Professional Documents
Culture Documents
Do not
Do not leave class Ask ME
Turn your
Arrive on distract or early questions if
cell phone
time annoy your without you are
off
classmates. permission confused.
in advance.
Techniques of Project Management (cont.)
⚫ Network diagram
◦ PERT
◦ CPM
⚫ Bar chart
Outline
⚫ Project Network
◦ Elements of Network (Steps of Network analysis)
◦ Characteristics of PERT and CPM
◦ Events and activities
◦ examples
4
Elements of Network
⚫ How to represent the project graphically?
◦ Divide the project into a number of jobs/tasks (called
ACTIVITIES)
◦ The beginning or end of each activity constitutes an EVENT
of the project.
5
Elements of Network (cont.)
ty event act
t ivi ivit
ac y
activity
event event event
ty
c tivi
ac a
tiv
ity event
6
Elements of Network (cont.)
⚫ To coordinate all of these activities, in developing a
realistic schedule, and then in monitoring the progress of
the project.
◦ Two closely related operations research techniques are widely
used:
● PERT (program evaluation and review technique) and
● CPM (critical path method),
7
Elements of Network (cont.)
⚫ Types of projects used PERT and CPM
◦ Installation of a management information system
◦ Research and development of a new product
◦ NASA space exploration projects
◦ Movie productions
◦ Building ships
◦ Relocation of a major facility
◦ Maintenance of a nuclear reactor
◦…
8
Characteristics of PERT and CPM
⚫ Should have clear jobs/operations
⚫ Definite commencement ﺑدءand completion (events)
⚫ Events and activities should occur in definite pattern
9
Characteristics of PERT and CPM (cont.)
⚫ The activity-on-arc (AOA) project network, where each
activity is represented by an arc. A node is used to
separate an activity (an outgoing arc) 🡪 Activity oriented
1 2 3
10
Characteristics of PERT and CPM (cont.)
⚫ The activity-on-node (AON) project network, where
each activity is represented by a node. Then the arcs are
used just to show the precedence relationships that exist
between the activities. 🡪 Event oriented
A B
11
Characteristics of PERT and CPM (cont.)
⚫ Example
◦ Await delivery of new computers
◦ Remove existing computers
◦ Install power supply
◦ Install new computers
◦ Connect to power
◦ Test
◦ Dispose اﻟﺗﺧﻠصthe old computers
12
Characteristics of PERT and CPM (cont.)
AOA
2 Dispose
t i ng old com
e xis s puters
ove uter
m p
Re com
Install power supply Connect to Test
1 4 5 6
power
Aw
ait de ll ers
live t a t
ry 3 Ins pu
m
co
13
Characteristics of PERT and CPM (cont.)
AON
Remove Dispose
existing old
comput comput
ers ers
Install Connect
start power finish
to Test
supply power
Install
Await
comput
delivery
ers
14
Event
⚫ Is the start or finish of an activity, such as
◦ Design completed
◦ Computer installed
⚫ Should be positive, specific, tangible and meaningful
⚫ Should be definitely distinguishable ﯾﻣﻛن ﺗﻣﯾزھﺎas a specific
point in time
⚫ Should be understood by all concerned with the project
15
Event (cont.)
⚫ Representation
16
Event (cont.)
17
Event (cont.)
Dual Event
18
Event (cont.)
Tail Event
Dual Event
Head Event
19
Activities
⚫ Activity is the actual performance of a task, such as
◦ Install computers
◦ Test
⚫ Represented by simple arrows
⚫ Drawn from left to right
⚫ The length of an arrow does not represent
◦ Magnitude ﺣﺟم- ﻣﻘدارof work
◦ Time for its completion
20
Activities (cont.)
21
Activities (cont.)
22
Activities (cont.)
⚫ Dummy Activities
Those do not require any
time and resources, and just
define dependency among
jobs.
23
Activities (cont.)
⚫ Dummy Activities
◦ Grammatical purpose
24
Activities (cont.)
⚫ Dummy Activities
◦ Logical purpose
25
Take a breath
26
Activities (cont.)
⚫ Rules for provision ﺗوﻓﯾرof dummies (Case 1)
27
Activities (cont.) activity
P
A
predecessor
-
-
Q -
B A
28
Activities (cont.)
⚫ Rules for provision of dummies (Case 3)
29
Activities (cont.)
⚫ Exercise: introduce dummy activities to identify each activity
uniquely
30
Activities (cont.)
⚫ Exercise
31
Network Rules
⚫ The initial node has only outgoing arrows.
⚫ No activity can start until its predecessors are finished.
⚫ An event cannot occur twice.
⚫ Any arrow should represent a single situation.
⚫ We have only one end point.
32
Graphical guidelines for network
⚫ Arrows are not used to indicate time.
⚫ Angle between arrows should be chosen to suit drafting
convenience.
⚫ As far as possible, avoid curved arrows.
33
Graphical guidelines for network (cont.)
⚫ Arrows should not normally cross each other.
34
Examples
35
Examples (cont.)
36
Examples (cont.)
37
Examples (cont.)
38
Examples (cont.)
39
Examples (cont.)
40
Examples (cont.)
Critical Path Method (CPM)
⚫ CPM was developed during the 1950s.
⚫ The focus of CPM is
◦ to determine when a project should be completed, and
◦ to schedule when each activity in the project must begin.
Why:
◦ to keep the project on schedule.
42
CPM (cont.)
⚫ The next step after creating the network is to determine
the earliest time (start and finish) that each activity in the
network can start and finish (forward pass).
2 Dispose
t i ng old com
e xis s puters
ove uter
m p
Re com
Install power supply Connect to Test
1 4 5 6
power
Aw
ait de ll ers
live t a t
ry 3 Ins pu
m
co
43
CPM (cont.)
⚫ Next, we make a backward pass through the network
to determine the latest time that each activity can start
and finish without delaying the completion of the project.
g 2 Dispose
i n old com
x ist puters
e e rs
ov u te
m p
Re com
Install power supply Connect to Test
1 4 5 6
power
Aw
ait de
live s t all ters
ry 3 In p u
m
co
44
Time estimates
⚫
45
Float
⚫
46
Critical Path
⚫ The critical path is the longest path through a project
network
⚫ Any delays in the start or finish times of the activities on
the critical path (also known as critical activities) delay
the completion of the project.
⚫ Project manager should always identify the critical
activities in a project to focus attention on these
activities and to avoid delays on them when possible.
47
Example 1
1. Draw the activity on arc
(AOA) network.
Activity Duration Immediate
2. By using the visual method Predecessor
48
Example 1(cont.)
11
10
2 26
10 C,
A, 8
18 26
1
E,7
0 1 4 5
0 B, 9 0
3 D, 1 19
19
9
9
49
References
50