SECOND FLOOR:
EQUIPMENT OUTPUT:
41.48 m2 ÷ 4.08 m2/MH= 11 MH ÷ 4 = 2.75 hrs say 3 hrs of stripping
LABOR
NO. OF
DESIGNATION NO. OF DAYS UNIT RATE AMOUNT
MEN
Site Engineer 1 1 ₱900.00 ₱900.00
Construction Foreman 1 1 ₱700.00 ₱700.00
Laborers 2 1 ₱450.00 ₱900.00
Skilled Workers 2 1 ₱550.00 ₱1,100.00
TOTAL LABOR COST ₱2,790.00
TOTAL DIRECT
₱2,790.00
COST
INDIRECT COST
Overhead, Contingency, Miscellaneous, (2%) ₱55.80
Contractor’s Profit, (7%) ₱195.3
TOTAL CONSTRUCTION COST ₱3,041.10