SUBMITTAL REVIEW COMMENTS

FROM : Project Director, KRBWSP- Stage II, NWSDB


TO : Project Director
DATE :
SUBMITTAL NUMBER : B-001085-DGT-TS-1914 dated 2019.10.24
SUBJECT : Electrical Pull Chamber Drawings
REFERENCE : KRBWSP/S2/TP/

The following are submittal review comments:

Item Specification
Comment
No. Paragraph
_B-001085_REC_CW_000_DN_030 1 FR app

_B-001085_REC_CW_000_DN_030 1 FR Awc
1. Section 1, section 4, section 2, section 5-chequered plates shall be
extended and bend, to cover the plan area of the chamber to minimize
water ingress.
1 2. Handles shall be fixed to side of the cover plate.
3. Necessary modifications shall be carried out to strengthen the
chequered plates.
_B-001085_REC_CW_000_DN_030 1 FR awc

1. Plan of D6-corner rebar detail is incorrect. Please revise the drawing.

APP – Approved.
AWC – Accepted with comments.
REJ – Rejected.