PROGRAM OF WORKS

1. Name of Project : Installation of Canopy for School Clinic ( L=24 ft ,W=10 ft H=12 ft )
2. Scope of Works : Steel and Masonry Works

3. Name of Office : Langub National High School


4. Address : Brgy. Langub, Escalante City
5. Appropriation : Php 51,300.00
6. Source of Fund : MOOE 2022 4th Quarter (JHS)
7. Date of Implementation : Oct 2022
8. Bill of Materials (Estimates)

ITEM MATERIAL COST LABOR COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO. UNIT COST TOTAL COST UNIT COST TOTAL COST
paint brush pcs 1 1 40.5 0 0.00
paint thinner bottle 1 2 70 0 0.00
Tex screw pcs 200 2 400 0 0.00
Red Lead Paint gal 2 535 1070 0 0.00
GI Pipe 2.5 diameter length 4 2,250.00 9000 0.00 0.00 0.00
GI Sheets 12 ft pcs 8 694 5552 0.00 0.00 0.00
C purlins 2 X 3 length 8 595 4760 0.00 0.00 0.00
Welding Rod kg 8 130 1040 0.00 0.00 0.00
Hollow Blocks pcs 120 18.5 2220 0.00 0.00 0.00
Cement bag 10 260 2600 0.00 0.00 0.00
Gravel cubic meter 1.00 1,700.00 1700 0.00 0.00 0.00
Sand cubic meter 1.00 1,100.00 1100 0.00 0.00 0.00
Deformed Bars 10 mm diameter length 10.00 180 1800 0.00 0.00
G.I Wire kg 2 135.00 270 0.00 0.00 0.00
31,622.50

9. SUMMARY
Description Amount
A. Bill of Materials 31,622.50
B. Labor Cost 17,027.50
10. Total Project Cost 48,650.00

Prepared by: Okay as to allocation: Reviewed by:

LOIDA C. ARO KATHY S. CINCO CLINT S. CINCO


School Princiapl Budget Officer ITO-I/Division PFC, Designate

Recommending Approval: Approved:

MICHELL L. ACOYONG, CESO VI RENATO T. BALLESTEROS, PhD, CESO VI


Assistant Schools Division Superintendent Schools Division Superintendent

You might also like