
Single door has been added.
6 B 1 How about here adding a door based on NFPA101. Please refer to GA drawing for detail information. Closed
(J910-UE00-P0UCB-170002)
<self revision>
7 C 1 Closed
Some panel has been updated as per latest vendor's information.