Professional Documents
Culture Documents
Payment
Payment
Weighted
Percentage with
Weighted Percentage with
Total Contract respect to the
respect to the Overall Amount Paid Remaining Remaining %
Amount Total Amount
Contract Cost
Paid to the
Contractor
Weighted
Percentage with
Weighted Percentage with
Total Contract respect to the
respect to the Overall Amount Paid Remaining Remaining %
Amount Total Amount
Contract Cost
Paid to the
Contractor
Weighted
Percentage with
Weighted Percentage with
Total Contract respect to the
respect to the Overall Amount Paid Remaining Remaining %
Amount Total Amount
Contract Cost
Paid to the
Contractor
91.754% ₱ 743,122,000.00 93.814% ₱ 681,844,621.92 86.08% ₱ 79,959,927.20 10.09%
₱ 38,054,789.00 4.804% 0.00% ₱ 38,054,789.00 4.80%
₱ 10,950,000.00 1.382% 0.00%
Total ₱ 792,126,789.00 100.000% ₱ 681,844,621.92 86.08% 14.90%
% of the total
Amount Paid by 91.754% ₱ 681,844,621.92
CHD 4A:
Actual Progress of
Original Contract as 89.24% ₱ 663,162,072.80
per CHD 4A:
* The Progress Billing for the Original Contract to be
Difference 2.514% ₱ 18,682,549.12 placed on hold until the contractor's actual site
progress % reached the equivalent paid amount