PNM/22-Hisham

06/10/2022
COMMENTS RESOLUTION SHEET
[ CRS ]

CONTRACT NUMBER GC21104100 CLIENT PROJECT NO. 4311

CONTRACT TITLE EPIC FOR AUTOMATION UPGRADE FOR NGL STORAGE AND LOADING FACILITIES, MESAIEED

CLIENT EXT. TRANSMITTAL REF. PNM/GC21104100/EXT/TN/1590 DATE 10/07/2022

DOCUMENT NUMBER 4311-M2JE-4-53-0001 DOCUMENT REVISION 1

DOCUMENT TITLE INSTRUMENT & F&G CABLE ROUTING LAYOUT - JETTY

previous issued DWG number Last Rev.status Code : 2


made void (if any)

No. CLIENT COMMENTS CONTRACTOR RESPONSE


1 4311-M2JE-4-53-0001-001 Newly added additional JB tag number shall be updated before AFC.
Assign and update Tags for the Cables
2 No implact in this drawing due to site survey, however this drawing shall be
Check whether there will be any impact on this drawing due to OEM further updated based on Loading aram vendor inputs. Hence this drawing is
site survey and reverse engineering. If, there is any impact, then issue as Approved for construction with hold.
indicate in the drawing that OEM site survey and reverse
engineering inputs are on HOLD and issue the drawing for ACH.
3 4311-M2JE-4-53-0001-002 Refer response 1.
Assign and update Tags for the Cables
4 Refer response 2.
Check whether there will be any impact on this drawing due to OEM
site survey and reverse engineering. If, there is any impact, then
indicate in the drawing that OEM site survey and reverse
engineering inputs are on HOLD and issue the drawing for ACH.
5 4311-M2JE-4-53-0001-003 Refer response 1.
Assign and update Tags for the Cables
6 Refer response 2.
Check whether there will be any impact on this drawing due to OEM
site survey and reverse engineering. If, there is any impact, then
indicate in the drawing that OEM site survey and reverse
engineering inputs are on HOLD and issue the drawing for ACH.
7 4311-M2JE-4-53-0001-005 Refer response 1.
Assign and update Tags for the Cables
8 Refer response 2.
Check whether there will be any impact on this drawing due to OEM
site survey and reverse engineering. If, there is any impact, then
indicate in the drawing that OEM site survey and reverse
engineering inputs are on HOLD and issue the drawing for ACH.