PO No . 701220081
Comments Resolution Sheet
Transmittal No.: WQIP-D1-ILF-T-0125 V2
Responsible reviewer: Mushtaq Zaidi/Mohammad Yousaf
Position: Surveyor/ Civil Engineer
Transmittal Date: 8/24/2023
Note: Acceptance does not relieve the contractor from his responsibility and liability concerning compliance with the contract requirement.
No. REV REVIEWER REFERENCE NWC/ILF COMMENT CWC RESOLUTION Code
2200016404-D1-CWC-010GEN-CIV-MS-00531 REVC, METHOD STATEMENT of SITE SURVEY WORKS B
1 ILF MZ Introduction of Project is missing Add at point # 1.0
2 ILF MZ Definition of Project survey Grid detail is missing Add at point # 3.0
3 ILF MZ Scope of work need to be describe in detail Add at point # 3.0
4 ILF MZ Describe ROW limit as per project requirement for site work Add at point # 8.1.1.6
Preparation of drawing detail is missing.
5 ILF MZ/AE Response from contactor is requierd.
open
control points data need to be attach/Polygon Point (PP) set based on the
9 ILF MZ reference points.Secondary bench mark to be shifting in presense of engineer.
Add at point # 8.2.5
Codes:
A - Approved As Submitted
B - Approved Except As Noted Page 1 of 2
C - Disapproved - Resubmit
D - Receipt Acknowledge
NWC Water Quality Improvement Projects
PO No . 701220081
Comments Resolution Sheet
Transmittal No.: WQIP-D1-ILF-T-0125 V2
Responsible reviewer: Mushtaq Zaidi/Mohammad Yousaf
Position: Surveyor/ Civil Engineer
Transmittal Date: 8/24/2023
Note: Acceptance does not relieve the contractor from his responsibility and liability concerning compliance with the contract requirement.
No. REV REVIEWER REFERENCE NWC/ILF COMMENT CWC RESOLUTION Code
Contractor has to make details field survey with staking to the exact alignments
17 ILF MZ of the pipe line to be constructed and excat determination of the location of complied
existing facilities such as crossing of existing facilites.
18 ILF MZ The final ROW of existing and new pipeline to be agreed with NWC/ILF. complied
19 ILF MZ 7.2.5.1 error tolerances need to be describe as per spec. complied
20 ILF MZ 7.2.5.2 need to be describe in detail. complied
21 ILF MY GEN Coordinate system shall be metioned (Datum and Zone) complied
22 ILF MY GEN Any existing utilities during excavation work shall be determined accurately and complied
record to be reflected in Asbuilt drawing
23 ILF MY GEN All calibration certificates for survey instrument shall be submitted for complied
information prior to start the work
24 ILF AE GEN All Appendix should be attached on proper way (typing and printing) Added open
25 ILF AM HSE Comply with PTW requirement of the client Added B
26 ILF AM HSE All the workers on site shall comply with PPE requirements of the site Added B
27 ILF AM HSE Ensure to maintain the good housekeeping at site Added B
28 ILF AM HSE Contractor should follow as mentioned in RA Added B
Codes:
A - Approved As Submitted
B - Approved Except As Noted Page 2 of 2
C - Disapproved - Resubmit
D - Receipt Acknowledge