HAMAD PORT PROJECT 7"
Ref: No. HPP/0085/LT/JEC/2018/0108
Date: 02 January 2018
Al-Jaber Engineering L.L.C
P.O. Box 22801
Doha, Qatar
03 JAN 207
Attention: Mr. Shadi Khashab, P1383
Project Director
NPI
SFSF
Subject: Hamad Port Project (HPP)
NPP/0085: Strategie Food Security Facilities
Method Statement, ITP and Risk Assessment for Piling Works
Dear Mr. Khashab,
We refer to your letter ref. NPP0085-LTR-JEC-NPP-0381. Dated 04 December 2017, regarding the
above subject.
HPP has reviewed the submitted documents and would like to advise the contractor that the submitted
documents cannot be reviewed and approved at this stage due to the following:
1. This method statement, ITP and Risk Assessment should be reviewed based on Pile Design and
Specification which are not developed by the Design Consultant.
2. Item 1.2: List of applicable documents are incomplete. Specification references and Building
code references are missing.
3. Item 1.3: Attach sample copy of hot and cold work permit.
Refer/mention all statutory permit requirements to perform piling operation so that all the
personnel involved in this operation are aware of the requirements and compliance accordingly.
4. Item 2.2: Roles and Responsibilities.
Roles and responsibilities of piling Sub-Contractor personnel are very brief and incomplete.
Please elaborate in consultation with the Piling Sub-Contractor.
Item 4.1: Segregate and list the Main contractor and Piling Sub Contractor manpower
6. Item 4.2: Segregate the equipment arranged /supplied by Main contractor and the Piling Sub
Contractor
7. Ttem 4.3: Add the following in the list
+ Approved concrete spacer
+ Tremie pipe
8. Item 5.1: Health and Safety
+ The HSE provisions are general. Please elaborate specific to the Piling Works.
a
Ph
4974 4406 4444 ‘Hamad Port Project
Fax : 4974 4406 4422 P.O Box: 28333
Doha - QATAR
Page 1 of 3M
12,
13.
14,
15.
16.
7
18,
19.
20.
2.
22.
23.
24,
ee
Fax:
HAMAD PORT PROJECT AT
+ PPE requirements, Information to personnel, site traffic management to be specific to the
Piling Works location and its surrounding areas.
+ Lighting and illumination level statements are for general Construction works. Please be
specific to Piling Work activities.
+ Permits and Certificates: Please add Drilling Rig in the list and attach checklist of the plant
before starting the job.
Item 5.1.1: Emergency Response: Please rewrite with reference to the Piling Work activities
Item 5.2: Environmental Issues: This item to be addressed by the Piling Sub-Contractor
especially related to substantial quantity of mud, slurry and excavated material. Excavated
material and water may contain toxic gases i.e. Hydrogen sulfide etc.
Item 5.2.1: Aspect Identification and Mitigation Measures: Please see comments item 5.2 above
and modify the table accordingly.
Item 6.1: Sequence of Work: The statements are general. Please elaborate the sequence of work
with reference to the piling activities for oil Tanks and Silos et,
Item 6.2(A): Ground Investigation Report: The statements are general.
Before starting the work, the Piling Sub Contractor's Engineer and field staff must be aware of
the ground condition as per the Geotechnical report.
Item 6.2(B): Unexpected Ground Condition: Under such a situation the Contractor shall find the
solution in consultation with the Design Consultant, Geotechnical Specialist, and Piling Sub
contractor.
Item 6.4: Installation tolerances (Setting out, Position, level, Verticality etc. shall be as per the
Piling specification and so far it has not been produced yet.
Item 6.4(F): Forcible correction to pile: Forcible correction to pile shall not be allowed until and
unless itis studied , verified and allowed by the Design Consultant and Piling Sub contractor.
Item 6.5(C): Damage to the Pile: Proposed sequence and timing for driving or boring piles to
be the part of this method statement,
Item 6.6(B): Steel Casing Removal: Stee! casing to be removed before Initial seting time of the
Cement.
Item 6.7(A): Please add the following in 3rd bullet point:
Inno case, the Drilling will be continued below the steel Casing level except Stee! casing reached
the rock level.
tem 6.10(E) Placing of Concrete: sub item (g): Please elaborate the method of concrete vibration
as proposed in this section.
Item 6.11: Testing (A): Concrete Sampling and Testing: Pile and Pile concrete testing plan to be
as per the Pile specification and Concrete specification. So far these are not yet produced
Japproved.
Item 6.11: Testing (B) sub item (2a): Type of testing on pile and frequency of testing to be as
per the approved Pile specification. This document has not been produced yet.
Inspection Test Plan: Activity nos. 2.1, 2.2 & 4.1 to be the Hold Point for PMC.
Activity nos. 3.1, 3.2 & 4.2 to be the Witness Point for PMC
+974 4406 4444 ‘Hamad Port Project
+974 4406 4422 P.O Box: 28333
Doha ~ QATAR
Page 2 of 3HAMAD PORT PROJECT
The contractor is requested to revise the submittal by incorporating / addressing all the above comments
and re submit the Method Statement to the Programme Management Consultant (DORSCH Qatar) for
further review and approval.
This is for your information and further necessary action.
‘Yours faithfully,
Ph
Fax: +974 4406 4422 P.O Box: 28333
Doha- QATAR
974 4406 4444 Hamad Pon Project
Page 3 of 3