Professional Documents
Culture Documents
Project Title : Pembangunan Aviation Fuel Hydrant System dan DPPU Kulon Progo
Job Code :
Company : PT. Pertamina (Persero) Date :
Contractor : PT. JGC Indonesia Report No.:
Sub-contractor : BMS-MEG-KSO Sheet :
REFERECES :
Drawing No. : Location :
Revision :
LOCATION OF POURING : ,
REPORT No :
COMPANY :
PCWBS : FWBS :
SUBCONTRACTOR :
DATE & TIME TESTED : See Attached Concrete Compressive Strength Test
PROPORTION TYPE
CEMENT
ABSOLUTE
FINE AGGREGATE
VOLUME (L/m3)
COARSE AGGREGATE
CEMENT
COARSE AGGREGATE
SLUMP (cm)
FRESH CONCRETE
TEST CYLINDER NUMBER See Attached Compressive Strength Test Result ASTM-39
COMPRESSIVE STRENGTH
SPECIMEN
A B C D E AVE
AGE
3 DAYS
TEST
7 DAYS
14 DAYS
28 DAYS
Comments :