PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)

BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1

BILL OF QUANTITIES -LIST OF CONTENTS - FACILITIES - LOT 1

SECTION DESCRIPTION REF.

Summary - Summary of BOQ's BFS

Bill 1 - P&G - Preliminary and General Items BF1

Bill 2 - CW (IP) - Civil and Building Works for Intake Pumping Station BF2

Bill 3 - MW (IP) - Mechanical Works for Intake Pump Station BF3

Bill 4 - EW (IP) - Electrical Works for Intake Pump Station BF4

Bill 5 - CW (WT) - Civil and Building Works for Water Treatment Plant BF5

Bill 6 - MW (WT) - Mechanical Works for Water Treatment Plant BF6

Bill 7 - EW WT) - Electrical Works for Water Treatment Plant BF7

LS-BD - Schedule of Breakdown of Lump Sum Price BFLS

Bill - PS - Provisional Sum BFPS

DAYWORKS Daywork Schedule BFDW


PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 SECTION -
SUMMARY
Total
GRAND SUMMARY BILL
REFERENCE Amount
(USD)
Section D - Work Items

Bill 1 General Items BF1 -

Bill 2 Civil and Building Works for Intake PS BF2 1,844,504.36

Bill 3 Mechanical Works for Intake Station BF3 -

Bill 4 Electrical Works for Intake Station BF4 -

Bill 5 Civil and Building Works forWater Treatment Plant BF5 10,327,821.50

Bill 6 Mechanical Works for Water Treatment Plant BF6 -

Bill 7 Electrical Works for Water Treatment Plant BF7 -

(A) Sub-total Bills for Work Items - Lot 1 12,172,325.86

Total for Daywork (Provisional Sum) BFDW 235,365.42

(B) Sub-total for Work Items plus Daywork 12,407,691.28

Part 10 Specified Provisional Sums BFPS -

(C) Total of Work Items plus Daywork plus Provisional Sums 12,407,691.28

(D) Add Provision for Contingency (10% Applied to (C)) 1,240,769.13

(E) Bid Price (C+D) (Carried forward to Form of Bid) - Lot 1 13,648,460.41

(F) Value Added Tax (excluded from all BOQ items)

Bidder's signature:

Bidder's name (printed) :

Bidder's authorized representative,


Page 3/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
BF1. BILL 1 - GENERAL ITEMS

All necessary materials required to perform the work to be provided by


the contractor to the respective sites.

Any contractual or specified requirement not itemized hereunder, shall


deemed to be included in the rates of the other bill items.

Contractual Requirements

BF1. 01 All bonds and guarantees in accordance with the Conditions of Contract ls 1 37,830.00 37,830.00 - -

BF1. 02 All insurance policies in accordance with the Conditions of Contract ls 1 238,649.10 238,649.10 - -

- - -
Specified Requirements: Engineer's and Employer's Facilities - - -
The Contractor shall provide, establish, maintain and remove at
completion of works as described in Specification - - -

Temporary Site Office and Equipment for the Engineer's Staff - - -

BF1. 03 Temporary Site Office Establishment ls 1 44,400.00 - - 44,400.00

BF1. 04 Maintenance mths 361.82 - - -

BF1. 05 Removal ls 1 2,600.00 - - 2,600.00

BF1. 06 Office Equipment for the Engineer's Staff ls 1 13,860.00 - - 13,860.00

Survey equipment, facilities and associated works required as described


BF1. 07 in specification for the project duration. ls 1 58,000.00 - - 58,000.00

- - -

Bidder's Signature or Initials ...........................................


Page 4/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Services for the Engineer's Staff - - -

Bidder's Signature or Initials ...........................................


Page 5/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

BF1. 08 Supply, Maintenance of vehicles supplied to Engineer's staff including mths 48 850.00 - - 40,800.00
fuel and maintenances
Local Area Network with DSL internet connection (minimum 10 mbps
BF1. 09 and router) mths 24 54.55 - - 1,309.20
Set of Initial and Progress Photographs (to cover all major activities ) as
BF1. 10 in specification. mths 24 2,515.91 - - 60,381.84

BF1. 11 Printing, Distribution and Preparation of Record Drawings including mths 24 818.18 - - 19,636.32
shop drawings for the Engineer's approval

BF1. 12 Attendance Upon the Engineer's Staff days 1,056 25.00 - - 26,400.00

- - -

Testing of Materials and Works; to be carried out within or outside


Cambodia by independent Specialist Laboratories as required by - - -
relevant specifications

BF1. 13 Testing of water retaining structures ls 1 30,250.00 - - 30,250.00

All specified testing relating to civil and building works for concrete,
BF1. 14 roads, paving, water retaining structures and any other testing required ls 1 45,000.00 - - 45,000.00
as specified and not listed above.

Pressure testing pipelines in access road, yard piping and process piping
BF1. 15 ls 1 40,666.34 - - 40,666.34
as specified.

BF1. 16 Disinfection and flushing of pipelines after pressure testing ls 1 5,000.00 - - 5,000.00

Factory Inspection/Performance Test for Major Mechanical Equipment


BF1. 17 as specified in the Specifications 15.1.3 ls 1 116,400.00 - - 116,400.00

Bidder's Signature or Initials ...........................................


Page 6/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

Factory Inspection/Performance Test for Major Electrical Equipment as


BF1. 18 specified in the Specifications 16.1.14 ls 1 57,327.00 - - 57,327.00

- - -

Bidder's Signature or Initials ...........................................


Page 7/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Testing of the Works; Plant Installation Testing and Trial Operation - - -

BF1. 19 Rotating equipment checklist and description of test procedures ls 1 2,910.00 - - 2,910.00

BF1. 20 Rotating equipment test report: vibration and alignment check. ls 1 2,910.00 - - 2,910.00

Dry run tests for treatment plant M&E equipment as specified prior to
BF1. 21 start up including services of equipment manufacturers representative ls 1 18,072.32 - - 18,072.32
and test reports.

Dry run tests for Intake Pump Station M&E equipment as specified prior
BF1. 22 to start up including services of equipment manufacturers ls 1 18,072.32 - - 18,072.32
representative and test reports.

Wet run tests on Water Treatment Plant M&E equipment prior to start
BF1. 23 up including services of equipment manufacturers representative and ls 1 35,081.56 - - 35,081.56
test reports.

Wet run tests on Intake Pumping Station M&E equipment prior to start
BF1. 24 up including services of equipment manufacturers representative and ls 1 35,081.56 - - 35,081.56
test reports.

Trial Operation of treatment plant, raw water and treated water


pumping station for acceptance and completion certificate, with
BF1. 25 Commissioning specialist on site full time for all tests on completion ls 1 80,443.63 - - 80,443.63
including 30 days after successfully completing trial operation

BF1. 26 Allow for any other testing required as specified and not listed above ls 1 3,880.00 - - 3,880.00

- - -
Training for BTBWSA staff - - -
Contractor's outline of the training program within 90 days after notice
BF1. 27 to start work. ls 1 1,455.00 - - 1,455.00

Bidder's Signature or Initials ...........................................


Page 8/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

BF1. 28 Course materials, student notes and instruction manuals 30 days prior ls 1 1,940.00 - - 1,940.00
to training

Bidder's Signature or Initials ...........................................


Page 9/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

BF1. 29 Training for instrumentation and control systems operation and days 20 582.00 - - 11,640.00
maintenance

Training for operation and maintenance of pumping station and


BF1. 30 days 15 582.00 - - 8,730.00
treatment plant equipment (Mechanical and Electrical)

BF1. 31 Training for operation of all treatment plant processes during trial days 60 582.00 - - 34,920.00
operation.

BF1. 32 Allow for any other training required as specified and not listed above ls 1 20,370.00 - - 20,370.00

- - -

Temporary Works - - -

BF1. 33 Project Sign Board Establish, Maintenance and Removal ls 1 3,600.00 - - 3,600.00

BF1. 34 Traffic Regulation (management), safety and control as specified days 730 47.00 - - 34,310.00

Protection and Upkeep of Site, adjacent areas and properties , Tidying


and cleaning the site including disposal of construction debris to the
BF1. 35 satisfaction of the Engineer during the construction and on completion mths 24 1,097.72 - - 26,345.28
[including delivery of any remaining pipes, fittings, specials and valves to
the Employer's stores]

BF1. 36 Mobilization and Setup of Piling Equipment for Concrete Pile ls 1 7,500.00 - - 7,500.00

- - -

Specified Requirements: Submittals and Services - - -

Preparing Project Schedule, reports, manuals, submittals and other


BF1. 37 deliverables for meeting as specified ls 1 5,940.00 - - 5,940.00

Bidder's Signature or Initials ...........................................


Page 10/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

Provide adequate Health, Safety and environmental protection and


BF1. 38 safety precautions during construction and preparation of EMPMS, ls 1 29,760.00 - - 29,760.00
implement EMoP and prepare monthly monitoring report

BF1. 39 Preparation of QC/QA and QMS and Compliance with the Quality ls 1 14,400.00 - - 14,400.00
Assurance Standards as specified

BF1. 40 As Built Drawings ls 1 7,860.00 - - 7,860.00

BF1. 41 Operation and Maintenance Manuals ls 1 4,800.00 - - 4,800.00

Allow for any other submittals and services required as specified and
BF1. 42 not listed above ls 1 3,600.00 - - 3,600.00

- - -
Specified Requirements: Personnel - - -

Key Personnel who meet the requirement in the qualification criteria


and other cost for personnel for engineers and surveyors except the
BF1. 43 foreman and labors which are included in the cost of the works. Bidder - - -
shall specify the months of each personnel to be assigned according to
his construction schedule except Project Manager.

BF1. 44 Project Manager mths 24 19,400.00 - - 465,600.00

BF1. 45 Site Engineer: civil works mths 24 16,975.00 - - 407,400.00

BF1. 46 Site Engineer: mechanical works mths 8 16,975.00 - - 135,800.00

BF1. 47 Site Engineer: electrical works mths 8 16,975.00 - - 135,800.00

BF1. 48 Pump engineer mths 4 13,580.00 - - 54,320.00

BF1. 49 Water treatment process engineer mths 4 13,580.00 - - 54,320.00

Bidder's Signature or Initials ...........................................


Page 11/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
BF1. 50 Electrical engineer mths 4 13,580.00 - - 54,320.00

Bidder's Signature or Initials ...........................................


Page 12/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 1 - PRELIMINARIES AND GENERAL BILL - 1

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
BF1. 51 Health and safety officer mths 24 15,520.00 - - 372,480.00

BF1. 52 Quality assurance engineer mths 24 15,520.00 - - 372,480.00

BF1. 53 Commissioning Specialist mths 2 15,520.00 - - 31,040.00

BF1. 54 Other Engineers and Surveyors ls 1 35,075.20 - - 35,075.20

- - -
Subtotal for Bill 1, CARRIED TO GRAND SUMMARY 276,479 - 3,094,287.58

Bidder's Signature or Initials ...........................................


Page 13/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) PRELIMINARIES & GENERAL BILL- 1
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
BF1. BILL 1 - GENERAL ITEMS
All necessary materials required to perform the work to be provided by
the contractor to the respective sites.

Any contractual or specified requirement not itemized hereunder, shall


deemed to be included in the rates of the other bill items.

Preliminary studies

Civil and structural engineering and other necessary studies to adapt the
project with functional modifications. This price includes especially
BF1. 01 calculations and shop drawings. ls 1 -
Calculation per Lump Sum.

Allow for preliminary survey including excavations and remote sensing of


BF1. 02 underground facilities before carrying out the works where not ls 1 -
specifically indicated elsewhere in these bills of quantities

Mobilization and Demobilization

BF1. 03 Mobilization including Transport of Materials ls 1 -


BF1. 04 Supply and shipment of plant ls 1 -

BF1. 05 Establishment, dis-establishment and clean up of site, including solid ls 1 -


waste management.
BF1. 06 Demobilization ls 1 -
Contractual Requirements -
BF1. 07 All bonds and guarantees in accordance with the Conditions of Contract ls 1 -

BF1. 08 All insurance policies in accordance with the Conditions of Contract ls 1 -

Specified Requirements: Engineer's and Employer's Facilities


The Contractor shall provide, establish, maintain and remove at
completion of works as described in Specification
Temporary Site Office and Equipment for the Engineer's Staff
BF1. 09 Temporary Site Office Establishment ls 1 -
BF1. 10 Maintenance mon 24 -
BF1. 11 Removal ls 1 -
BF1. 12 Office Equipment for the Engineer's Staff ls 1 -
Survey equipment, facilities and associated works required as described
BF1. 13 in specification for the project duration. ls 1 -

Services for the Engineer's Staff

BF1. 14 Supply and Maintenance of vehicles supplied to Engineer's staff including veh- 48 -
fuel mon

BF1. 15 Local Area Network with DSL internet connection (minimum 2mbps and mon 24 -
router)
Set of Initial and Progress Photographs (to cover all major activities and
BF1. 16 including monthly drone photos ) as in specification. mon 24 -

BF1. 17 Attendance Upon the Engineer's Staff d 1,056 -

BF1. 18 Printing, Distribution and Preparation of shop drawings for the ls 1 -


Engineer's approval

BF1. 19 Printing, Distribution and Preparation of Record (As-built) Drawings for ls 1 -


the Engineer's approval
Testing of Materials and Works; to be carried out within or outside
Cambodia by independent Specialist Laboratories as required by
relevant specifications

BF1. 20 Testing of water retaining structures ls 1 -


All specified testing relating to civil and building works for concrete,
BF1. 21 roads, paving, water retaining structures and any other testing required ls 1 -
as specified and not listed above.
Pressure testing pipelines in access road, yard piping and process piping
BF1. 22 as specified. ls 1 -

BF1. 23 Disinfection and flushing of pipelines after pressure testing ls 1 -

Bidder's Signature or Initials ...........................................


Page 14/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) PRELIMINARIES & GENERAL BILL- 1
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Factory Inspection/Performance Test for Major Mechanical Equipment as


BF1. 24 specified in the Specifications 15.1.3 ls 1 -

BF1. 25 Factory Inspection/Performance Test for Major Electrical Equipment as ls 1 -


specified in the Specifications 16.1.14

Testing required by the Engineer not covered by the specifications

BF1. 26 Compacted backfill - Field Density Test - MDD 95% nr 24 -

BF1. 27 Compacted backfill - CBR nr. 24 -

Testing of the Works; Plant Installation Testing and Trial Operation

BF1. 28 Rotating equipment checklist and description of test procedures ls 1 -

BF1. 29 Rotating equipment test report: vibration and alignment check. ls 1 -

Dry run tests for treatment plant M&E equipment as specified prior to
BF1. 30 start up including services of equipment manufacturers representative ls 1 -
and test reports.

Dry run tests for Intake Pump Station M&E equipment as specified prior
BF1. 31 to start up including services of equipment manufacturers representative ls 1 -
and test reports.

Wet run tests on Water Treatment Plant M&E equipment prior to start
BF1. 32 up including services of equipment manufacturers representative and ls 1 -
test reports.

Wet run tests on Intake Pumping Station M&E equipment prior to start
BF1. 33 up including services of equipment manufacturers representative and ls 1 -
test reports.

Trial Operation of treatment plant, raw water and treated water


BF1. 34 pumping station for acceptance and completion certificate, with ls 1 -
Commissioning specialist on site full time for all tests on completion
including 30 days after successfully completing trial operation

BF1. 35 Allow for any other testing required as specified and not listed above ls 1 -

Training for BTBWSA staff

Trainings: manuals will be supplied in Khmer and English language.

Trainings will be as specified and include 35 workdays of ‘on the job


training’ for raw water intake and WTP operation.

BF1. 36 Contractor's outline of the training program within 90 days after notice ls 1 -
to start work.
Course materials, student notes and instruction manuals 30 days prior to
BF1. 37 training ls 1 -

BF1. 38 Training for instrumentation and control systems operation and ls 1 -


maintenance

BF1. 39 Training for operation and maintenance of pumping station and ls 1 -


treatment plant equipment (Mechanical and Electrical)
Training for operation of all treatment plant processes during trial
BF1. 40 operation. ls 1 -

BF1. 41 Allow for any other training required as specified and not listed above ls 1 -

Temporary Works -
BF1. 42 Project Sign Board Establishment nr 1 -
BF1. 43 Maintenance mon 24 -
BF1. 44 Removal nr 1 -
BF1. 45 Traffic Regulation (management), safety and control as specified days 720 -
BF1. 46 Site Fencing including Relocation as specified mon 24 -

Bidder's Signature or Initials ...........................................


Page 15/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) PRELIMINARIES & GENERAL BILL- 1
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Protection and Upkeep of Site, adjacent areas and properties , Tidying


and cleaning the site including disposal of construction debris to the
BF1. 47 satisfaction of the Engineer during the construction and on completion mon 24 -
[including delivery of any remaining pipes, fittings, specials and valves to
the Employer's stores]

Specified Requirements: Submittals and Services


Preparing Project Schedule, reports, manuals, submittals and other
BF1. 48 deliverables for meeting as specified ls 1 -

Provide adequate Health, Safety and environmental protection and


BF1. 49 safety precautions, particularly taking account of COVID-19 requirements ls 1 -
in the SCC, during construction and preparation of HSP and CEMP,
implement EMoP and prepare monthly monitoring report

BF1. 50 Preparation of QC/QA and QMS and Compliance with the Quality ls 1 -
Assurance Standards as specified
BF1. 51 As Built Drawings ls 1 -

Recording of (GIS) coordinates of all installed pipelines and assets


BF1. 52 (including facilities, fences and boundaries), including valves, hydrants, ls 1 -
manholes etc. and submission of all data in readable and editable format to
BTBWS/MISTI

BF1. 53 Allow for any other submittals and services required as specified and not ls 1 -
listed above
BF1. 54 Project Plaque ls 1 -
BF1. 55 Architectural Model of WTP and Intake PS building ls 1 -

Specified Requirements: Personnel

Costs for Key Personnel who meet the requirement in the qualification
criteria plus costs for other personnel, engineers and surveyors with the
exception of the foreman and labourers who are included in the cost of
the works.
Bidder shall specify the person months of each professional (with the
exception of the Project Manager) to be assigned according to the
construction schedule.

BF1. 56 Project Manager mon 24 -


BF1. 57 Site Engineer: civil works mon 24 -
BF1. 58 Site Engineer: mechanical works mon 8 -
BF1. 59 Site Engineer: electrical works mon 8 -
BF1. 60 Pump engineer mon 4 -
BF1. 61 Water treatment process engineer mon 4 -
BF1. 62 Electrical engineer mon 4 -
BF1. 63 Health and Safety officer mon 24 -
BF1. 64 Environmental Safeguards Officer mon 24 -
BF1. 65 Quality assurance engineer mon 24 -
BF1. 66 Commissioning Specialist mon 2 -
BF1. 67 Other Engineers and Surveyors ls 1 -

Specified Requirements: Environmental Monitoring and Management

The Contractor will comply with requirements of the Environmental


Management Plan included in Volume 5 of the Bid Documents as well as
all Environmental requirements covered elsewhere in the Contract
Documemts

BF1. 68 Replacement of trees - not covered elsewhere ls 1 -


BF1. 69 Environmental Specialist mon 24 -
BF1. 70 Environmental Baseline Monitoring and Testing mon 24 -
BF1. 71 Environmental Training ls 1 -
BF1. 72 Miscellaneous costs to meet environmental requirements ls 1 -

Specified Requirements: Miscellaneous

BF1. 73 Miscellaneous costs to meet General and Preliminary requirements not ls 1 -


covered elsewhere in this Bill

Subtotal for Part 1, CARRIED TO GRAND SUMMARY -

Bidder's Signature or Initials ...........................................


Page 16/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF2. BILL 2 – INTAKE PUMPING STATION

Bill 2-1 – Raw Water Intake

Demolition and Site Clearance


General clearance Demolition and removal of all
articles, objects and obstructions
which are required to be cleared
BF2. 01 except the trees with diameter > ha 0.19 9,600.00 1,830.72
200mm

Trees Clearing and Grubbing


BF2. 02 Diameter >200 mm nr 50 50.00 2,500.00

Tree planting replacement of cleared trees (4 per 1 cleared tree)


BF2. 03 nr 200 40.00 8,000.00

Earthwork
Excavation by dredging Materials other than topsoil, rock or
BF2. 04 artificial hard materials m3 1,000 5.50 5,500.00

General excavation Materials other than topsoil, rock or


BF2. 05 artificial hard materials m3 3,918 5.50 21,549.00

Excavation of Topsoil Topsoil including transportation to


temporary storage and storage for
BF2. 06 re-use and landscaping m3 1,000 5.50 5,500.00

Backfill including compaction in Selected material (without organic


layers to 95% MDD as specified matter, etc.)
BF2. 07 m3 553 16.80 9,290.40

Backfill including compaction in Well graded sand as specified or


layers to 95% MDD as specified instructed by the Engineer
BF2. 08 m3 1,000 40.00 40,000.00

Disposal of excavated material Materials other than topsoil, rock or


BF2. 09 artificial hard materials m3 3,000 3.50 10,500.00

Compacted base course Below concrete structure


BF2. 10 approximately 400mm thick m3 130 43.00 5,590.00

Surface shaping (landside)


BF2. 11 m2 2,000 2.50 5,000.00

Concrete

Bidder's Signature or Initials ...........................................


Page 17/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Includes supply and provision of concrete, casting work and ancillary
materials, formworks, scaffolding, support and ancillary materials
including joints, water stop, and tie-bars which is specified in the
drawings and/or required for construction to comply with
specifications.

15Mpa
Concrete blinding layer 100mm
BF2. 12 thick m3 40 150.00 6,000.00

Base concrete 30Mpa


for concrete block retaining wall shown on drawings of IPS siteworks
BF2. 13 and stone masonry wall and retaining walls m3 48 160.00 7,680.00

Backfill concrete 30Mpa


for concrete block retaining wall shown on drawings of IPS siteworks
BF2. 14 and stone masonry wall and retaining walls m3 302 160.00 48,320.00

Top concrete 30Mpa


for concrete block retaining wall shown on drawings of IPS siteworks
BF2. 15 and stone masonry wall and retaining walls m3 47 260.00 12,220.00

Concrete in partition walls for 30Mpa


concrete block retaining wall and shown on drawings of IPS siteworks
BF2. 16 stone masonry wall and retaining walls m3 101 260.00 26,260.00

Concrete for sheet pile copings 37Mpa


shown on drawings of IPS siteworks
BF2. 17 and retaining walls m3 32 260.00 8,320.00

Concrete for inverted T wall 37Mpa


shown on drawings of IPS siteworks
BF2. 18 and retaining walls m3 46 260.00 11,960.00

Concrete for gravity wall 37Mpa


shown on drawings of IPS siteworks
BF2. 19 and retaining walls m3 384 260.00 99,840.00

Bidder's Signature or Initials ...........................................


Page 18/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Concrete for stair 37Mpa
shown on drawings of IPS siteworks
BF2. 20 and retaining walls m3 29 280.00 8,120.00

Concrete for trash fence anchor 30Mpa


foundation shown on drawings of IPS siteworks
BF2. 21 and retaining walls m3 7 160.00 1,120.00

Lean concrete 30Mpa


shown on drawings of IPS siteworks
BF2. 22 and retaining walls m3 65 150.00 9,750.00

Concrete Ancillaries
-
Reinforcement Deformed Bar, shown on drawings
of IPS siteworks and retaining walls
BF2. 23 t 150 1,390.00 208,500.00

Anchor bars for concrete Deformed High Yield Stressed Bar,


structure 390MPa
BF2. 24 kg 76 2.00 152.00

Joint for revetment Water Stop, filler and sealant as


specified in particular spec P13.2.6
BF2. 25 and P13.2.8 nr 15 30.00 450.00

External waterproofing of bitumen coating


Pumping Station below ground
BF2. 26 level m2 800 21.00 16,800.00

Piles

Steel sheet piling as required (and approved by the Engineer) for


temporary works to form coffer dam to enable construction of the
inlet works including intake PS, including supply of materials, driving
and installation with ancillaries, tie rods, ring joints, turnbuckles and
nuts, all in accordance with specification.
BF2. 27 Measured as horizontal meter length of coffer dam. m 162 28.80 4,665.60

Riprap Class A
as specified and shown on drawings
BF2. 28 of intake works m3 100.0 50.00 5,000.00

Blockwork and Masonry Supply and construct

Grouted riprap Class A


BF2. 29 as specified and shown on drawings 714 100.00 71,400.00
of intake works m3

Precast concrete block retaining as specified and shown on drawings


BF2. 30 wall of intake works m2 156 51.84 8,087.04
River Bank Protection Supply and Install

Gravel backfill as specified and shown on drawings


BF2. 31 of intake works m3 424 43.00 18,232.00

Filter cloth as specified and shown on drawings


BF2. 32 of intake works m2 17 6.00 102.00

Stone masonry wall as specified and shown on drawings


BF2. 33 of intake works m2 2,218 75.00 166,350.00

Vegetation mattress as specified and shown on drawings


BF2. 34 of intake works m2 782 10.00 7,820.00

Bidder's Signature or Initials ...........................................


Page 19/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
PVC pipe for weep holes for all pvc φ50mm, supply and installation
masonry and retaining wall
BF2. 35 m 1,620 15.00 24,300.00

Supply and Installation


Including , Nylon Rope,
Polyethylene and Styrofoam
Floating, Polyethylene Net and
BF2. 36 Floating trash fence miscellaneous materials shown on nr 1 15,840.00 15,840.00
drawing No. C-OP-O-008

BF2. 37 Rubber Fender, 400H x 1000L Supply and Installation Including bolt nr 11 1,396.80 15,364.80
etc. for mounting to the revement

Bidder's Signature or Initials ...........................................


Page 20/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 2-2 – Intake Pump Station


Earthwork

Excavation Materials other than topsoil, rock or


BF2. 38 artificial hard materials m3 4,000 15.00 60,000.00

Excavation of Topsoil Topsoil including transportation to


temporary storage and storage for
BF2. 39 re-use and landscaping m3 500 8.00 4,000.00

Excavation in Rock Excavation in rock where SPT N


BF2. 40 value greater than 50 m3 1,000 30.00 30,000.00

Backfill Materials other than topsoil, rock or


BF2. 41 artificial hard materials m3 1,000 38.00 38,000.00

Cement stabilization of soil As instructed by the Engineer


BF2. 42 m3 500 40.00 20,000.00
Truck loading, transportation and for all related earth works for Intake
BF2. 43 disposal of excavated material off Pump Station m3 3,000 8.00 24,000.00
site

Compacted base course Below concrete structure


BF2. 44 approximately 400mm thick m3 110 43.00 4,730.00

Ground cover, t=150mm for access


to Intake PS including compaction
BF2. 45 Basecourse filling and paving to 95% MDD as specification - m2 1,000 6.00 6,000.00
Section 2.5
Class F&G, In situ Concrete and Concrete Ancillaries

Reinforcement includes supply and provision of re-bars, processing as


specified and shown in the drawings.

o Reinforcement Strength of Rebar 390MPa t 103.6 1,390.00 144,004.00

Includes supply and provision of concrete, casting work and ancillary


materials, formworks and ancillary materials including joints, water
stops, and tie-bars which is specified in the drawings and/or required
for construction to comply with specification.

Concrete blinding layer 100mm 15MPa


BF2. 46 thick m3 30 150.00 4,500.00

BF2. 47 Concrete for roof slab 37MPa m3 56.4 280.00 15,792.00

BF2. 48 Concrete for middle slab 37MPa m3 286 280.00 80,080.00

BF2. 49 Concrete for bottom slab 37MPa m3 670 160.00 107,200.00

Bidder's Signature or Initials ...........................................


Page 21/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF2. 50 Concrete for wall 37MPa m3 677 260.00 176,020.00

BF2. 51 Concrete for beam and column 37MPa m3 55.9 280.00 15,652.00

BF2. 52 Concrete for pipe protection 37MPa m3 14.6 160.00 2,336.00

BF2. 53 Concrete for stair 37MPa m3 24.9 280.00 6,972.00

BF2. 54 Concrete for stage 37MPa m3 5.6 280.00 1,568.00

BF2. 55 Concrete for intake mouth 37MPa m3 16.2 280.00 4,536.00

BF2. 56 Concrete for electric duct 30MPa m3 8.1 160.00 1,296.00

BF2. 57 Concrete for maintenance stage 37MPa m3 8.7 280.00 2,436.00


Concrete for stair to intake
BF2. 58 mouth 30MPa m3 3.6 280.00 1,008.00

BF2. 59 Concrete for plain concrete & 30MPa m3 94 160.00 15,040.00


cinder concrete
BF2. 60 Lean concrete 15Mpa m3 48 150.00 7,200.00
Hollow Brick 220mm, 180mm two
BF2. 61 Outer walls layers and 20mm mortar rendering m2 350 40.00 14,000.00
for both sides
Hollow Brick 120mm, 80mm single
BF2. 62 Inner walls layer and 20mm mortar rendering m2 136 30.00 4,080.00
for both sides
Pipework - Supports and Protection, Ancillaries to Laying and Excavation

Includes labour and equipment for installation and jointing work,


scaffolding equipment and labour and miscellaneous materials for
installation, welding and protection of welded joint as specified.

All internal pipework and fittings for the intake PS and the Sediment
pump well including boxouts, supports and building in pipes to
BF2. 63 complete the works shown on the drawings and as specified not ls 1 -
included elsewhere

Bidder's Signature or Initials ...........................................


Page 22/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Structural Metalwork

Supply and Install doors, louvres and windows as shown on the


drawings and specified
BF2. 66 Rolling shutter W x H = 4500 x 4690 nr 1 2,880.00 2,880.00

BF2. 67 Rolling shutter W x H = 1000 x 2300, nr 1 936.00 936.00


steel soundproof door
BF2. 68 Plastic door W x H = 760 x 2035 nr 1 158.40 158.40

BF2. 69 Sliding window W x H = 1870 x 1325 nr 1 288.00 288.00

BF2. 70 Sliding window W x H = 1270 x 1325 nr 1 273.60 273.60

BF2. 71 Security grill for window W x H = 1880 x 1325 nr 1 208.80 208.80

BF2. 72 Security grill for window W x H = 1280 x 1325 nr 1 144.00 144.00

BF2. 73 Vent brick W x H = 415 x 415 nr 1 14.40 14.40

BF2. 74 Concrete louver W x H = 800 x 1800 nr 1 144.00 144.00


Miscellaneous Metalwork

Supply and Installation including welding and jointing work, painting


as specified.
BF2. 75 Bar screen 2.0 x 2.84m x 60° nr 2 86.40 172.80

BF2. 76 Step iron with polypropylene W=300mm with fall arrest cage nr 50 21.60 1,080.00
coatings
Circle fall arrest cage for iron
BF2. 77 steps D=800mm m 12 14.40 172.80

BF2. 78 Stainless Steel stair and platforms as outlined in drawings ls 1 2,160.00 2,160.00

Bidder's Signature or Initials ...........................................


Page 23/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Stainless steel multi-stage vertical ladder with platforms, railing, safety
BF2. 79 hoops and safety chains in pump forbay, as shown on drawing B-IW- ls 1 5,400.00 5,400.00
PS/PW-C-GA-XS-014, etc.

BF2. 80 Ceiling hook for lubrication pump 50kg, nr 1 288.00 288.00

BF2. 81 Ceiling hook for electric panel 500kg, nr 19 36.00 684.00


Gratings and metal flooring including frames as specified and shown
BF2. 82 ls 1 1,800.00 1,800.00
on the drawings
Cinder Concrete for Intake Pump 30MPa
BF2. 83 Station m3 44 160.00 7,040.00
Thrust Block work including 30MPa
BF2. 84 formwork and scaffolding m3 4 160.00 640.00
Supply and Installation of Catwalk and Stairs
BF2. 85 ls 1 10,800.00 10,800.00
Painting

Including all materials, labour and incidentals.

BF2. 86 Floor tile Including bedding mortar m2 200 30.00 6,000.00

BF2. 87 Mortar Wall m2 300 8.00 2,400.00

BF2. 88 Watertight mortar Roof m2 200 12.00 2,400.00

BF2. 89 Emulsion paint on cement mortar m2 200 5.50 1,100.00

BF2. 90 Steel trowel finish by cement 100 10.00 1,000.00


mortar m2
Waterproofing

Watertight asphalt roof


BF2. 91 Roof m2 240 15.00 3,600.00
Simple Building Works Incidental to Civil Engineering Works

Handrail
BF2. 92 H=1.1m (level) SS304 m 3 65.00 195.00
Handrail for step
BF2. 93 H=1.1m (inclined) SS304 m 7 65.00 455.00

Bidder's Signature or Initials ...........................................


Page 24/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 2 - CIVIL WORKS FOR INTAKE BILL - 2
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 PUMPING STATION

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Roof drain
BF2. 94 φ75mm nr 4 45.00 180.00
Downpipe
BF2. 95 VP75 m 10 15.00 150.00
Construction of Guard House, Fencing and Main/ Side Gates
including general preparation, formwork, re-bar arrangement,
concrete, interior and exterior finishing for all floors, walls, bases and
ceilings, roofing, windows, doors, shutters, shelves, supply and
installation of Main gate and side gate, Nameplate Panel with
BF2. 96 BTBWSA logo, and other miscellaneous equipment specified in the ls 1 22,968.00 22,968.00
Drawings and Specifications

Other miscellaneous items that are specified or shown on the


drawings or that the Contractor may deem necessary to complete the
BF2. 97 works in fencing and gates ls 1 1,440.00 1,440.00

Stop logs for 2m x 2m opening on each intake channel as specified


BF2. 98 and shown on the Drawings nr 2 432.00 864.00
Mechanical Work

Supply, installation and testing.

Sluice gate 2.0m x 2.0m


BF2. 99 nr 4 11,520.00 46,080.00
Travelling rail for crane I-450x175x11x20, Travel length = 16
m, supply and installation
BF2. 100 nr 1 1,800.00 1,800.00

Electrical Work

Building electrical works for Pump Station including distribution


panels, cables and termination, conduit and fittings, lighting fixtures,
switches, internet and telephone systems, sound system, earthing
BF2. 101 protection systems and other miscellaneous equipment specified in ls 1 8,640.00 8,640.00
the Drawings.

Lightning Protection System supply and installation


BF2. 102 ls 1 1,584.00 1,584.00

Sub-total forBill 2, CARRIED TO GRAND SUMMARY 1,844,504.36

Bidder's Signature or Initials ...........................................


Page 25/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 3 - MECHANICAL WORKS FOR
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 INTAKE PUMPING STATION BILL-3

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF3. BILL 3 – MECHANICAL WORK FOR INTAKE PUMP STATION


3.1 Pumps (including supply and installation with all electrical
connections, mounting and adjustment).

Submersible Pump with cooling jacket in a dry pit set up , 356l/sec


x19.4m, with motors >100kW, with full sensor option on pump motor,
BF3. 01 20 meter of power cable and sensor cables, mounting plate, lifting chain nr 3 -
and chain supports.

Spare parts for main intake pumps for each pump ( bearings, seals,
BF3. 02 sensor set , O ring set) nr 3 -

Drain sump pumps @ drain Intake pit 10l/sec x15m, with motors
BF3. 03 >5.5kW, fixed installation nr 2 -

BF3. 04 Spare Drain sump pump as above (supply only) nr 1 -


Sedimentation sump pumps @ intake sedimentation basin 8.2l/sec
x10m, with motors >3.7kW, inclusive pedestal, guiderail and supports,
BF3. 05 lifting chain nr 2 -

BF3. 06 Spare sedimentation pump as above (supply only) nr 1 -


3.2 Cranes and Hoists (supply and install complete)
Station Crane, Overhead crane movable on an I beam moving by means
of a trolly, 6 ton capacity inclusive of electrical power cable including
BF3. 07 controls and accessories nr 1 -

Manual chain hoist and accessories for sedimentation pumps


BF3. 08 ls 1 -
3.3 Pipes, Valves, Ventilation Fans and Miscellaneous (Supply and
install) -
Intake ventilation fan, wall mounted, axial flow type 1000m3/h @ 2300
BF3. 09 Pa, inclusive of back draft shutters nr 2 -

Discharge ventilation fan - wall mounted, axial flow type 1000m3/h @


BF3. 10 2300 Pa, inclusive of back draft shutters nr 1 -

Pump inlet pipe , Raw water, from inlet well to pump, SP, ND450 mm
BF3. 11 nr 3 -

Pump discharge pipe , Raw water, from pump to header pipe, SP,
BF3. 12 ND300 mm nr 3 -

Flanged Eccentric Reducer for inlet pipe 450mm to 300mm dia


BF3. 13 nr 3 -

Pump discharge pipe, Raw water, header pipe in the pump room, SP,
BF3. 14 ND700 mm nr 1 -

Drainage pipe, Sand drainage pipe in the pump room, SSP, ND100 mm
BF3. 15 nr 1 -

Drainage pipe, Floor drainage pipe in the pump room, SSP, ND50 mm
BF3. 16 m 30 -

Lubrication pipe, Lubrication pipe to auto strainers, GSP, ND50 mm


BF3. 17 nr 1 -

Lubrication pipe, Lubrication pipe from auto strainers to intake pumps,


BF3. 18 GSP, ND32 mm, ND50 mm nr 1 -

Bidder's Signature or Initials ...........................................


Page 26/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 3 - MECHANICAL WORKS FOR
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 INTAKE PUMPING STATION BILL-3

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Pump inlet , ND450 mm, knife valve for water
BF3. 19 nr 3 -

Pump discharge check valves, ND300 mm, swing check valve


BF3. 20 nr 3 -

Pump discharge , ND300 mm, knife valve for water


BF3. 21 nr 3 -

Transmission flow control, ND700 mm, toothed vane disc butterfly valve
BF3. 22 nr 1 -

Air valves for header pipe, ND80 mm high speed air valve
BF3. 23 nr 3 -

Air valves for vertical shaft pipe, ND100 mm high speed air valve
BF3. 24 nr 3 -

Air valves isolation for header pipe, ND80 mm, knife valve
BF3. 25 nr 3 -

Air valves isolation, ND100 mm, knife valve


BF3. 26 nr 3 -

Sand drainage pump discharge checks, ND100 mm, swing check valve
BF3. 27 nr 1 -

Pipes, Fittings, Valves and miscellaneous work specified in the Drawings


BF3. 28 and the Specifications and not included in Bill 3 ls 1 -

Supply and Installation of Fire extinguishers CO2 type 9 KG inclusive


BF3. 29 with wall mounting hooks and signage nr 8 -

Supply and Electrical Room (Ground Floor)


Installation of
BF3. 30 Checker Plate nr 1 -
(No.1)

Supply and Intake Pumps (walkway beside pumps for access)


Installation of
BF3. 31 Checker Plate nr 1 -
(No.2)

Supply and Sand Drainage Pump (2 no.)


Installation of
BF3. 32 Checker Plate nr 1 -
(No.3)

Supply and Hinged Manhole Cover light duty (for access to the
Installation of wet well stairs)
BF3. 33 Manhole cover nr 1 -
(No.4)

Supply and Intake Pumps Opening in Electrical Room


Installation of
Stainless Steel
Fence and Railing
BF3. 34 including chain nr 1 -
link gateway

Sub-total for Bill 3, CARRIED TO GRAND SUMMARY -

Bidder's Signature or Initials ...........................................


Page 27/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 4 - ELECTRICAL WORKS FOR
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 INTAKE PUMPING STATION BILL - 4

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF4. BILL 4 – ELECTRICAL WORKS FOR INTAKE PUMP STATION

All items are supply and install including ancillaries.

Panel boards and motor control centres as per one line diagrams

pole panel
BF4. 01 nr 1 -

ATS/MDB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF4. 02 description and schematics nr 1 -

System control panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF4. 03 description and schematics. nr 1 -

Pump control panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF4. 04 description and schematics nr 3 -

sump pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF4. 05 description and schematics nr 1 -

sediment system panel inclusive of all switches/sensors/cables/means


of communication with other system components as indicated in panel
BF4. 06 description and schematics nr 1 -

Fan panel inclusive of all switches/sensors/cables/means of


BF4. 07 communication with other system components as indicated in panel nr 1 -
description and schematics

Hoist panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF4. 08 description and schematics nr 1 -

Generator (400 kVA)


BF4. 09 nr 1 -
fuel tank storage system of 2500L inclusive of piping and auxiliaries to
genset constructed in a reinforced concrete bund with a a 1.1 times the
BF4. 10 tank capacity nr 1 -

Transformer (400 kVA) oil type for outdoor use inclusive of accessories
BF4. 11 as buchold relay/lifting hooks/oil fill plug/oil drain valve. nr 1 -

BF4. 12 MV termination kit nr 1 -


Poles and wire supports for transformer installation and MV fuse and
BF4. 13 cable installation and termination nr 1 -

MV metering equipment inclusive of instalation acceptable for the


BF4. 14 electrical power supplier nr 1 -

Connection Fee's to obtain an electrical connection


BF4. 15 nr 1 -
Wires, Cables, Conduits, Boxes, Fittings, Cable Racks, Ducts, Grounding
and Other Miscellaneous Items for plants for Electrical Room for Intake
BF4. 16 Pump Station. ls 1 -

Miscellaneous Electrical Work

Bidder's Signature or Initials ...........................................


Page 28/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 4 - ELECTRICAL WORKS FOR
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 INTAKE PUMPING STATION BILL - 4

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF4. 17 Heavy duty galvanized steel cable trays, ducts and raceways as per ls 1 -
Drawings and Specifications

Indoor and outdoor lighting complete including all power distribution


BF4. 18 panels, fixtures, boxes, wiring and conduit to distribution panel as per ls 1 -
Drawings and Specifications

BF4. 19 Power outlets complete all receptacles, boxes, wiring and conduit to ls 1 -
distribution panel as per Drawings and Specifications

Earthing system complete including equipment bonding as shown on


BF4. 20 ls 1 -
Drawings and Specifications

Sub-total for Bill 4, CARRIED TO GRAND SUMMARY -

Bidder's Signature or Initials ...........................................


Page 29/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF5. BILL 5 – CIVIL AND BUILDING WORKS

Bill 5-1 – Access Road and Drainage


(1) Access Road

General Clearance Demolition and removal of all articles,


objects and obstructions which are
required to be cleared except the trees
BF5. 01 with diameter > 200mm m2 4,670.0 0.96 4,483.20

Trees Clearing and Grubbing


BF5. 02 Diameter >200 mm nr 100 10.80 1,080.00

Tree Planting replacement of cleared trees (5 per 1 cleared tree)


BF5. 03 nr 100 40.00 4,000.00
Stripping of Top Soil and temporary storage, t=30cm
BF5. 04 m3 1,000 5.50 5,500.00
Roadway Excavation, Common
BF5. 05 m3 466 5.50 2,563.00
Embankment, 90% MDD
BF5. 06 m3 2,050 16.80 34,440.00
Sub-base material, CBR =>30%, 95% MDD, 20cm thickness
BF5. 07 m3 802 43.00 34,486.00
Aggregate Base course, CBR=>80%, 98% MDD, 15cm thickness
BF5. 08 m3 646 43.00 27,778.00
Sub-base Shoulder, CBR=>30%, 95% MDD, 30cm thickness
BF5. 09 m3 341 43.00 14,663.00

Concrete for Pavement - Materials and Labour


BF5. 10 32MPa t=200mm m3 589 160.00 94,240.00

Wire Mesh
BF5. 11 t 36.6 1,590.00 58,194.00

Grade390 Deformed Reinforcement Bar


BF5. 12 t 3.1 1,390.00 4,309.00

BF5. 13 Mastic Joint Sealer(15*25) Kg 463 20.00 9,260.00

BF5. 14 Plastic Sheeting m2 474 1.20 568.80

BF5. 15 Flexible Filler m2 10 5.00 50.00

BF5. 16 PVC ф25 m 109 3.00 327.00

Road Shoulder, Laterite Materials and Labour


BF5. 17 t=400mm m2 300 16.80 5,040.00

Bidder's Signature or Initials ...........................................


Page 30/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Slope Embankment and Sodding for Protection
BF5. 18 m2 300 7.20 2,160.00

(2) Drainage Structure for Access Road


-
Supply and Installation of Drainage Pipe Culvert φ800, Depth not
BF5. 19 exceeding 2.3m m 30 165.60 4,968.00

Supply and install drainage manhole1200 x 1400 complete including RC


BF5. 20 cover for depth to invert not exceeding 2.3m nr 4 4,104.00 16,416.00

Drainage Culvert as specified in the Drawing


BF5. 21 ls 1 11,736.00 11,736.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 22 Bill 5-1. ls 1 29,952.00 29,952.00

Sub-total for Bill 5-1 – Access Road and Piping, CARRIED TO PART SUMMARY 366,214.00

Bidder's Signature or Initials ...........................................


Page 31/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-2 – Earthwork for Water Treatment Plant


General Clearance Demolition and removal of all articles,
objects and obstructions which are
required to be cleared except the trees
BF5. 23 with diameter > 200mm ha 1.6 9,600.00 14,880.00

Stripping of Top Soil, t=30cm


BF5. 24 m³ 200 5.50 1,100.00
General Excavation below land formation level after stripping of top soil
BF5. 25 including dewatering m³ 44,070 5.50 242,385.00
Filling and Embankment including compaction in 30cm layers
BF5. 26 m³ 2,000 16.80 33,600.00
Backfill including compaction Well graded sand as specified or
BF5. 27 in layers to 95% MDD as instructed by the Engineer m3 8,533 40.00 341,320.00
specified
Transportation of Soil from designated location owned by Employer to
BF5. 28 the site, less than 10km one way m3 10,000 3.00 30,000.00
Other miscellaneous items that are specified or shown on the drawings
or that the Contractor may deem necessary to complete works in Bill 5-
BF5. 29 2. ls 1 8,352.00 8,352.00

Sub-total for Bill 5-2 – Earthwork for Water Treatment Plant, CARRIED TO PART SUMMARY 671,637.00

Bidder's Signature or Initials ...........................................


Page 32/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Bill 5-3 – Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin (in Treatment Facilities)
Construction of Receiving Well, Coagulation Basin, Flocculation and
Sedimentation Basin including supply of materials, general
preparation, formwork, re-bar arrangement, concrete, interior and
exterior finishing for all floors, walls, columns, bases, ladders, handrails,
stepirons as specified and shown in the Drawings

Compacted base course Below concrete structure


BF5. 30 approximately 150mm thick m3 531 43.00 22,833.00

Lean Concrete, 18N t=10cm


BF5. 31 m3 354 150.00 53,100.00
Re-bar works
BF5. 32 t 459 1,390.00 638,010.00
Concrete Works Top Slab
BF5. 33 m³ 70 280.00 19,600.00
Concrete Works Wall
BF5. 34 m³ 1,604 260.00 417,040.00
Concrete Works Base Slab
BF5. 35 m³ 1,455 160.00 232,800.00
Concrete Works Stairs and Miscellaneous
BF5. 36 m³ 22 280.00 6,160.00
Concrete Works Mass Concrete 30MPa
BF5. 37 m3 371 160.00 59,360.00

BF5. 38 Handrails m 280 65.00 18,200.00


BF5. 39 Manhole c/w cover nr 18 1,310.40 23,587.20
BF5. 40 External Waterproofing work Bitumen coating m2 3,000 21.00 63,000.00
Internal Waterproofing work Hydroepoxy painting as specified including
BF5. 41 supply and application m2 3,000 21.00 63,000.00

Building electrical works for Receiving Well and Coagulation Basin,


Flocculation and Sedimentation Basin (in Treatment Facilities)
including distribution panels, cables and termination, conduit and
BF5. 42 fittings, lighting fixtures, switches, and other miscellaneous equipment ls 1 3,600.00 3,600.00
specified in the Drawings.

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 43 Bill 5-3. ls 1 11,808.00 11,808.00

Sub-total for Bill 5-3 – Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin (in Treatment Facilities), 1,609,265.20
CARRIED TO PART SUMMARY

Bidder's Signature or Initials ...........................................


Page 33/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-4 – Filters (in Treatment Facilities)


Base Course t=20cm
BF5. 44 m2 1,150 8.60 9,890.00
Lean Concrete, 18N t=10cm
BF5. 45 m2 1,150 15.00 17,250.00
Re-bar work
BF5. 46 t 188 1,390.00 261,320.00
Concrete Works Top Slab
BF5. 47 m³ 56 280.00 15,680.00
Concrete Works Wall
BF5. 48 m³ 544 260.00 141,440.00
Concrete Works Base Slab
BF5. 49 m³ 829 160.00 132,640.00
Concrete Works Stairs and Miscellaneous
BF5. 50 m³ 10 280.00 2,800.00
Non-reinforced Concrete 18N
BF5. 51 m³ 780 150.00 117,000.00
External Waterproofing work Bitumen coating
BF5. 52 m2 600 21.00 12,600.00
Internal Waterproofing work Hydroepoxy painting as specified in GS
BF5. 53 (painting) 7.4.5, 4. epoxy painting m2 600 21.00 12,600.00

Handrails
BF5. 54 m 280 86.00 24,080.00
Manhole
BF5. 55 nr 18 1,310.40 23,587.20
Building Architectural work for Filter Gallery & Blower Room in Water
Treatment Facility -

Construction of Filter Gallery & Blower Room including supply of


materials, general preparation, formwork, re-bar arrangement,
concrete, interior and exterior finishing for all floors, walls, columns,
bases, ceilings, roofing, windows, doors, shutters, ladders, step irons,
BF5. 56 crane beams,underdrain, blocks,filter media, except the works included ls 1 14,400.00 14,400.00
in Civil works

Building electrical works for Filter Gallery & Blower Room including
distribution panels, cables and termination, conduit and fittings, lighting
BF5. 57 fixtures, switches, and other miscellaneous equipment specified in the ls 1 7,200.00 7,200.00
Drawings.

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
Bill 5-4
BF5. 58 ls 1 6,984.00 6,984.00

Sub-total for Bill 5-4 – Filters (in Treatment Facilities), CARRIED TO PART SUMMARY 799,471.20

Bidder's Signature or Initials ...........................................


Page 34/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-5 – Clear water reservoir and Distribution Pump Station


Construction Works including materials and labour and temporary
works and equipment as specified and shown on the drawings

Sand Backfill
BF5. 59 m³ 24,464 40.00 978,560.00

Blinding layer, t=150mm Thk. (Concrete cube compressive strength = 15


BF5. 60 MPa) m³ 401 140.00 56,140.00

Concrete for main Structures like as Column, Base Slab, Top Slab, Roof
Slab with Parapet Wall, External Wall, Internal Wall and Partition Wall,
BF5. 61 manhole (Concrete cube compressive strength = 37 MPa) t 4,805 140.00 672,700.00

Formwork
BF5. 62 m2 17,354 31.00 537,974.00

Deformed bar with Yield strength = 390 MPa


BF5. 63 t 625 1,390.00 868,750.00

External Waterproofing work Bitumen coating


BF5. 64 m2 5,000 21.00 105,000.00

Internal Waterproofing work Hydroepoxy painting as specified including


BF5. 65 supply and application m2 11,000 21.00 231,000.00

Handrail
BF5. 66 m 80 86.00 6,880.00

Bidder's Signature or Initials ...........................................


Page 35/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Manhole Including 6 ventilation towers complete
with protective cowel annd filters and 14
BF5. 67 access manholes with chimney and step nr 20 1,306.80 26,136.00
irons in upper part

Building Architectural work for Pump Station specified in Architectural


Drawings -

Construction of Pump Station including supply of materials, general


preparation, formwork, re-bar arrangement, concrete, interior and
exterior finishing for all floors, walls, columns, bases, ceilings, roofing,
windows, doors, shutters, crane beams (40m) , ladders, step irons,
BF5. 68 except the works included in Civil works, as specified and shown on the ls 1 201,600.00 201,600.00
Drawings

Building electrical works for Pump Station including distribution panels,


cables and termination, conduit and fittings, lighting fixtures, switches,
internet and telephone systems, sound system, lightning and earthing
BF5. 69 protection systems and other miscellaneous equipment specified in the ls 1 25,920.00 25,920.00
Drawings.

Supply and Install Stainless steel Stairs and platforms as outlined on the
BF5. 70 drawings ls 1 10,800.00 10,800.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 71 Bill 5-5 ls 1 38,880.00 38,880.00

Sub-total for Bill 5-5 – Clear water reservoir and Distribution Pump Station, CARRIED TO PART SUMMARY 3,760,340.00

Bidder's Signature or Initials ...........................................


Page 36/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-6 – Drainage Basin


Construction of Drainage Basin including supply of materials, general
preparation, formwork, re-bar arrangement, concrete, interior and
BF5. 72 exterior finishing for all floors, walls, columns, bases, step irons, ladders ls 1 3,600.00 3,600.00
as specified and shown in the Drawings

Base Gravel Basecourse, t=15cm


BF5. 73 m³ 81 43.00 3,483.00

Concrete, 15MPa Blinding layer - 10cm thick


BF5. 74 m³ 56 150.00 8,400.00

Re-bar work
BF5. 75 t 143 1,390.00 198,770.00

Structural Concrete
BF5. 76 m³ 1,065 260.00 276,900.00

Handrail H=1.10m
BF5. 77 m 72 86.00 6,192.00

Supply and Install lifting beam for travelling trolley hoist for a capacity
BF5. 78 of 1500kg including all embedding and securing to structure. nr 1 3,600.00 3,600.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 79 Bill 5-6 ls 1 5,760.00 5,760.00

Sub-total for Bill 5-6 – Drainage Basin, CARRIED TO PART SUMMARY 503,105.00

Bidder's Signature or Initials ...........................................


Page 37/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-7 – Sludge Storage Lagoon

BF5. 80 Sand Backfill m³ 1,147 40.00 45,880.00


BF5. 81 Gravel (Max f50) with thickness t = 150mm m³ 61 43.00 2,623.00
BF5. 82 Gravel layer thickness t = 200mm - 300mm m³ 369 43.00 15,867.00
leveling concrete layer, t=100mm Thk. (Concrete cube compressive
BF5. 83 strength = 15 MPa) m³ 41 140.00 5,740.00

Concrete apron (Non reinforced concrete with cube compressive


BF5. 84 strength = 37MPa) m³ 1.2 140.00 168.00

Base concrete with minimum reinforcement (Concrete cube


BF5. 85 compressive strength = 37 MPa) m³ 304 140.00 42,560.00

Concrete for main Structures like as Footing, Wall, Approach Slab and U-
BF5. 86 drain (Concrete cube compressive strength = 37 MPa) m³ 296 140.00 41,440.00

BF5. 87 Formwork m2 2,238 31.00 69,378.00

BF5. 88 Deformed bar with Yield strength = 390 MPa t 61.8 1,390.00 85,902.00

Elastic filler t=20mm


BF5. 89 m2 14 15.00 210.00

PVC pipe ND100


BF5. 90 m 42 10.00 420.00

Perforated PVC pipe Straight


BF5. 91 m 600 10.00 6,000.00

Stop logs including all accessories as specified and shown on the


BF5. 92 Drawings LS 1 14,400.00 14,400.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 93 Bill 5-7 ls 1 4,824.00 4,824.00

Sub-total for Bill 5-7 – Sludge Storage Lagoon, CARRIED TO PART SUMMARY 335,412.00

Bidder's Signature or Initials ...........................................


Page 38/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-8 – Administration building


Pile foundation work including all plant, equipment, labour and
materials for setup, re-bar arrangement, concrete, jointing and other
ancillary works.

BF5. 94 Pile work Driven pile size 0.3x0.3x12.0m nr. 66 597.60 39,441.60
Construction of Administration Building including supply of materials,
general preparation, formwork, re-bar arrangement, concrete, interior
and exterior finishing for all floors, walls, bases and ceilings, roofing,
BF5. 95 stairs, windows, doors, handrails, shutters, shelves, racks, tables and ls 1 439,200.00 439,200.00
other miscellaneous equipment specified in the Drawings.

Building electrical works for Administration Building including


distribution panels, cables and termination, conduit and fittings, lighting
fixtures, switches, internet and telephone systems, sound system,
BF5. 96 lightning and earthing protection systems and other miscellaneous ls 1 18,000.00 18,000.00
equipment specified in the Drawings.

Water Supply and Wastewater system work for Administration Building


including supply and installation of PPR cold water pipes and fittings,
sanitary fixtures, PVC pipes and fittings, 2200l 2 chamber septic tank
BF5. 97 package inclusive of 20 meters of leachfield piping buried in the ground ls 1 10,800.00 10,800.00
and other miscellaneous equipment specified in the Drawings.

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 98 Bill 5-8 ls 1 5,112.00 5,112.00

Sub-total for Bill 5-8 – Administration building, CARRIED TO PART SUMMARY 512,553.60

Bidder's Signature or Initials ...........................................


Page 39/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-9 – Chemical building


Construction of Chemical Building including supply of materials, general
preparation, formwork, re-bar arrangement, concrete, interior and
exterior finishing for all floors, walls, bases and ceilings, roofing,
BF5. 99 windows, doors, shutters, shelves, racks tables and other miscellaneous ls 1 396,000.00 396,000.00
equipment specified in the Drawings.

Building electrical works for Chemical Building including distribution


panels, cables and termination, conduit and fittings, lighting fixtures,
switches, internet and telephone systems, sound system, lightning and
BF5. 100 earthing protection systems and other miscellaneous equipment ls 1 39,600.00 39,600.00
specified in the Drawings.

Other miscellaneous items that are specified or shown on the drawings


BF5. 101 or that the Contractor may deem necessary to complete the works in ls 1 4,392.00 4,392.00
Bill 5-9

Sub-total for Bill 5-9 – Chemical building, CARRIED TO PART SUMMARY 439,992.00

Bidder's Signature or Initials ...........................................


Page 40/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-10 – Generator House


Construction of Generator Building including general preparation,
formwork, re-bar arrangement, concrete, interior and exterior finishing
for all floors, walls, bases and ceilings, roofing, windows, doors,
BF5. 102 shutters, shelves, racks tables and other miscellaneous equipment ls 1 136,800.00 136,800.00
specified in the Drawings.

Building electrical works for Generator Building including distribution


panels, cables and termination, conduit and fittings, lighting fixtures,
BF5. 103 switches, earthing protection system and other miscellaneous ls 1 6,192.00 6,192.00
equipment specified in the Drawings.

Construct reinforced concrete bund for Genset fuel tank that holds 1.1
BF5. 104 times the tank (9000 litres) capacity. ls 1 1,080.00 1,080.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 105 Bill 5-10 ls 1 1,440.00 1,440.00

Sub-total for Bill 5-10 – Generator House, CARRIED TO PART SUMMARY 145,512.00

Bidder's Signature or Initials ...........................................


Page 41/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-11 – Gates, Plaque Shelter and Fencing


Construction of Main/ Side Gates, Plaque Shelter and fencing including
general preparation, formwork, re-bar arrangement, concrete, interior
and exterior finishing for all floors, walls, bases and ceilings, roofing,
windows, doors, shutters, shelves, supply and installation of Main gate
and side gate, Nameplate Panel with BTBWSA logo, and other
BF5. 106 miscellaneous equipment specified in the Drawings and Specifications. ls 1 20,000.00 20,000.00

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF5. 107 Bill 5-11 ls 1 2,000.00 2,000.00

Sub-total for Bill 5-11 –Gates, Plaque Shelter and Fencing, CARRIED TO PART SUMMARY 22,000.00

Bidder's Signature or Initials ...........................................


Page 42/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-12 – Yard piping


Piping Works including supply of materials and miscellaneous materials
for connecting and installation, trenching, excavation, temporary work,
jointing work, installation work, filling works, inspections and testing
and miscellaneous materials for connecting and installation specified in
the Drawings

A. Raw Water Conveyance DIP ND700


BF5. 108 Pipe ls 1 54,000.00 54,000.00

B. Filtered Water Pipe DIP ND800


BF5. 109 ls 1 40,320.00 40,320.00

C. Treated Water DIP ND800


BF5. 110 Transmission Pipe ls 1 47,520.00 47,520.00

D. Backwash Return Pipe DIP ND350


BF5. 111 ls 1 5,760.00 5,760.00

E-1. Receiving Well Overflow RCP ND500


BF5. 112 Pipe ls 1 3,600.00 3,600.00

E-2 Receiving Well Drain DIP ND100


BF5. 113 Pipe ls 1 576.00 576.00

F-1. Sedimentation Basin DIP ND 200


BF5. 114 Sludge Drain Pipe ls 1 1,440.00 1,440.00

F-3. Sedimentation Basin DIP ND 300


BF5. 115 Sludge Drain Pipe ls 1 15,840.00 15,840.00

G. Treatment Facilities Drain DIP ND200


BF5. 116 Pipe ls 1 7,200.00 7,200.00

Bidder's Signature or Initials ...........................................


Page 43/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
H. Backwash Drain Pipe DIP ND400
BF5. 117 ls 1 7,200.00 7,200.00

I. Clear Water Reservoir DIP ND500


BF5. 118 Overflow Pipe ls 1 12,240.00 12,240.00

J. Plant Drain Pipe RCP ND800-1000


BF5. 119 ls 1 17,280.00 17,280.00

K. Sludge Lagoon Drainage uPVC ND250


BF5. 120 Pipe ls 1 23,040.00 23,040.00

L. Drainage Basin Overflow DI ND400


BF5. 121 Pipe ls 1 10,800.00 10,800.00

L. Drainage Basin Recycle DI ND300


BF5. 122 Pipe ls 1 10,800.00 10,800.00

Water Supply Pipes, HDPE OD32-90 including materials and labour for
straight pipes, fittings, expansion joint, trenching and filling as specified
BF5. 123 in the Drawings ls 1 18,000.00 18,000.00

Water Supply Pipes, HDPE OD32-90 including materials and labour for
straight pipes, fittings, expansion joint, trenching and filling as specified
BF5. 124 in the Drawings ls 1 18,000.00 18,000.00

Miscellaneous work as specified in the Drawings and the Specifications


BF5. 125 and not included elsewhere in the Bill 5-12 ls 1 21,600.00 21,600.00

Sub-total for Bill 5-12 – Yard piping, CARRIED TO PART SUMMARY 315,216.00

Bidder's Signature or Initials ...........................................


Page 44/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-13 – Yard Development


(1) Internal Road

BF5. 126 Cutting Existing Ground 100mm thk. and recompact 95% of MDD m3 1,547 10.00 15,470.00

BF5. 127 Back Fill Selected Material and recompact 95% of MDD m3 1,547 16.80 25,989.60

BF5. 128 Sub Base Layer With Compact 95% of MDD m3 726 43.00 31,218.00

BF5. 129 Aggregate Base Course m3 544 43.00 23,392.00

BF5. 130 Concrete of Internal Road Pavement m3 544 160.00 87,040.00

BF5. 131 Wire Mesh of Internal Road


Pavement
t 33.6 1,590.00 53,424.00

BF5. 132 Formwork m2 217 20.00 4,340.00

BF5. 133 Smooth Dowel Bar, RB18 x 600


@300, One on Paint & Greased
t 0.3 1,390.00 417.00

BF5. 134 Deformed Bar, RB16 x 600 @450,


One on Paint & Greased
t 0.7 1,390.00 973.00

BF5. 135 Mastic Joint Sealer kg 159 36.00 5,724.00

BF5. 136 Flexible Joint Filler m2 8 15.00 120.00

BF5. 137 Plastic Sheeting m2 457 1.20 548.40

2) Retaining Wall and


Concrete Post

2.1 Structural Works

BF5. 138 Excavation m3 1,211 5.50 6,660.50

BF5. 139 Back Fill and Compaction m3 666 16.80 11,188.80

BF5. 140 Lean Concrete, 50mm thk m3 86 150.00 12,900.00

BF5. 141 Compacted Stone (4x6) With Sand, 150mm thk m3 259 43.00 11,137.00

BF5. 142 Concrete for Retaining Wall m3 501 140.00 70,140.00

BF5. 143 Reinforement


Wall
Bar for Retaining
t 45.1 1,390.00 62,689.00

BF5. 144 Formwork for Retaining Wall m2 2,197 31.00 68,107.00

BF5. 145 Concrete Post 150x150@2000 nr. 101 not applicable -

BF5. 146 Chains Link m 780 not applicable -

Bidder's Signature or Initials ...........................................


Page 45/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

2.2 Architectural Works

BF5. 147 Wall Painting m2 759 9.00 6,831.00

(3) Drainage pipes and chambers

Bidder's Signature or Initials ...........................................


Page 46/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Supply and Installation of Drainage pipes and chambers specified in the
Drawings

3.1 RC U Drain

BF5. 148 Excavation m3 1,080 5.50 5,940.00

BF5. 149 Back Fill and Compaction m3 695 16.80 11,676.00

BF5. 150 Lean Concrete, 50mm thk m3 39 150.00 5,850.00

BF5. 151 Compcted Stone (4x6) With Sand, 150mm thk m3 118 43.00 5,074.00

BF5. 152 Concrete for U Drain m3 238 240.00 57,120.00

BF5. 153 Reinforement Bar for U Drain t 24 1,390.00 33,360.00

BF5. 154 RC Cover Type 1 nr 788 15.00 11,820.00

BF5. 155 RC Cover Type 2 nr 1,454 18.00 26,172.00

BF5. 156 Heavy Duty Steel Grating Cover m2 17 1,500.00 25,500.00

BF5. 157 Weephole, Dia, 40mm @1200mm m 198 2.00 396.00

BF5. 158 Connection Chamber Type A nr 5 591.00 2,955.00

BF5. 159 Connection Chamber Type B nr 13 669.00 8,697.00

3.2 RC Pipe Drain

BF5. 160 Excavation m3 1,140 5.50 6,270.00

BF5. 161 Granula Bedding Back Fill and Compaction m3 89 43.00 3,827.00

BF5. 162 Selected Field Material Back Fill and Compaction m3 286 16.80 4,804.80

BF5. 163 Backfilling With Selected Excavation Material m3 403 16.80 6,770.40

BF5. 164 Lean Concrete, 50mm thk m3 3 150.00 450.00

BF5. 165 Compcted Stone (4x6) With Sand, 150mm thk m3 6 43.00 258.00

RC Pipe

BF5. 166 RC Pipe Dia.600 m 113 276.00 31,188.00

BF5. 167 RC Pipe Dia.800 m 85 309.00 26,265.00

BF5. 168 Manhole MH nr 7 1,395.00 9,765.00

BF5. 169 Manhole DMH nr 3 1,519.00 4,557.00


(4) Landscaping

Construction of Flag poles including general preparation, steel


structural works, concrete, masonry and miscellaneous works specified
BF5. 170 in the Drawings. ls 1 5,400.00 5,400.00

Yard Lighting system including Street LED Lighting fixtures, distribution


panels, cables and termination, conduit and fittings, earthing and other
BF5. 171 miscellaneous works specified in the Drawings. ls 1 7,200.00 7,200.00

Turfing and Natural Backfill, h=200mm


BF5. 172 m2 200 8.00 1,600.00

Bidder's Signature or Initials ...........................................


Page 47/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Lean Concrete, 50mm thk
BF5. 173 m3 4 150.00 600.00
Compcted Stone (4x6) With Sand, 150mm thk
BF5. 174 m3 11 43.00 473.00
Concrete Block Pavment
BF5. 175 m2 470 30.00 14,100.00
Concrete Curb for Road
BF5. 176 m 228 20.00 4,560.00
Concrete Curb for Walkway
BF5. 177 m 140 20.00 2,800.00
Tree Planting with each approved type tree of initial size 2 m high & 200
mm girth including 1 m3 of subsoil and 3 wooden stakes for stabilizing
tree. Maintain tree till the end of Defects Liability Period.

Tree Type-1 (Champey Tree, H=2.5m)


BF5. 178 nr 7 75.60 529.20
Flower Type-3 (Slakgnan Flower, H=2m)
BF5. 179 nr 25 68.40 1,710.00
Flower Type-4 (Machul Flower, H=1.2m)
BF5. 180 nr 3 75.60 226.80
Miscellaneous landscaping works specified in the Drawings or the
BF5. 181 Specifications but otherwise not included elsewhere in Bill 5.13 ls 1 1,440.00 1,440.00

Sub-total for Bill 5-13 –Yard Development , CARRIED TO PART SUMMARY 826,223.50

Bidder's Signature or Initials ...........................................


Page 48/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 5-14 – Miscellaneous Facilities


Construction of Raw Water Measuring Chamber including timbering
piling, base gravel, lean concrete, re-bar work, scaffolding, form work,
BF5. 182 concrete and supply and installation of manhole and steps as specified ls 1 17,280.00 17,280.00
in the drawings.

Miscellaneous civil and building works specified in the Drawings or the


BF5. 183 Specifications but otherwise not included elsewhere in Bill 5.14 ls 1 3,600.00 3,600.00

Sub-total for Bill 5-14 – Miscellaneous Facilities, CARRIED TO PART SUMMARY 20,880.00

Bidder's Signature or Initials ...........................................


Page 49/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 5 - CIVIL WORKS FOR WATER
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 TREATMENT PLANT BILL - 5

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

PART SUMMARY FOR Bill 5

Sub-total for Bill 5-1 – Access Road and Piping, CARRIED TO PART SUMMARY 366,214.00

Sub-total for Bill 5-2 – Earthwork for Water Treatment Plant, CARRIED TO PART SUMMARY 671,637.00

Sub-total for Bill 5-3 – Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin (in Treatment Facilities), 1,609,265.20
CARRIED TO PART SUMMARY
Sub-total for Bill 5-4 – Filters (in Treatment Facilities), CARRIED TO PART SUMMARY 799,471.20

Sub-total for Bill 5-5 – Clear water reservoir and Distribution Pump Station, CARRIED TO PART SUMMARY 3,760,340.00

Sub-total for Bill 5-6 – Drainage Basin, CARRIED TO PART SUMMARY 503,105.00

Sub-total for Bill 5-7 – Sludge Storage Lagoon, CARRIED TO PART SUMMARY 335,412.00

Sub-total for Bill 5-8 – Administration building, CARRIED TO PART SUMMARY 512,553.60

Sub-total for Bill 5-9 – Chemical building, CARRIED TO PART SUMMARY 439,992.00

Sub-total for Bill 5-10 – Generator House, CARRIED TO PART SUMMARY 145,512.00

Sub-total for Bill 5-11 – Gates, Plaque, Shelter and Fencing, CARRIED TO PART SUMMARY 22,000.00

Sub-total for Bill 5-12 – Yard piping, CARRIED TO PART SUMMARY 315,216.00

Sub-total for Bill 5-13 – Yard Development, CARRIED TO PART SUMMARY 826,223.50

Sub-total for Bill 5-14 – Miscellaneous Facilities, CARRIED TO PART SUMMARY 20,880.00

Sub-total for Bill 5, CARRIED TO GRAND SUMMARY 10,327,821.50

Bidder's Signature or Initials ...........................................


PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 6 - MECHANICAL WORKS FOR BILL-6
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT

Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY
RATE Amount
(USD) (USD)

BF6. BILL 6 – MECHANICAL WORKS FOR WATER TREATMENT PLANT

Bill 6-1 – Treatment Facilities (Coagulation, Flocculation,


Sedimentation and Filtration Block - CFSF block)

Bill 6-1-1 – Piping

Piping Works including supply of materials, finishing and painting,


welding, jointing, installation work as shown in the drawings and the
specifications, inspections and testings and miscellaneous materials for
connecting and installation. Piping shall be supported, anchored, or
guided by the Contractor to prevent undue line deflection, excessive
vibration and to protect piping and connected equipment from
excessive loading and expansion stress. Actuated valves are inclusive of
actuator unless already specified in a different Bill

Bill 6-1-1-1 Sedimentation Sludge Evacuation Pipeline - Piping in


Carbon Steel unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
sedimentation basin sludge evacuation system including all excavation,
BF6. 01 layng and backfill as LS breakdown ls 1 -

Bill 6-1-1-1-2 Filters Inlet/Backwash Outlet Pipeline - Piping in Carbon


Steel unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
BF6. 02 Filters Inlet/ Backwash Outlet system including all excavation, layng and ls 1 -
backfill as LS breakdown

Bill 6-1-1-1-3 Filtered Water Valves Chamber - Piping in Ductile Iron


unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Filtered Water Valves Chamber including all excavation, layng and
BF6. 03 backfill as LS breakdown ls 1 -

Bill 6-1-1-1-4 Filters Backwash Pipeline - Piping in Carbon Steel unless


differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Filters Backwash Pipeline system including all excavation, layng and
BF6. 04 backfill as LS breakdown ls 1 -

Bill 6-1-1-1-5 Filters Outlet and Drain Pipelines - Piping in Carbon Steel
unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Filters Outlet and Drain Pipeline system including all excavation, layng
BF6. 05 and backfill as LS breakdown ls 1 -

Bill 6-1-1-1-6 Filters Air Scour Pipeline - Piping in Carbon Steel unless
differently specified
Pipes, Valves, Nozzles, Fittings and Sensors for all items incorporated in
the Filters Air Scour Pipeline system including all excavation, layng and
BF6. 06 backfill as LS breakdown ls 1 -

Bill 6-1-1-1-7 Sedimentation Tanks Drain Pipeline - Piping in Carbon


Steel unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Sedimentation Tanks Drain Pipeline system including all excavation,
BF6. 07 layng and backfill as LS breakdown ls 1 -

Bill 6-1-1-1-8 High Pressure Service Water - Piping in Carbon Steel


unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
High Pressure Service Water Pipeline system including all excavation,
BF6. 08 layng and backfill as LS breakdown ls 1 -

Bill 6-1-1-1-9 Supply and installation of chemicals pipelines - From the


chemical building to the dosing point (included) and inclusive of
fittings, supports, channels and isolating ball valves and other
accessories as indicated in the P&ID
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Chemical Pipeline systems including all excavation, layng and backfill as
BF6. 09 LS breakdown ls 1 -

Pipes, Valves, Fittings and Sensors incorporated in all WTP piping


systems not described in the above lump sum breakdowns items, but as
BF6. 10 listed in the Particular Specifications volume 2A section 1.4 ls 1 -

Bill 6-1-1-1-10 Supply and installation of yard piping - Pipin in Carbon


Steel unless differently specified

Bill 6-1-2 – Pumps and blowers (supply, installation and testing)


P01 A&B - Sedimentation Sludge Pump; Type: Centrifugal, Submersible;
Duty point: Q=70 l/s, dH static = 2.237 m, dH dynamic = 6.263 m, dH
BF6. 11 total = 8.500 m; Power input (P1): 12.7 kW nr 2 -

P04, P05 & P06 Drain Pump; Type: Free Standing Submersible Drainage
Centrifugal Pump; Duty point: Q=>5 l/s with a total dH total = 10 m;
BF6. 12 Power rated (P2): 1.5 kW nr 3 -

P03 High pressure service water pump; Type: Vertical multistage


centrifugal pump; Duty point: Q=>12.5 l/s with a total dH total = 60 m;
BF6. 13 Outdoor installation, tropical climate; Power rated (P2): 15 kW nr 1 -

B01 A&B Air Scour Blower; Type: Roots type blower; Duty point: Q=51
m3/min, discharge pressure 400 mbar; Installation: Indoor installation,
tropical climate; Motor output: 55 kW totally enclosed fan cooled type;
Accessories (for each unit): V belt and Pulley, pressure gauge and stand,
BF6. 14 safety valve attached to blower, check valve inlet silencer and nr 2 -
antivibration plate

Bill 6-1-3 – Steel work


Bill 6-1-3-1 Ladders
Supply and installation of ladders. The steps and brackets made of a
DN20 stainless steel (AISI304) bar. Vertical ladder rails made of DN32
stainless steel bars. Wall brackets shall be fixed to the wall by anchor
bolts. The steps shall be 400 mm wide and 150 mm deep (from the wall)
unless differently specified in the drawings. The distance between steps
shall be 300 mm. The number of steps per ladder shall be as indicated in
the Contract Drawings

Ladders of types and quantities as itemised and described in the LS


BF6. 15 breakdown for Bills 6-1-3-1 ls 1 -

Bill 6-1-3-2 Handrails


Supply and installation of stainless steel handrails as indicated in the
Contract Drawings. The handrail shall be made completely of AISI304
stainless steel. Vertical tubes and upper guardrail shall be DN32 with a
minimum 3mm wall thickness. Mid rail shall be DN20 with a minimum
2.5mm wall thickness. All the pieces will be connected by welding.

Handrails of types and quantities as itemised and described in the LS


BF6. 16 breakdown for Bills 6-1-3-2 ls 1 -

Bill 6-1-3-3 Gratings


Supply and installation of stainless steel (AISI304) gratings for sidewalk
as shown in the Contract Drawings
Gratings and handrails of types and quantities as itemised and
BF6. 17 described in the LS breakdown for Bills 6-1-3-3 nr 1 -

Bill 6-1-3-4 Manhole covers


Supply and installation of stainless steel (AISI304) watertight manhole
BF6. 18 covers as shown in the Contract Drawings nr 18 -

Bill 6-1-3-5 Penstock/Slide Gate


Supply and installation of stainless steel (AISI304) slide gates in the inlet
splitting chamber; four side sealing, wall mounted; opening size 1000 x
BF6. 19 500 mm. With extended spindle, supports and pedestal nr 2 -

Supply and installation of stainless steel (AISI304) slide gates in the


flocculation nrs; basic sealing, wall mounted; opening size 300 x 200
BF6. 20 mm. nr 102 -

stainless Steel Flocculation Basin Drain Gates as shown on the


BF6. 21 Work drawings and in Specification ls 1 -
stainless steel Flocculation Basin Weirs as shown on drawings and
BF6. 22 Work specification ls 1 -

stainless steel Catwalk for each basin as shown on the Drawings and
BF6. 23 Work in Specification ls 1 -

Bill 6-1-3-6 Other steel works


Supply and installation of I-beam S6x12.5 over the sedimentation sludge
BF6. 24 gallery access stairs nr 1 -

Bill 6-1-4 – Pumps and Blowers for Filtration Building


Air Scouring Blower roots type, 51 m3/min @40 Kpa, 1760 rpm inclusive
ofFrame, pullys, belts, electro motor, discharge silencer, pressure
BF6. 25 gauge, check valve, safety valve nr 2 -

Spare parts for each Air Scouring Blower as: belts, bearing set, gasket
BF6. 26 set nr 2 -

filter valve gallery Sump Pump cast iron submersible pump installed
BF6. 27 fixed in the sump 6.3L/sec @12 meter nr 2 -
valve chamber Sump Pump cast iron submisible pump installed fixed in
BF6. 28 the sump 6.3L/sec @12 meter nr 2 -

drain valve galery Sump Pump cast iron submisible pump installed fixed
BF6. 29 in the sump 6.3L/sec @12 meter nr 2 -
Spare Pumps for sump pump set ups cast iron submisible pump
BF6. 30 installed fixed in the sump 6.3L/sec @12 meter nr 2 -

Sludge drainage pump submisrsible pump, 75 L/sec @9.7 meters


BF6. 31 inclusive pedestal, guidrail and suports, lifting chain nr 2

Spare parts for each sludge drain pump like: bearing set, mechanical
BF6. 32 seal, O ring set. nr 2

Bill 6-1-5 – Miscellaneous


Supply and Installation of Filtration media: Filter media shall be quartz
sand suitable for drinking water use with an effective size of 0.85-0.95
BF6. 33 mm and a uniformity coefficient of less than 1.4. The required amount is m3 450 -
inclusive to about 10% spare

Supply and Installation of Filter Under Drain blocks including wall


BF6. 34 sleeves, accessories and spare parts m2 410 -

Supply and Installation of support media: 2 layers of 50 mm of gravel


BF6. 35 with size distribution between 12 mm – 18 mm m3 41 -

Supply and Installation of support media: 2 layers of 50 mm of gravel


BF6. 36 with size distribution between 3 mm – 6 mm m3 41 -

Supply and Installation of support media: 1 layer of 50 mm of gravel


BF6. 37 with size distribution between 3 mm – 1.5 mm m3 20.5 -

Supply and Installation of support media: 1 layer of 50 mm of gravel


BF6. 38 with size distribution between 6 mm – 12 mm m3 20.5 -

BF6. 39 Throwable Polyethylene Safety Ring Buoy with rope and stand nr 30 -
BF6. 40 Supply Portable sump pump nr 2 -
Supply and Install stainless steel Equipment Handling Jib Crane
BF6. 41 complete with remote cable controls, power supply and accessories, nr 1 -
0.5ton

Supply and Install Ventilation Fans as per Specification and as shown on


the drawings

BF6. 42 Sedimentation Pipe Gallery Exhaust Fan nr 1 -

BF6. 43 Valve room Exhaust Fan nr 2 -

BF6. 44 Filter valve Gallery Exhaust Fan nr 2 -

BF6. 45 drain valve gallery Exhaust Fan nr 1 -

BF6. 46 blower room supply and Exhaust Fan nr 3 -

Other miscellaneous mechanical works items that are shown on the


BF6. 47 drawings or specified but not itemized in the BOQ including any items nr 1 -
deemed necessary by the Contractor to complete the works.

Sub-total for Part 6-1. Coagulation, Flocculation, Sedimentation and Filtration Block - CFSF block, CARRIED TO PART SUMMARY -

Bill 6-2 – Drainage Tanks

Bill 6-2-1 – Piping

Piping Works including supply of materials, finishing and painting,


welding, jointing, installation work as shown in the drawings and the
specifications, inspections and testings and miscellaneous materials for
connecting and installation. Piping shall be supported, anchored, or
guided by the Contractor to prevent undue line deflection, excessive
vibration and to protect piping and connected equipment from
excessive loading and expansion stress.
Bill 6-2-1-1 Drainage water recirculation and discharge pipeline -
Piping in Carbon Steel unless differently specified
Pipes, Valves, Fittings and Sensors for all items incorporated in the
Drainage Water Recirculation and Discharge Pipeline system including
BF6. 48 all excavation, laying and backfill as LS breakdown ls 1 -

Drainage Basin Butterfly Valve, 500mm dia


BF6. 49 nr 2 -
Drainage Basin Knife Valve , 250mm dia
BF6. 50 nr 4 -

Bill 6-2-2 – Pumps and blowers (supply, installation and testing)


P07 A, B & C Drainage Tanks Pumps; Type: Submersible Centrifugal
Pump; Duty point (max): Q=159 l/s, dH static = 7.070 m, dH dynamic =
BF6. 51 4.340 m, dH total = 11.410 m; Power input (P1): 16 kW; Variable Speed nr 3 -
Drive

Bill 6-2-3 – Steel work


Bill 6-2-3-1 Ladders
Supply and installation of ladders. The steps and brackets made of a
DN20 stainless steel (AISI304) bar. Vertical ladder rails made of DN32
stainless steel bars. Wall brackets shall be fixed to the wall by anchor
bolts. The steps shall be 400 mm wide and 150 mm deep (from the wall)
unless differently specified in the drawings. The distance between steps
shall be 300 mm. The number of steps per ladder shall be as indicated in
the Contract Drawings

Ladders of types and quantities as itemised and described in the LS


BF6. 52 breakdown for Bills 6-2-3-1 ls 1 3,600.00 3,600.00

Bill 6-2-3-2 Handrails


Supply and installation of stainless steel handrails as indicated in the
Contract Drawings. The handrail shall be made completely of AISI304
stainless steel. Vertical tubes and upper guardrail shall be DN32 with a
minimum 3mm wall thickness. Mid rail shall be DN20 with a minimum
2.5mm wall thickness. All the pieces will be connected by welding.

Handrails of types and quantities as itemised and described in the LS


BF6. 53 breakdown for Bills 6-2-3-2 nr 1 -

Bill 6-2-3-3 Gratings and Manholes


Supply and installation of stainless steel (AISI304) gratings for sidewalk
BF6. 54 as shown in the Contract Drawings ls 1 -

BF6. 55 CWT access manhole cover (frame size: 800 x 800 mm) nr 16 -
CWT equipment access manhole (frame size 1000 x 1200 mm
BF6. 56 nr 2 -

Bill 6-2-3-4 Penstock/Slide Gate


Supply and installation of stainless steel (AISI304) slide gates (inclusive
of frame, slide, seals, stem, stem guides and pedestal); four side sealing,
BF6. 57 wall mounted; DN300 opening nr 2 -

Bill 6-2-4 – Miscellaneous


BF6. 58 Throwable Polyethylene Safety Ring Buoy with rope and stand nr 2 -
Mechanical lifting hoist on beam set up with a travel trolly of a capacity
of 1500kg and set up so each of the 3 pumps installed can be lifted up
BF6. 59 out of the drainage basin nr 1 -
Other miscellaneous works items that are shown on the drawings or
BF6. 60 specified but not itemized in the BOQ including any items deemed nr 1 -
necessary by the Contractor to complete the works.

Sub-total for Part 6-2. Drainage Tanks, CARRIED TO PART SUMMARY 3,600.00

Bill 6-3 – Sludge Lagoons

Bill 6-3-1 – Piping

Piping is included in the yard piping Bill

Bill 6-3-2 – Pumps and blowers (supply, installation and testing)

None

Bill 6-3-3 – Steel work

Bill 6-3-3-1 Ladders


Supply and installation of ladders. The steps and brackets made of a
DN20 stainless steel (AISI304) bar. Vertical ladder rails made of DN32
stainless steel bars. Wall brackets shall be fixed to the wall by anchor
bolts. The steps shall be 400 mm wide and 150 mm deep (from the wall)
unless differently specified in the drawings. The distance between steps
shall be 300 mm. The number of steps per ladder shall be as indicated in
the Contract Drawings

Ladders of types and quantities as itemised and described in the LS


BF6. 61 breakdown for Bills 6-3-3-1 ls 1 -

Bill 6-3-3-2 Handrails


Supply and installation of stainless steel handrails as indicated in the
Contract Drawings. The handrail shall be made completely of AISI304
stainless steel. Vertical tubes and upper guardrail shall be DN32 with a
minimum 3mm wall thickness. Mid rail shall be DN20 with a minimum
2.5mm wall thickness. All the pieces will be connected by welding.

Handrails of types and quantities as itemised and described in the LS


BF6. 62 breakdown for Bills 6-3-3-2 nr 8 -

Bill 6-3-3-3 Gratings


Supply and installation of stainless steel (AISI304) gratings for sidewalk
as shown in the Contract Drawings
Handrails of types and quantities as itemised and described in the LS
BF6. 63 breakdown for Bills 6-3-3-3 nr 2 -

Bill 6-3-4 – Miscellaneous


Supply and installation of aluminium stop logs 2100 mm x 150 mm x 90
BF6. 64 mm (set of 12 planks) + guides, seal and lifting device nr 4

Supply and installation of aluminium stop logs: set of 3 planks 430 mm x


BF6. 65 300 mm x 50 mm + 1 plank 430 mm x 300 mm x 50 mm + guides, seal nr 8
and lifting device

Supply and installation of the sludge lagoons underdrain system


composed of:
BF6. 66 Perforated PVC Sch40 pipe, 100mm internal diameter m 438

BF6. 67 Filling lean concrete externally up to half-way level of the perforated m3 148 -
PVC pipes (100mm)
0-100 mm (variable due to floor slope) deep layer of 16-40 mm crushed
BF6. 68 stone/ gravel m3 74 -

BF6. 69 50 mm deep layer of 10-15 mm gravel m3 74 -


BF6. 70 50 mm deep layer of 2-10 mm gravel m3 74 -

BF6. 71 100 mm deep layer of washed sand (effective size 0.3-0.75 mm, m3 148 -
uniformity coefficient <4).
Front loader/
BF6. 72 excavator 4-5T with approximately 2m wide loader bucket nr 1 -

Other miscellaneous works items that are shown on the drawings or


BF6. 73 specified but not itemized in the BOQ including any items deemed ls 1 -
necessary by the Contractor to complete the works in Bill 6-3

Sub-total for Part 6-3. Sludge Lagoons, CARRIED TO PART SUMMARY -

Bill 6-4 – Administration building

HVAC work for Administration Building including supply and


installation of air conditioning unit and accessories, plumbing and other
BF6. 74 miscellaneous equipment specified in the Drawings. ls 1 -

Supply and Installation of Laboratory Equipment shown in the


BF6. 75 Specifications and drawings LS 1 -

Supply and Installation of Fire extinguisher inclusive with wall mounting


BF6. 76 hooks and signage as specified in the Drawings nr 24 -

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF6. 77 Bill 6-4 ls 1 -

Sub-total for Part 6-4. Administration Building, CARRIED TO PART SUMMARY -

Bill 6-5 – Chemical building

Bill 6-5-1 – Tanks, hoppers & bunds (supply, installation and testing)

V1 A, B, C, D, E & F, Coagulant preparation tank made of High-Density


Cross-linked Polyethylene: H=2.0 m D=2.15 m, Working volume 5.1 m3.
Inclusive of support for the internal mixer/agitator, powder chemical
inlet with a safe sack emptying platform with a grid, dust collection
BF6. 78 hood, 3 lugs for transport, nozzles as specified and anti-vortex blades. nr 6 -
All specified control instrumentation unless already included in other
Bills.

V2, Coagulant spill and drain collection tank made of High-Density


Cross-linked Polyethylene: H=2.4 m D=1.2 m, Working volume 2.0 m3.
BF6. 79 Inclusive of nozzles as specified. All specified control instrumentation nr 1 -
unless already included in other Bills.

V3 A & B, Hydrated lime hopper: H=2.5 m D=1.5 m, working volume 1.3


m3. Inclusive of support legs, inspection hatch, powder chemical inlet
with a safe sack emptying platform with a grid, dust collection hood, 3
lugs for transport, mechanical arch breaker with geared motor, base
BF6. 80 plate with flange, fitted with an opening for conveyor inlet. Rotating nr 2 -
paddle level sensors and all specified control instrumentation unless
already included in other Bills.

V4 A & B, Hydrated Lime Slurry preparation: H=1.0 m D=1.2 m, working


volume 0.9 m3. Inclusive of support for agitator, inspection hatch, 3 lugs
for transport, vent with spraying nozzle, other nozzles as specified and
BF6. 81 anti-vortex blades. All specified control instrumentation unless already nr 2 -
included in other Bills.
V5 A, B & C, Calcium hypochlorite preparation tank made of High-
Density Cross-linked Polyethylene: H=2.0 m D=1.8 m, Working volume
3.6 m3. Inclusive of support for the internal mixer/agitator, powder
chemical inlet with a working surface for safe opening and discharge of
BF6. 82 chemical drums with a grid, dust collection hood, 3 lugs for transport, nr 3 -
nozzles as specified and anti-vortex blades. All specified control
instrumentation unless already included in other Bills.

V6, Calcium hypochlorite spill and drain collection tank made of High-
Density Cross-linked Polyethylene: H=2.4 m D=1.2 m, Working volume
BF6. 83 2.0 m3. Inclusive of nozzles as specified. All specified control nr 1 -
instrumentation unless already included in other Bills.

Construction of concrete secondary containment as shown in the


BF6. 84 Contract Drawings inclusive of epoxy lining nr 1 -

Bill 6-5-2 – Metering pumps and metering conveyors

Supply of all labor, materials, equipment, and incidentals required to


install, ready for operation, and field test the metering pumps and
conveyors, control skids, valves and appurtenances as shown on the
Contract Drawings, P&ID and specifications.

MP01 A, B & C + MP02, Coagulant dosing and transfer/recirculation


pump; Type: electrically actuated, diaphragm pump; Max Flow 781 l/h,
BF6. 85 Max pressure 2.5 bar, Turn down ratio > 10:1 nr 4 -

MP03 A, B & C + MP04, Calcium Hypochlorite dosing and


transfer/recirculation pump; Type: electrically actuated, diaphragm
BF6. 86 pump; Max Flow 482 l/h, Max pressure 2.5 bar, Turn down ratio > 10:1 nr 4 -

MP05 A, B, C & D, Hydrated lime slurry dosing; Type: electrically


actuated, peristaltic pump; Max Flow 1173 l/h, Max pressure 2.5 bar,
BF6. 87 Turn down ratio > 10:1 nr 4 -

Hydrated lime metering conveyor inclusive of inlet chute, metering


conveyor tube, metering spiral, outlet chute Ø 150 mm, anti-blockage
switch (diaphragm sensor), geared motor, gearbox speed: 110 rpm,
motor: 1,1 kW. Estimated metering conveyor length: 3.0 m. Flexible
outlet chute Ø 150 - Height to be defined on site, Injector – estimated
BF6. 88 length: 1.0 m, outer tube Ø 88,9 mm, geared motor, gearbox speed 61,1 nr 2 -
rpm, motor: 0.37 kW. All metalworks in stainless steel AISI304

Bill 6-5-3 – Mixers/Agitators

Supply of all labor, materials, equipment, and incidentals required to


install, ready for operation, and field test the Mixer/Agitators on the
chemicals preparation tanks. Mixer/Agitator composed of 4 flat blades
(inclined at 45°, Ø 500 mm) and agitator shaft, length: 850 mm - Ø 25
mm. Geared motor 124 rpm - 0,55 kW

Agitators for coagulant preparation tanks (V1 A, B, C, D, E & F) -


BF6. 89 Material, Hastelloy or lined by suitable chemical resistant material nr 6 -

Agitators for calcium hypochlorite preparation tanks (V5 A, B & C) -


BF6. 90 Material, AISI 316 or lined by suitable chemical resistant material nr 3 -

Agitators for lime slurry preparation units (V4 A & B) - AISI 316 or
BF6. 91 equivalent nr 2 -

Bill 6-5-4 – Piping


Piping Works including supply of materials, finishing and painting,
welding, jointing, installation work as shown in the drawings and the
specifications, inspections and testings and miscellaneous materials for
connecting and installation. Piping shall be supported, anchored, or
guided by the Contractor to prevent undue line deflection, excessive
vibration and to protect piping and connected equipment from
excessive loading and expansion stress.

Supply and installation of coagulant piping within the chemical building.


The systems has to be furnished complete with pump suction, discharge
piping, recirculation piping, connection piping and valves, instruments,
automation and accessories as described in the P&ID drawings and in
BF6. 92 the specifications. Pipe material unless differently indicated shall be nr 1 -
uPVC.

Supply and installation of calcium hypochlorite piping within the


chemical building. The systems has to be furnished complete with pump
suction, discharge piping, recirculation piping, connection piping and
valves, instruments, automation and accessories as described in the
BF6. 93 P&ID drawings and in the specifications. Pipe material unless differently nr 1 -
indicated shall be uPVC.

Supply and installation of hydrated lime piping within the chemical


building. The systems has to be furnished complete with pump suction,
discharge piping, recirculation piping, connection piping and valves,
instruments, automation and accessories as described in the P&ID
BF6. 94 drawings and in the specifications. Pipe material unless differently nr 1 -
indicated shall be flexible uPVC.

Water distribution pipeline within the chemical building complete of


BF6. 95 isolation valves, check valves and instrumentation as shown in the P&ID nr 1 -
drawing

Bill 6-5-5 – Steel work

Bill 6-5-5-1 Handrails


Supply and installation of stainless steel handrails as indicated in the
Contract Drawings. The handrail shall be made completely of AISI304
stainless steel. Vertical tubes and upper guardrail shall be DN32 with a
minimum 3mm wall thickness. Mid rail shall be DN20 with a minimum
2.5mm wall thickness. All the pieces will be connected by welding.

Handrails of types and quantities as itemised and described in the LS


BF6. 96 breakdown for Bills 6-5-5-1 nr 1 -

Platforms
Supply and installation of stainless steel (AISI304) platforms as shown in
the Contract Drawings
B-WTP-CHB-C-GA-DT-012: Coagulant and lime platform (Surface
BF6. 97 including access stairs: 38.0 m2) nr 1 -
B-WTP-CHB-C-GA-DT-012: Calcium hypochlorite platform (Surface
BF6. 98 including access stairs: 22.3 m2) nr 1 -

Bill 6-5-6 – Miscellaneous

Supply and Install stainless steel Pump Handling Jib Crane complete with
BF6. 99 remote cable controls, power supply and accessories, 0.5tonne nr 1 -
Supply and install of overhead roller door as shown in the Contract
Drawings. The doors shall be made for heavy duty
BF6. 100 commercial/industrial applications and provide a free passage of 2.5 m nr 2 -
width and 3.0 m height. The doors shall be electrical actuated

Supply and install stainless steel (Grade 304) pallet lift (inclusive of
safety guards) to elevate standard pallet (1200 x 1000 x 1800 mm high)
BF6. 101 of chemical bags/drum. Safe working load of 1000 Kg.

Lift 1: coagulant and lime service. From building ground floor (15.00 m
asl) to first stop at the work platform level (16.60 m asl), second stop at
BF6. 102 first floor (19.80 m asl). nr 1 -

Lift 2: Calcium hypochlorite service. From building ground floor (15.00 m


BF6. 103 asl) to the work platform level (16.60 m asl). nr 1 -

BF6. 104 Manual pallet jack (2000 kg load) nr 4 -


BF6. 105 Hand lifter nr 2 -
BF6. 106 Fork lift nr 1 -
Supply and install of emergency Shower and Eyewash Station inclusive
BF6. 107 of first aid wall cabinet located as per Contract Drawings nr 2 -

BF6. 108 Supply of particulate respirators (N95 masks or better) nr 500 -


BF6. 109 Supply of 3 months worth stock of coagulant t 150 -
BF6. 110 Supply of 3 months worth stock of hydrated lime t 150 -
BF6. 111 Supply of 3 months worth stock of calcium hypochlorite t 25 -
Supply and install of dust collection system above each chemicals bag
breaker or drum discharge. The dust collection system shall maintain
the bag breaking area under negative pressure to prevent dust to
BF6. 112 escape. The extracted area shall be filtered locally with replaceable filter nr 11 -
cartridges. Inclusive of spare cartridge for 2 years.

HVAC work for Chemical Building including supply and installation of air
conditioning unit and accessories, plumbing and other miscellaneous
BF6. 113 equipment specified in the Drawings. ls 1 -

Water Supply and drainage system work for Chemical Building


including supply and installation of PVC pipes and fittings and other
BF6. 114 miscellaneous equipment specified in the Drawings. ls 1 -

Supply and Installation of Fire extinguisher ABC type 9 KG inclusive with


BF6. 115 wall mounting hooks and signage. nr 10 -

Supply and install a pallet lift with a capacity of 2500Kg lifting pallets
from the ground to first floor of the building installed with accessories
BF6. 116 so a level surface is achieved to transport pallets on and off the lift. nr 1 -

BF6. 117 Supply of hand operated hydraulic pallet trollies nr. 4 -


Other miscellaneous works items that are shown on the drawings or
BF6. 118 specified but not itemized in the BOQ including any items deemed ls 1 -
necessary by the Contractor to complete the works.

Sub-total for Part 6-5. Chemical building, CARRIED TO PART SUMMARY -

Part 6-6. Distribution Pump Station

(1) Pumps

Supply and Installation of Pumps as specified in the Specifications and


the Drawings

Distribution Pumps, Horizontal split case centrifugal pump fit with


bronze impeller and bearing temperature sensors, 246 l/sec @ 55
BF6. 119 meter, 1485 rpm E3 electro motor suitable for VFD operation nr 5 -

BF6. 120 Spare parts per Distribution Pump as (bearing set, gaskets, seals) nr 5 -
Backwash Pump, closed coupled centrifugal end suction pump,
1000m3/hours @ 25 meter, equipped with a 1485 rpm E3 electric
BF6. 121 motor suitable for VFD use nr. 2 -

Spare parts for Backwash each pump including: bearing set, mechanical
BF6. 122 seal, O ring set. nr 2 -
Pump Station Sump Pumps, cast iron submersible pump installed fixed
BF6. 123 in the sump 6.3L/sec @12 meter nr 3 -

Spare pump Submersible Sump Pumps, cast iron submersible pump


BF6. 124 6.3L/sec @12 meter (supply only) nr 1 -
(2) Cranes and Hoists

Supply and Installation of cranes and hoists with accessories as specified


in the Specifications and the Drawings
Single I- beam (40m) motorized crane on a trolly, remotely operated
BF6. 125 6000kg lifting capacity nr 1 -

Hand-operated chain hoist with geared trolley, 6000 kg


BF6. 126 nr 1 -
(3) Pipes, Valves and Miscellaneous

Piping Works including supply of materials, finishing and painting,


welding, Flange Jointing, installation, inspections and testings and
miscellaneous materials for connecting and installation.

BF6. 127 Valves and sensors for all systems incorporated in the pump station as
listed in the particular specifications volume 2A section 1.4 ls 1

Distribution pipe, Finished water, pump discharge pipe to header pipe,


BF6. 128 SP, ND300 mm, ND450 mm, ND800 mm ls 1 -

BF6. 129 Pump Distribution Header Pipe, DN800 ls 1 -


Flow Meter Bypass Valve, DN 800
BF6. 130 ls 1 -
intake ventilation fan, wall mounted, axial flow type 1000m3/h @ 2300
BF6. 131 Pa, inclusive of back draft shutters nr 4 -

discharge ventilation fanwall mounted, axial flow type 1000m3/h @


BF6. 132 2300 Pa, inclusive of back draft shutters nr 2 -

intake fan ducting inclusive of discharge grills


BF6. 133 ls 1 -
Cat Walk specified in the Drawings
BF6. 134 ls 1 -
Thrust Block in the Distribution Pump Station as specified and in
BF6. 135 Drawings ls 1 -
Plant Water System Pipes ND80 and 150 specified in the Drawings
BF6. 136 ls 1 -
Plant Water System Isolation Valve, ND150
BF6. 137 nr 1 -
Plant Water Pressure Reducing Valve, ND150
BF6. 138 nr 1 -
Miscellaneous valves at distribution pump station up to ND100
BF6. 139 ls 1 -
HVAC work for Pump Station including supply and installation of air
conditioning unit and accessories, plumbing and other miscellaneous
BF6. 140 equipment specified in the Drawings. ls 1 -

Supply and Installation of Fire extinguisher ABC type 9 KG inclusive


BF6. 141 with wall mounting hooks and signage. nr 7 -

Supply and Installation of Fire extinguisher CO2 type 9 KG inclusive


BF6. 142 with wall mounting hooks and signage. nr 4 -

(4) Clear Water Reservoir


Clear water reservoir inlet isolation valve, ND800, with extension stem
BF6. 143 and manual floor stand operator nr 2 -

Clear water reservoir outlet butterfly valve, ND800, with extension stem
BF6. 144 and manual floor stand operator nr 3 -

Clear water reservoir drain valve, ND 200, with extension spindle


BF6. 145 nr 3 -
Pipes, Fittings, Flexible Joint, Valves and other miscellaneous work
BF6. 146 specified in the Drawings and the Specifications and not included ls 1 -
elsewhere in Bill 6-6
Stainless Steel SS316 ladders (5m x 400mm wide x 150mm step) for
BF6. 147 each main access point including safety hoop anchored at top and nr 20 -
bottom with SS316 bolts

Sub-total for Part 6-6. Distribution Pump Station, CARRIED TO PART SUMMARY -
Part 6-7. Miscellaneous WTP Piping and Equipment

Mechanical lifting hoist on a rotating pole and boom set up with a


capacity of 1500kg and set up so each of the 2 pumps installed can be
BF6. 148 lifted up out of the sludge drainage basin nr 1 -

Supply and install yard piping as shown on the drawings including all
excavation, backfill, valves, fittings and testing up to the limits of Lot 1
BF6. 149 for WTP facilities ls 1 -

Fire fight piping distributing the water to hose reels over the premises,
Steel pipe DN 100 schedule 40 installed underground and protected
BF6. 150 with bituminous lining for corrosion protection m 300 -

Fire hose reel cabinets red painted steel cabinets complete with
pressure gauge pressure reducing valve 30 meters hose of 25 mm
BF6. 151 diameter inclusive with an adjustable nozzle nrs 5 -

BF6. 152 Fire


Pump
Fighting nr 2 -

Sub-total for Part 6-7. Miscellaneous Equipment, CARRIED TO PART SUMMARY -

PART SUMMARY FOR Bill 6


Sub-total for Part 6-1. Coagulation, Flocculation, Sedimentation and Filtration Block - CFSF block, CARRIED TO PART -
SUMMARY
Sub-total for Part 6-2. Drainage Tanks, CARRIED TO PART SUMMARY
Sub-total for Part 6-3. Sludge Lagoons, CARRIED TO PART SUMMARY -
Sub-total for Part 6-4. Administration building, CARRIED TO PART SUMMARY -
Sub-total for Part 6-5. Chemical building, CARRIED TO PART SUMMARY -
Sub-total for Part 6-6. Distribution Pump Station, CARRIED TO PART SUMMARY -
Sub-total for Part 6-7. Miscellaneous WTP Piping and Equipment, CARRIED TO PART SUMMARY -

Sub-total for Bill 6, CARRIED TO GRAND SUMMARY -


Page 62/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

BF6. BILL 6 – MECHANICAL WORKS FOR WATER TREATMENT PLANT

Bill 6-1 – Treatment Facilities (Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin)
Note: The bidder who intends to propose the contractor's alternative
design for this part shall fill in the form "Part 8.1 Contractor's
Alternative design - Treatment Facilities (Receiving Well and
Coagulation Basin, Flocculation and Sedimentation Basin)" and may
leave the rates or bidder’s estimated quantities of this part blank.

Flocculation and Sedimentation Basin

Piping Works including supply of materials, finishing and painting,


welding, jointing, installation work as shown in the drawings and the
specifications, inspections and testings and miscellaneous materials for
connecting and installation.

Flocculation Basin Flocculation Basin Inlet Gate


BF6. 01 Inlet Gate nr 4 1,275.38 - - 5,101.52 - -

Sedimentation Basin Drain Pipe, DIP ND 250 and 300


BF6. 02 ls 1 20,396.17 - - 20,396.17 - -

Sedimentation Basin Drain Valve ND200


BF6. 03 GV-SED-1 to 8 nr 8 536.74 - 31.10 4,293.92 - 248.80

Sedimentation Basin Drain Main Valve ND 300


BF6. 04 GV-SED-9 nr 1 1,116.27 - 44.77 1,116.27 - 44.77

Sedimentation Basin Drain Main Valve ND 300


BF6. 05 BV-SE-DM-1 nr 1 412.81 - 44.77 412.81 - 44.77

BF6. 06 Sludge Extraction Pipe (A) DIP ND150 and ND200 ls 1 29,079.15 - - 29,079.15 - -

MOPLV-SE-A1 to Sludge Extraction Valve, ND150


BF6. 07 A16 nr 16 - 8,304 23.32 - 132,869 373.12

Bidder's Signature or Initials ...........................................


Page 63/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

BF6. 08 GV-SXI-A1 to A16 Isolation Valve ND 150 with Operation Stage nr 16 366.29 - 23.32 5,860.64 - 373.12

BF6. 09 Sludge Extraction Pipe (B) PVC, DIP and SP, ND200 and ND150 ls 1 4,390.32 - 55,401.82 4,390.32 - 55,401.82

BF6. 10 MOPLV-SE-B1 to Sludge Extraction Valve ND150 nr 16 - 9,538 23.32 - 152,603 373.12
B16

BF6. 11 GV-SXI-B1 to B16 Isolation Valve ND 150 nr 16 366.29 - 23.32 5,860.64 - 373.12

BF6. 12 MOPLV-SE-M1 Sludge Extraction Valve ND200 nr 1 - 9,538 31.09 - 9,538 31.09

GV-SEBY-1 Sludge Discharge Tower By-pass Valve ND200


BF6. 13 nr 1 536.74 - 31.09 536.74 - 31.09

BF6. 14 Sludge Extraction Pipe Flushing Pipe, DIP ND 100 to 200 ls 1 459.75 447 - 459.75 447 -

BF6. 15 CV-SEFLS-1 Sludge Extraction Pipe Flushing Check Valve ND200 nr 1 350.69 - 31.09 350.69 - 31.09

BF6. 16 BV-SEFLS-1 Sludge Extraction Pipe Flushing Flow Control Valve nr 1 - 2,670 31.09 - 2,670 31.09
ND200

BF6. 17 MOBV-SEFLS-1 Sludge Extraction Pipe Flushing Isolation Valve ND200 nr 1 4,884.92 - 31.09 4,884.92 - 31.09

BF6. 18 MOBV-SEFLS-BY-1 Sludge Extraction Pipe Flushing By-pass Valve ND150 nr 1 - 9,230 23.32 - 9,230 23.32

GV-SED Sedimentation Basin Outlet Conduit Drain Valve,


BF6. 19 ND100 nr 1 390.11 - 12.95 390.11 - 12.95

C-SE-SHC-1 & 2 Equipment Handling Crane,0.5 ton


BF6. 20 set 2 5,767.77 - 129.55 11,535.54 - 259.10

P-SASEW-1 & 2 Settled Water Sampling Pump


BF6. 21 set 2 - 8,274 129.55 - 16,548 259.10

Bidder's Signature or Initials ...........................................


Page 64/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
EF-SED Sedimentation Pipe Gallery Exhaust Fan
BF6. 22 nr 2 - - 129.55 - - 259.10

Steel works
- - - - - -

Steel Work Flocculation Basin Drain Gate


BF6. 23 nr 60 - - 111.78 - - 6,706.80

Steel Work Flocculation Basin Weir


BF6. 24 nr 48 - - 263.00 - - 12,624.00

Steel Work Catwalk for each basin


BF6. 25 nr 16 - - 394.50 - - 6,312.00

Miscellaneous piping works including all valves and fittings, finishing and
painting, welding, installation work as shown in the drawings and the
BF6. 26 specifications. ls 1 - - 1,959.67 - - 1,959.67

Other miscellaneous mechanical works items that are shown on the


drawings or specified for Receiving Well and Coagulation Basin,
Flocculation and Sedimentation Basin but not itemized in the BOQ
including any items deemed necessary by the Contractor to complete
BF6. 27 the works. ls 1 - - - - - -

Sub-total for Bill 6-1 – Treatment Facilities (Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin), CARRIED TO PART 94,669.19 323,905 85,804.13
SUMMARY

Bidder's Signature or Initials ...........................................


Page 65/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

Bill 6-2 – Treatment Facilities (Filtration Basin)


Note: The bidder who intends to propose the contractor's alternative
design for this part shall fill in the form "Part 8.2 Contractor's
Alternative design - Treatment Facilities (Filtration Basin)" and may
leave the rates or bidder’s estimated quantities of this part blank.

(1) Pumps and Blowers

P-BW-1 to 3 Backwash Pump, 12 CMM x 10 m x 980 min-1


BF6. 28 nr 3 - - -

Spare parts for Backwash Pumps as specified in the Specifications


BF6. 29 set 1 - - -

AB-FAS-1 & 2 Air Scouring Blower


BF6. 30 nr 2 - - -

Spare parts for Air Scouring Blowers as specified in the Specifications


BF6. 31 set 1 - - -

P-FSUP-1 to 3 Backwash Pump Station Sump Pump


BF6. 32 nr 2 - - -

Spare parts for Sump Pumps as specified in the Specifications


BF6. 33 set 1 - - -

P-SAFW-1 & 2 Filtered Water Sampling Pump


BF6. 34 set 2 - - -

- - -

(2) Pipes, Valves and Miscellaneous


- - -

Bidder's Signature or Initials ...........................................


Page 66/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Piping Works including supply of materials, finishing and painting,
welding, jointing, installation work as shown in the drawings and the
specifications, inspections and testings and miscellaneous materials for
connecting and installation. - - -

Filter effluent water pipe


BF6. 35 ls 1 - - -

Back wash water pipe


BF6. 36 ls 1 - - -

Air scouring pipe


BF6. 37 ls 1 - - -

Sludge Extraction Pipe Flushing Connecting Pipe


BF6. 38 ls 1 - - -

Sampling Water Pipe


BF6. 39 ls 1 - - -

MOSG-FI-1 to 8 Filter Inlet Gate 600 x 600 mm


BF6. 40 nr 8 - - -

MOBV-FO-1 to 8 Filter Outlet Valve, ND350


BF6. 41 nr 8 - - -

MOBV-BW- 1to 8 Filter Backwash Valve, ND500


BF6. 42 nr 8 - - -

MOBV-AW-1 to 8 Filter Air Scouring Valve, ND300


BF6. 43 nr 8 - - -

MOBLV-AV-1 to 8 Filter Air Vent Valve, ND50


BF6. 44 nr 8 - - -

GV-FDR-1 to 8 Filter Drain Valve, ND100


BF6. 45 nr 8 - - -

EF-F Filter Pipe Gallery Exhaust Fan


BF6. 46 nr 2 - - -

Bidder's Signature or Initials ...........................................


Page 67/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
EF-BWSP Backwash Pump Room Ventilation Fan
BF6. 47 nr 2 - - -

C-BW-SHC Backwash Pump Room Equipment Handling Crane,


BF6. 48 2.0 ton nr 1 - - -

Miscellaneous piping works including all valves and fittings, finishing and
painting, welding, installation work as shown in the drawings and the
BF6. 49 specifications. ls 1 - - -

Other miscellaneous mechanical works items that are shown on the


drawings or specified for Filtration Basin but not itemized in the BOQ
BF6. 50 including any items deemed necessary by the Contractor to complete ls 1 - - -
the works.

Sub-total for Bill 6-2 – Treatment Facilities (Filtration Basin), CARRIED TO PART SUMMARY - - -

Bidder's Signature or Initials ...........................................


Page 68/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

Bill 6-3 – Chemical Feed System


(4-3-1) PAC Feed System

MX-PAC-1 & 2 PAC Mixer


BF6. 51 nr 2 12,166.54 - 1,619.26 24,333.08 - 3,238.52

P-PACTR -1 & 2 PAC Transfer Pump


BF6. 52 nr 2 - 26,963 323.85 - 53,927 647.70

AB-PAC- 1 & 2 PAC Circulation Blower


BF6. 53 nr 2 - 10,267 161.93 - 20,534 323.86

P-PACF- 1 to 3 PAC Feed Pump


BF6. 54 nr 3 - 13,048 971.55 - 39,145 2,914.65

T-PAC- 1 to 4 PAC Storage Tank, FRP 25m3


BF6. 55 nr 4 8,137.39 - 3,238.52 32,549.56 - 12,954.08

TC-PAC-1 PAC Calibration Tank, FRP 1.5m3


BF6. 56 nr 1 1,054.72 - 323.85 1,054.72 - 323.85

TEL-PAC-1 PAC Elevated Tank, PVC 150L


BF6. 57 nr 1 1,017.13 - 97.16 1,017.13 - 97.16

TD(DT)-PAC-1 PAC Dilution Tank, PVC 290L


BF6. 58 nr 1 1,314.32 - 97.16 1,314.32 - 97.16

C-CHB-MOCH-1 Chemical Handling Hoist, 1.5ton


BF6. 59 Set 1 7,984.56 - 3,690.00 7,984.56 - 3,690.00

EF-CHA- 1 to 4 Ventilation Fan A


BF6. 60 nr 4 - 203 129.54 - 811 518.16

EF-CHB- 1 to 4 Ventilation Fan B


BF6. 61 nr 4 - 203 129.54 - 811 518.16

EF-CHC- 1 to 6 Ventilation Fan C


BF6. 62 nr 6 - 203 129.54 - 1,217 777.24

EF-CHD- 1 to 5 Ventilation Fan D


BF6. 63 nr 5 - 203 129.54 - 1,014 647.70

Bidder's Signature or Initials ...........................................


Page 69/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Pipes, Fittings, Flexible Joint, Valves and other miscellaneous work
specified in the Drawings and the Specifications and not included in Bill
BF6. 64 6-3-1 ls 1 50,699.09 - 26,347.86 50,699.09 - 26,347.86

(4-3-2) Lime Feed System

LM-FD Lime Feeder, Volumetric screw feeder with storage


BF6. 65 hopper nr 3 72,893.43 - 129.54 218,680.29 - 388.62

T-LM Lime Preparation Tank, Steel 1.5 m3


BF6. 66 nr 3 11,500.64 - 369.00 34,501.92 - 1,107.00

MX-LM-1 to 3 Lime Mixer, Mechanical mixer with support beam


BF6. 67 and legs nr 3 6,649.05 - 129.54 19,947.15 - 388.62

P-LMTR-1 to 3 Lime Transfer Pump, 200 L/min x 12 m


BF6. 68 nr 3 10,718.87 - 323.85 32,156.61 - 971.55

DSC-LM-1 Dust Collector, Package type, self-standing, self-


BF6. 69 contained multi filter nr 1 5,520.95 - 97.16 5,520.95 - 97.16

SL-LM-1 to 3 Lime Slide


BF6. 70 Unit 3 2,650.10 - 97.16 7,950.30 - 291.48

Pipes, Fittings, Flexible Joint, Valves and other miscellaneous work


specified in the Drawings and/or the Specifications and not included in
BF6. 71 Bill 6-3-2 ls 1 619.21 2,682 16,747.85 619.21 2,682 16,747.85

Sub-total for Bill 6-3 – Chemical Feed System, CARRIED TO PART SUMMARY 438,328.89 120,139 73,088.38

Bidder's Signature or Initials ...........................................


Page 70/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

Bill 6-4– Chlorine Feed System


C-CLB-MOWH-1 Container Handling Hoist
BF6. 72 Set 1 8,611.51 - - 8,611.51 - -

CLB-WS-1 & 2 Weighing Scale


BF6. 73 Unit 2 34,890.43 - 1,845.00 69,780.86 - 3,690.00

CHCO-1 to 36 Chlorine Container


BF6. 74 set 36 5,478.54 - 1,599.00 197,227.44 - 57,564.00

CLB-CH-1 to 4 Chlorinator
BF6. 75 Unit 4 18,839.42 - 1,295.41 75,357.68 - 5,181.64

Chlorination system control panel


BF6. 76 Unit 1 30,102.05 - 1,619.26 30,102.05 - 1,619.26

CLB-NU-1 Neutralization System


BF6. 77 Unit 1 217,944.99 - 1,619.26 217,944.99 - 1,619.26

CLB-LEAK-1 to 8 Chlorine Gas Leakage Detector


BF6. 78 Unit 8 3,990.32 - 1,619.26 31,922.56 - 12,954.08

EF-CLB1-1 to 7 Ventilation Fan 1


BF6. 79 Unit 7 - 203 1,619.26 - 1,419 11,334.82

EF-CLB2- 1 Ventilation Fan 2


BF6. 80 Unit 1 - 203 161.93 - 203 161.93

P-CLBOP-1 to 4 Chlorine Water Booster Pump


BF6. 81 Unit 4 - 203 161.93 - 811 647.72

Pipes, Fittings, Flexible Joint, Valves and other miscellaneous work


specified in the Drawings and the Specifications and not included in Bill
BF6. 82 6-4 ls 1 574.67 - 47,813.25 574.67 - 47,813.25

Sub-total for Bill 6-4– Chlorine Feed System, CARRIED TO PART SUMMARY 631,521.76 2,433 142,585.96

Bidder's Signature or Initials ...........................................


Page 71/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Part 6-5. Distribution Pump Station

(1) Pumps

Supply and Installation of Pumps as specified in the Specifications and


the Drawings

P-DP-1 to 5 Distribution Pumps, 60m x 18.75 m3/min duty with


≧280kW motors and Fly Wheel and accessories
BF6. 83 nr 5 - 57,801 6,477.03 - 289,004 32,385.15

Spare parts for Distribution Pumps as specified in the Specifications


BF6. 84 set 1 - 28,868 - - 28,868 -

P-NFP 1 to 3 Night Flow Pumps, 30m x 5 m3/min duty with


BF6. 85 ≧37kW motors nr 3 6,921.78 - 3,238.52 20,765.34 - 9,715.56

Spare parts for Night Flow Pumps as specified in the Specifications


BF6. 86 set 1 248.25 - - 248.25 - -

P-DP-SU 1 to 4 Pump Station Sump Pumps, 200 L/min x 12m


BF6. 87 nr 4 855.86 - 129.54 3,423.44 - 518.16

P-DP-SU 5 Pump Station Sump Pumps, 200 L/min x 12m (Supply


BF6. 88 only) nr 1 855.86 - 129.54 855.86 - 129.54

Spare parts for Submersible Sump Pumps as specified in the GS 15.5.5.


BF6. 89 set 1 337.23 - - 337.23 - -

(2) Cranes and Hoists - - -


Supply and Installation of cranes and hoists with accessories as specified
in the Specifications and the Drawings - - -

C-DP-SB-WH-1 Single beam motorized bridge crane, 3 ton


BF6. 90 set 1 13,227.08 - 1,845.00 13,227.08 - 1,845.00

C-DP-HCH1-1 Hand-operated chain hoist with geared trolley, 3 ton


BF6. 91 set 1 4,336.35 - 1,845.00 4,336.35 - 1,845.00

Bidder's Signature or Initials ...........................................


Page 72/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
C-DP-HCH2-1 & 2 Hand-operated chain hoist with plane trolley, 0.5 ton
BF6. 92 set 2 1,222.99 - 369.00 2,445.98 - 738.00

C-DP-HCH3-1 Hand-operated chain hoist with plane trolley, 0.5 ton


BF6. 93 set 1 2,870.11 - 369.00 2,870.11 - 369.00

(3) Pipes, Valves and Miscellaneous

Piping Works including supply of materials, finishing and painting,


welding, Flange Jointing, installation, inspections and testings and
miscellaneous materials for connecting and installation.

FW-DPS-1 and 2 Suction pipe, Wall embedded pipe, Finished water,


pump suction pipe, DIP, SP ND700 mm and 400 mm
BF6. 94 ls 1 33,517.13 - 26,061.41 33,517.13 - 26,061.41

FW-DPD-1 and 2 Distribution pipe, Finished water, pump discharge


pipe to header pipe, SP, ND250 mm, ND450 mm,
BF6. 95 ND700 mm ls 1 1,887.05 - 119,539.55 1,887.05 - 119,539.55

FW-NFPS-1 and 2 Night flow pipe, Finished water, pump suction pipe
DIP and SP, ND150 and ND300 with miscellaneous
BF6. 96 valves including GV-NFP-MFTI, MOGV-NFP-MFT ls 1 254.59 - 3,062.13 254.59 - 3,062.13

FW-NFPD-1 Night flow pipe, Finished water, pump discharge


BF6. 97 pipe, DIP and SGP ND80mm, SGP ND125 mm, SP ls 1 254.59 - 4,642.83 254.59 - 4,642.83
ND250 mm, SP ND450 mm

FW-CLBP-1 to 3 Pipe for chlorination, Finished water, suction pipe,


BF6. 98 DIP and SGP, ND80 to 150 mm ls 1 - - 5,111.44 - - 5,111.44

FW-PLW-1 Plant water pipe, Finished water, SGP ND150 mm,


BF6. 99 ND80 mm and ND25 mm ls 1 - - 8,461.60 - - 8,461.60

DP-DR-1 and 2 Drain pipe, Station drain water, SGP ND80 mm, Soft
BF6. 100 PVC flexible pipe ND80mm ls 1 - - 2,284.27 - - 2,284.27

Bidder's Signature or Initials ...........................................


Page 73/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
GV-DP-S Pump Suction Valves for Distribution Pump, ND700
BF6. 101 nr 5 11,661.04 - 192.50 58,305.20 - 962.50

Bidder's Signature or Initials ...........................................


Page 74/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
CV-DP Pump Discharge Check Valves for Distribution Pump,
BF6. 102 ND450 nr 5 3,537.39 - 77.37 17,686.95 - 386.85

MOBV-DP-T Pump Discharge Valve for Distribution Pump, ND450


BF6. 103 nr 5 5,779.34 - 77.37 28,896.70 - 386.85

GV-DP-TI Pump Discharge Isolation Valve for Distribution


BF6. 104 Pump, ND450 nr 5 3,921.10 - 77.37 19,605.50 - 386.85

GV-DP-FMI Pump Discharge Header Pipe Isolation Valve, ND700


BF6. 105 nr 1 11,661.04 - 192.50 11,661.04 - 192.50

MOBV-DP-FC Pump Distribution Header Pipe, Flow Control, ND700


BF6. 106 nr 1 - 25,110 192.50 - 25,110 192.50

BV-DP-FMB Flow Meter Bypass Valve, ND700


BF6. 107 nr 1 2,201.65 - 192.50 2,201.65 - 192.50

GV-NFP-S Pump Suction Valves for Night flow Pump, ND150


BF6. 108 nr 3 390.23 - 23.32 1,170.69 - 69.96

CV-NFP Pump Discharge Check Valves for Night flow Pump,


BF6. 109 ND125 nr 3 71.02 - 19.43 213.06 - 58.29

MOGV-NFP-T Pump Discharge Valve for Night flow Pump, ND125


BF6. 110 nr 3 5,235.39 - 19.43 15,706.17 - 58.29

GV-NFP-SI Pump Suction Isolation Valve for Night Flow Pumps,


BF6. 111 ND300 nr 1 1,200.41 - 44.77 1,200.41 - 44.77

GV-NFP-DI Pump Discharge Isolation Valve for Night flow Pump,


BF6. 112 ND250 nr 1 898.68 - 37.31 898.68 - 37.31

GV-CLBOP-SI Inlet Valves for chlorination, ND150


BF6. 113 nr 1 390.23 - 23.32 390.23 - 23.32

SF-DP Ventilation Supply Fans


BF6. 114 nr 4 - 203 129.54 - 811 518.16

Cat Walk specified in the Drawings MDS-M-002 to 009


BF6. 115 ls 1 - - 23,317.58 - - 23,317.58

Bidder's Signature or Initials ...........................................


Page 75/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Thrust Block in the Distribution Pump Station as specified in MDS-M-002
BF6. 116 to 007 ls 1 Included in D.3 - - -

Plant Water System Pipes ND80 and 150 specified in the Drawing M-DP-
BF6. 117 M014 ls 1 - - 1,212.64 - - 1,212.64

GV-DPPW-1 & 2 Plant Water System Isolation Valve, ND150


BF6. 118 nr 2 179.88 - 38.05 359.76 - 76.10

PRDV-DPPW-1 Plant Water Pressure Reducing Valve, ND150


BF6. 119 nr 1 - 4,015 23.32 - 4,015 23.32

SWT-A and SWT-B Supply and Installation of Sampling Water Storage


BF6. 120 Tanks nr 2 1,684.58 - 23.32 3,369.16 - 46.64

Miscellaneous valves at distribution pump station up to ND100 inclding


GV-NFP-MFTI, MOGV-NFP-MFT, AV-DP-HP, GV-DP-HPAV, GV-DPHP-P,
BF6. 121 GV-DP-BLO, BLV-CLBOP-S, GV-CLBOP, BLV-CLBOP, CV-DP-SU, GV-DPPW- ls 1 6,257.49 - 1,262.18 6,257.49 - 1,262.18
BY, GV-DP-BLO and FM-CL

(4) Clear Water Reservoir - - - - - -


BV-CRIV-1 & 2 Clear water reservoir inlet isolation valve, ND800,
with extension stem and manual floor stand operator
BF6. 122 nr 2 3,302.48 - 277.21 6,604.96 - 554.42

SG-CRO-1 & 2 Clear water reservoir outlet gate, ND800, with


BF6. 123 extension stem and manual floor stand operator nr 2 5,314.08 - 277.21 10,628.16 - 554.42
GV-CR-1 & 2 Clear water reservoir drain valve, ND 200, with
BF6. 124 extension spindle nr 2 620.87 - 31.10 1,241.74 - 62.20

Sub-total for Part 6-5. Distribution Pump Station, CARRIED TO PART SUMMARY 270,820.55 347,808 247,328.79

Bidder's Signature or Initials ...........................................


Page 76/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Part 6-6. Drainage Basin and Sludge Lagoon

(1) Pumps

P-DBWWR-1 to 4 Wash Waste Water Return Pump


BF6. 127 nr 4 10,442.41 - 971.55 41,769.64 - 3,886.20

P-DBSL-1 & 2 Sludge Drain Pump


BF6. 128 nr 2 - 4,686 161.93 - 9,372 323.86

(2) Pipes, Valves and Miscellaneous


- - - - - -

Piping Works including supply of materials, finishing and painting,


welding, Flange Jointing, installation, inspections and testings and
miscellaneous materials for connecting and installation. - - - - - -

Steel Pipes, Welded and Flanged Joint as specified in M-DB-G-001 and


BF6. 129 002 ls 1 - - 18,630.93 - - 18,630.93

SG-TDBI-1& 2 Drainage Basin Inlet Gate, 600x600


BF6. 130 nr 2 4,038.70 - - 8,077.40 - -

SG-TDBOA-1& 2 Drainage Basin Outlet Gate A, 600x600


BF6. 131 nr 2 3,932.42 - - 7,864.84 - -

SG-TDBOB-1& 2 Drainage Basin Outlet Gate B, 300x300


BF6. 132 nr 2 2,231.91 - - 4,463.82 - -

CV-DBWWR-1to 3 Pump Discharge Check Valves for WWWR Pump,


BF6. 133 ND200 nr 3 175.34 - 31.09 526.02 - 93.27

GV-DBWWR-1 to Return pump Discharge Valve, ND200


BF6. 134 3 nr 3 908.83 - 31.09 2,726.49 - 93.27

GV-DBWWR-4 to Pump Discharge By-pass Valve for WWWR Pump,


BF6. 135 6 ND150 nr 3 547.62 - 23.32 1,642.86 - 69.96

GV-DBWWR-7 to Pump Discharge By-pass Valve for WWWR Pump,


BF6. 136 8 ND100 nr 2 343.08 - 12.95 686.16 - 25.90

Bidder's Signature or Initials ...........................................


Page 77/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
GV-TDBSL-1 &2 Pump Discharge Isolation Valve for Sludge Drain
BF6. 137 Pump, ND100 nr 2 343.08 - 12.95 686.16 - 25.90

BV-DBWWR-1 Wash Waste Water Return Isolation Valve, ND350


BF6. 138 nr 1 481.61 - 53.73 481.61 - 53.73

GV-DBSL-1 Sludge Drain Valve, ND350


BF6. 139 nr 1 3,929.08 - 53.73 3,929.08 - 53.73

C-DB-JBCH-1 Pump Handling Jib Crane, 0.5ton


BF6. 140 set 1 4,040.88 - 323.85 4,040.88 - 323.85

Pipes, Fittings, Flexible Joint, Valves and other miscellaneous work


specified in the Drawings and the Specifications and not included in Bill
BF6. 141 6-6 ls 1 - - 73.96 - - 73.96

Sub-total for Part 6-6. Drainage Basin and Sludge Lagoon, CARRIED TO PART SUMMARY 76,894.96 9,372 23,654.56

Bidder's Signature or Initials ...........................................


Page 78/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)
Part 6-7. Equipment

Supply and Installation of Inclined Tube Settler


BF6. 142 m2 691 128.31 - - 88,662.21 - -
Supply and Installation of Filter Sand with 5% spare
BF6. 143 m3 570 - - 15.78 - - 8,994.60
Supply and Installation of Filter Under Drain including IMS caps,
BF6. 144 accessories and spare parts m2 543 - - 36.90 - - 20,036.70
FM-SEFLS-1 Orifice Flow Meter, ND200
BF6. 145 nr 1 - 163 31.09 - 163 31.09
MF-FBW-1 Orifice Flow Meter, ND450
BF6. 146 nr 1 - 234 77.37 - 234 77.37
FM-FAS-1 Orifice Flow Meter, ND300
BF6. 147 nr 1 - 192 44.77 - 192 44.77
HPTR-1 & 2 Hand Pallet Truck
BF6. 148 nr 2 - - - - - -
HLF-1 & 2 Hand Lifter
BF6. 149 nr 2 - - - - - -
FFHC-1 to 10 Fire Fighting Hose Cabinet with Hose and Nozzle Sets
BF6. 150 ls 1 16,101.00 - 64.77 16,101.00 - 64.77
AQU - 1 Supply and Installation of Aquarium
BF6. 151 nr 1 - 6,691 971.55 - 6,691 971.55
P-SUPPO-1 & 2 Portable Sump Pump
BF6. 152 nr 2 3,856.93 - 971.55 7,713.86 - 1,943.10
Supply and Installation of Laboratory Equipment shown in the
BF6. 153 Specifications and drawings ls 1 - 16,729 - - 16,729 -
FLTR-1 Forklift Truck
BF6. 154 unit 1 - - - - - -
DTCR-1 and 2 Diesel Engine Truck Crane
BF6. 155 unit - - - - - - -

Sub-total for Part 6-7. Equipment, CARRIED TO PART SUMMARY 112,477.07 24,009 32,163.95

Bidder's Signature or Initials ...........................................


Page 79/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL 6 - MECHANICAL WORKS FOR INTAKE WATER TREATMENT PLANT BILL-6

FC LC FC LC
ITEM ITEM DESCRIPTION UNIT QUANTITY RATE RATE RATE Amount Amount Amount
(USD) (OTHER) (USD) (USD) (OTHER) (USD)

PART SUMMARY FOR Bill 6

Sub-total for Bill 6-1 – Treatment Facilities (Receiving Well and Coagulation Basin, Flocculation and Sedimentation Basin), CARRIED TO PART 94,669.19 323,905.00 85,804.13
SUMMARY

Sub-total for Bill 6-2 – Treatment Facilities (Filtration Basin), CARRIED TO PART SUMMARY - - -

Sub-total for Bill 6-3 – Chemical Feed System, CARRIED TO PART SUMMARY 438,328.89 120,139.43 73,088.38

Sub-total for Bill 6-4– Chlorine Feed System, CARRIED TO PART SUMMARY 631,521.76 2,433.06 142,585.96

Sub-total for Part4-5. Distribution Pump Station, CARRIED TO PART SUMMARY 270,820.55 347,807.55 247,328.79

Sub-total for Part4-6. Drainage Basin and Sludge Lagoon, CARRIED TO PART SUMMARY 76,894.96 9,372.28 23,654.56

Sub-total for Part4-7. Equipment, CARRIED TO PART SUMMARY 112,477.07 24,009.12 32,163.95

Sub-total for Bill 6, CARRIED TO GRAND SUMMARY 1,624,712.42 827,666 604,626

Bidder's Signature or Initials ...........................................


Page 80/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

BF7. BILL 7 – ELECTRICAL WORKS FOR WATER TREATMENT PLANT

All items are supply and install including ancillaries.

Bill 7-1. Treatment Facilities

Panel boards and motor control centres as per panel drawings, one line
diagrams and specifications
Main Distribution Panel
BF7. 01 nr 1 -

MCC for Backwash


BF7. 02 nr 1 -
Aux. Relay Panel for Backwash
BF7. 03 nr 1 -

MCC for Sludge Extraction-1


BF7. 04 nr 1 -

Aux. Relay Panel for Sludge Extraction-1


BF7. 05 nr 1 -
MCC for Sludge Extraction-2
BF7. 06 nr 1 -

Aux. Relay Panel for Sludge Extraction-2


BF7. 07 nr 1 -

MCC for Filter Motorized Valve-1


BF7. 08 nr 1

Aux. Relay Panel for Filter Motorized Valve-1


BF7. 09 nr 1

MCC for Filter Motorized Valve-2


BF7. 10 nr 1

Aux. Relay Panel For Filter Motorized Valve-2


BF7. 11 nr 1

MCC for Filter Motorized Valve-3


BF7. 12 nr 1

Aux. Relay Panel for Filter Motorized Valve-3


BF7. 13 nr 1

MCC for Filter Motorized Valve-4


BF7. 14 nr 1

Aux. Relay Panel for Filter Motorized Valve-4


BF7. 15 nr 1

MCC for Chlorination Control


BF7. 16 nr 1 -

Aux. Relay Panel for Chlorination control


BF7. 17 nr 1 -

Instrumentation Panel
BF7. 18 nr 1 -

I/O Panel
BF7. 19 nr 1 -

Field Control Station Panel


BF7. 20 nr 1

Front Part Sludge Extraction Local Control Panel


BF7. 21 nr 1 -

Bidder's Signature or Initials ...........................................


Page 81/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
End Part Sludge Extraction Local Control Panel
BF7. 22 nr 1 -

Settled Water Sampling Pump Local Control Panel


BF7. 23 nr 1 -

Filter Local Control Panel


BF7. 24 nr 4 -

Backwash Pump Station Local Control Panel


BF7. 25 nr 1 -

Maintenance Power Supply Panel


BF7. 26 nr 2 -

Backwash Pump Station Sump Pump Pit Level Switch


BF7. 27 nr 1 -

Receiving Well Level Switch


BF7. 28 nr 1 -
Filter Inlet Level Switch
BF7. 29 nr 1

Filter Water Level


BF7. 30 nr 8 -

Filter Outlet Conduit Level


BF7. 31 nr 1 -

Blower DB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 32 description and schematics nr 1

Filter valve panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 33 description and schematics nr 8

Sump pump (valve room) panel inclusive of all


switches/sensors/cables/means of communication with other system
BF7. 34 components as indicated in panel description and schematics nr 1

Sump pump (valve gallery) panel inclusive of all


switches/sensors/cables/means of communication with other system
BF7. 35 components as indicated in panel description and schematics nr 1

Drain valve panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 36 description and schematics nr 1

Clean pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 37 description and schematics nr 1

Fire pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 38 description and schematics nr 1

Sub-total for Bill 7-1. Treatment Facilities, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 82/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-2. Distribution Pump Station & Clear Water Reservoir


No.1 LV Incoming Panel
BF7. 39 nr 1 -
No.2 LV Incoming Panel
BF7. 40 nr 1 -
Bus Tie Panel
BF7. 41 nr 1 -
No.1 LV Feeder Panel
BF7. 42 nr 1 -

No.2 LV Feeder Panel


BF7. 43 nr 1 -

No.1 Distribution Pump Panel


BF7. 44 nr 1 -

No.1 Distribution Pump Bypass Panel


BF7. 45 nr 1 -

No.2 Distribution Pump Panel


BF7. 46 nr 1 -

No.2 Distribution Pump Bypass Panel


BF7. 47 nr -

No.3 Distribution Pump Panel


BF7. 48 nr 1 -

No.3 Distribution Pump Bypass Panel


BF7. 49 nr -

No.4 Distribution Pump Panel


BF7. 50 nr 1 -

No.4 Distribution Pump Bypass Panel


BF7. 51 nr -

No.5 Distribution Pump Panel


BF7. 52 nr 1 -

No.5 Distribution Pump Bypass Panel


BF7. 53 nr -

No.1 Night Flow Pump Panel


BF7. 54 nr 1

No.2 Night Flow Pump Panel


BF7. 55 nr 1

No.3 Night Flow Pump Panel


BF7. 56 nr 1

Battery Panel
BF7. 57 nr 1 -

DC Power Supply Panel


BF7. 58 nr 1 -

CVCF Panel
BF7. 59 nr 1 -

MCC for Pump Station


BF7. 60 nr 1 -

Aux. Relay Panel for Pump Station


BF7. 61 nr 1 -

MCC for Drainage Basin


BF7. 62 nr 1 -

Bidder's Signature or Initials ...........................................


Page 83/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Aux. Relay Panel for Drainage Basin
BF7. 63 nr 1 -

Instrumentation Panel
BF7. 64 nr 1 -

I/O Panel
BF7. 65 nr 1 -

Field Control Station Panel


BF7. 66 nr 1

Distribution Pump Local Control Panel


BF7. 67 nr 5 -

Night Flow Pump Local Control Panel


BF7. 68 nr 1 -

Pump Station Drainage Pump Local Control Panel


BF7. 69 nr 2 -

Ventilation Supply Fan Local Control Panel


BF7. 70 nr 2 -

Chlorine Water Booster Pump Local Control Panel


BF7. 71 nr 1 -

Pump Station Drainage Pump Pit Level Switch


BF7. 72 nr 2 -

Clear Water Reservoir Level Switch


BF7. 73 nr 2 -

Clear Water Reservoir Water Level sensors including all cabling and
BF7. 74 supports nr 2 -

Pump Well Level sensors including all cabling and supports


BF7. 75 nr 1 -

Distribution Pipe Pressure sensors including all cabling


BF7. 76 nr 1 -

Distribution Flow Meter (ultrasonic clamp-on type DN800) including all


BF7. 77 transmitters, cabling and accessories as specified in Particular nr 1 -
Specifications section 16.10.3 located in the distribution PS

Backwash Flow Meter (electromagnetic full bore type DN400) including


BF7. 78 all transmitters, cabling and accessories as specified in Particular nr 1 -
Specifications section 16.10.2 located in the distribution PS.

Maintenance Power Supply Panel


BF7. 79 nr 2 -

Pump DB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 80 description and schematics nr 1 -

Backwash pump panel inclusive of all switches/sensors/cables/means


of communication with other system components as indicated in panel
BF7. 81 description and schematics nr 2

Pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 82 description and schematics nr 5

Sump pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 83 description and schematics nr 1

Bidder's Signature or Initials ...........................................


Page 84/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Hoist panel inclusive of all switches/sensors/cables/means of
communication with other system components as indicated in panel
BF7. 84 description and schematics nr 1

Fan panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 85 description and schematics nr 2

Sub-total for Bill 7-2. Distribution Pump Station & Clear Water Reservoir, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 85/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-3. Drainage Basin

Wash Waste Water Return Pump Local Control Panel


BF7. 86 nr 1 -

Drain Pump panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 87 description and schematics nr 1

Drainage Basin Water Level sensors including all cabling and supports
BF7. 88 nr 2 -

Sub-total for Bill 7-3. Drainage Basin, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 86/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-4. Administration Building

Incoming Panel
BF7. 89 nr 1 -

No.1 VCB Panel


BF7. 90 nr 1 -

No.2 VCB Panel


BF7. 91 nr 1 -

No.1 Transformer Primary Panel


BF7. 92 nr 1 -

No.2 Transformer Primary Panel


BF7. 93 nr 1 -

Intake Pump Station Feeder Panel


BF7. 94 nr 1 -

No.1 Transformer
BF7. 95 nr 1 -

No.2 Transformer
BF7. 96 nr 1 -

Step Up Transformer
BF7. 97 nr 1 -

DS Panel
BF7. 98 nr 1 -

Operator Station
BF7. 99 nr 4

Monitoring Station for Director's Room


BF7. 100 nr 1 -

Engineering Station
BF7. 101 nr 1 -
System control computer inclusive of software as required in the system
BF7. 102 specifications nr 2 -

Large Screen Display And Video Controller


BF7. 103 nr 1 -

A4 Color Laser Printer


BF7. 104 nr 1 -

A3 Monochrome Laser Printer


BF7. 105 nr 1 -
Power Distribution Panel
BF7. 106 nr 1 -

Disclosure Server for Distribution Monitoring


BF7. 107 (Web Server) nr 1 -

Field Control Station Panel


BF7. 108 nr 1 -

Telemeter Panel and Modification of Local Station Panel FPMD-LSP-Z2


BF7. 109 to Z7 nr 1 -

Camera System for WTP Inclusive of all cabling/conduiting from camaras


to monitoring station in the Admin building with camara feeds from the
admin building (1 unit), distribution pump room (3 units), generator
BF7. 110 building (3 units), chemical building (2 units), sand filters (4 units) and nr 1 -
perimeter fence (6 units)

Bidder's Signature or Initials ...........................................


Page 87/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Office DB panel inclusive of all switches/sensors/cables/means of
communication with other system components as indicated in panel
BF7. 111 description and schematics nr 1 -

1st floor panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 112 description and schematics nr 1 -

Work shop panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 113 description and schematics nr 1 -

Sub-total for Bill 7-4. Administration Building, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 88/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-5. Chemical Building

Main Distribution Panel


BF7. 114 nr 1 -

MCC for Chemical Building -1


BF7. 115 nr 1 -

Aux. Relay Panel for Chemical Building -1


BF7. 116 nr 1 -

MCC for Chemical Building -2


BF7. 117 nr 1 -

Aux. Relay Panel for Chemical Building -2


BF7. 118 nr 1 -

Instrumentation Panel
BF7. 119 nr 1 -

Instrumentation Panel
BF7. 120 nr 1 -

PAC Transfer Pump Local Control Panel


BF7. 121 nr 1 -

PAC Circulation Blower Local Control Panel


BF7. 122 nr 1 -

PAC Feed Pump Local Control Panel


BF7. 123 nr 1 -

Ventilation Fan A Local Control Panel


BF7. 124 nr 2 -

Ventilation Fan C Local Control Panel


BF7. 125 nr 2 -

Ventilation Fan B Local Control Panel


BF7. 126 nr 2 -

Ventilation Fan D Local Control Panel


BF7. 127 nr 2 -

Ventilation Fan C Local Control Panel


BF7. 128 nr 1 -

Ventilation Fan D Local Control Panel


BF7. 129 nr 1 -

Lime Preparation Tank Local Control Panel


BF7. 130 nr 1 -

PAC Tank Level sensors including all cabling and supports


BF7. 131 nr 4 -

PAC Tank Level Switch including all cabling and supports


BF7. 132 nr 4 -

Lime Preparation Tank Level Switch including all cabling and supports
BF7. 133 nr 3 -

PAC Calibration Tank Level Switch including all cabling and supports
BF7. 134 nr 1 -

Chemical DB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 135 description and schematics nr 1 -

Bidder's Signature or Initials ...........................................


Page 89/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Alum dosing panel inclusive of all switches/sensors/cables/means of
communication with other system components as indicated in panel
BF7. 136 description and schematics nr 1 -

Chlorine dosing panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 137 description and schematics nr 1 -

Lime dosing panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 138 description and schematics nr 1 -

Ventilation panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 139 description and schematics nr 1 -

Pallet lift panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 140 description and schematics nr 1 -

First floor DB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 141 description and schematics nr 1 -

Flow meter panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 142 description and schematics nr 1 -

Sub-total for Bill 7-5. Chemical Building, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 90/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-6. Chlorination Buildings

No.1 Ventilation Fan 1 Local Control Panel


BF7. 146 nr 1 -

No.2 Ventilation Fan 1 Local Control Panel


BF7. 147 nr 1 -

Ventilation Fan 2 Local Control Panel


BF7. 148 nr 1 -

Sub-total for Bill 7-6. Chlorination Buildings, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 91/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-7. Generator Building


No.1 Generator
BF7. 152 ls 1 -

No.2 Generator
BF7. 153 nr 1 -

Daily Service Fuel Tank


BF7. 154 nr 1 -

No.1 Generator Panel


BF7. 155 nr 1 -

No.1 Generator Control Panel


BF7. 156 nr 1 -

No.2 Generator Panel


BF7. 157 nr 1 -

No.2 Generator Control Panel


BF7. 158 nr 1 -

Synchronous Panel
BF7. 159 nr 1 -

MV Feeder Panel
BF7. 160 nr 1 -

No.1 Battery Panel


BF7. 161 nr 1 -

No.2 Battery Panel


BF7. 162 nr 1 -

Auxiliary Equipment Control Panel


BF7. 163 nr 1 -

Vent Silencer
BF7. 164 nr 2 -

Pulse Output Fuel Consumption Meter


BF7. 165 20A nr 2 -

Fuel Feed Pump


BF7. 166 nr 3

Main Fuel Tank


BF7. 167 nr 2

Fuel Filling Box


BF7. 168 nr 1

ATS panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 169 description and schematics nr 1

MDB panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 170 description and schematics nr 1

Fan panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 171 description and schematics nr 1

Property panel inclusive of all switches/sensors/cables/means of


communication with other system components as indicated in panel
BF7. 172 description and schematics nr 1

Bidder's Signature or Initials ...........................................


Page 92/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
MV switch gear cubicle inclusive of all
switches/sensors/cables/meetering/means of communication with
BF7. 173 other system components as indicated in schematics nr 1 -

BF7. 174 Generator (1600 kVA) nr 1 -


Fuel tank storage system of 9000L inclusive of support/piping and
BF7. 175 auxilaries to genset ( located in a reinforced concrete bund) nr 1 -

BF7. 176 Transformer (1600 kVA) inclusive of accessories nr 1 -


BF7. 177 MV termination kit nr 2 -
Supply and instalation of Concrete poles (12 meters long) inclusive all
assesories as cable arms, arrestors and earthing connections to
BF7. 178 transport MV cables from hook up point to the grid to the MV switch nr 1 -
gear cubicle

BF7. 179 Connection Fee's to obtain an electrical connection nr -

BF7. 180 Heavy duty galvanized steel cable trays, ducts and raceways. nr 1 -
Supply and Installation of Fire extinguishers CO2 type 9 KG inclusive
BF7. 181 with wall mounting hooks and signage nr 1 -

Other miscellaneous items that are specified or shown on the drawings


or that the Contractor may deem necessary to complete the works in
BF7. 182 Bill 7-7 ls 1 -

Sub-total for Bill 7-7. Generator Building, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 93/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-8. Online Water Quality Monitoring

Raw Water Turbidity


BF7. 183 Surface-Scattered Light Type nr 1 -

Raw Water pH
BF7. 184 Combination Electrode Type nr 1 -

Filtered Water Residual Chlorine


BF7. 185 Reagent less Free Chlorine Analyzer nr 1 -

Finished Water Residual Chlorine


BF7. 186 Reagent less Free Chlorine Analyzer nr 1 -

Finished Water Turbidity


BF7. 187 Surface-Scattered Light Type nr 1 -

Finished Water pH
BF7. 188 Combination Electrode Type nr 1 -

Online Water Quality Monitoring Panel


BF7. 189 nr 1

Sub-total for Bill 7-8. Online Water Quality Monitoring, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 94/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-9. Raw Water Measuring Chamber

Raw Water ElectroMagnetic Full Bore Flow Meter 700mm dia. including
BF7. 190 all power supply, transmitters and cabling and accessories as specified, nr 1 -
located in flow meter chamber at WTP

Sub-total for Bill 7-9. Raw Water Measuring Chamber, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 95/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

Bill 7-10. Wires, Cables and Miscellaneous

Wires, Cables, Conduits, Boxes, Fittings, Cable Racks, Ducts, Grounding


and Other Miscellaneous Items including Floor Work for Electrical Room
and Generator Room and Raised Access Floor Work for Control Room
BF7. 191 for Water Treatment Plant ls 1 -

Sub-total for Bill 7-10. Wires, Cables and Miscellaneous, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 96/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)
Bill 7-11. Yard Systems
Yard Lighting system including Street LED Lighting fixtures, distribution
panels, cables and termination, conduit and fittings and other
BF7. 192 miscellaneous works specified in the Drawings. ls 1 -

Yard power distribution system including man/pull holes, cable


ducting, power distribution cables and fittings and other miscellaneous
BF7. 193 works specified in the Drawings. ls 1 -

Yard signal distribution system including man/pull holes, cable


ducting, signal cables for system communication purposes inclusive of
BF7. 194 accessories to establish a trouble free connection . ls 1 -

Sub-total for Bill 7-11. Modification of Existing Systems, CARRIED TO PART SUMMARY -

Bidder's Signature or Initials ...........................................


Page 97/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP) BILL 7 - ELECTRICAL WORKS FOR BILL - 7
BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 WATER TREATMENT PLANT
Total
ITEM ITEM DESCRIPTION- Lot 1 UNIT QUANTITY RATE Amount
(USD) (USD)

PART SUMMARY FOR Bill 7

Sub-total for Bill 7-1. Treatment Facilities, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-2. Distribution Pump Station & Clear Water Reservoir, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-3. Drainage Basin, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-4. Administration Building, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-5. Chemical Building, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-6. Chlorination Buildings, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-7. Generator Building, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-8. Online Water Quality Monitoring, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-9. Raw Water Measuring Chamber, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-10. Wires, Cables and Miscellaneous, CARRIED TO PART SUMMARY -

Sub-total for Bill 7-11. Yard Systems, CARRIED TO PART SUMMARY -

Sub-total for Bill 7, CARRIED TO GRAND SUMMARY -

Bidder's Signature or Initials ...........................................


Page 98/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR PROVISIONAL SUMS BILL - PS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)

BFPS. PROVISIONAL SUMS

Note: The Provisional Sums given in the Bill of Quantities are for
defined work and may be used in whole or in part, or not at all

Geo-technical Survey

BFPS. 01 Mobilization/Demobilization nr 1 -

BFPS. 02 Standard Penetration Test nr 50 -

BFPS. 03 All required sampling and laboratory testing to establish soil physical nr 100 -
characteristics and bearing capacity

Defined Work
Provision of standards and other reference documents
BFPS. 04 ls 1 -
Public announcements as directed by the Engineer
BFPS. 05 ls 1 -
Payment to Dispute Board (Employer's portion only)
BFPS. 06 ls 1 -

BFPS. 07 Reinstatement of private properties as directed by the Engineer ls 1 -

Environmental monitoring and measurement other than that defined


BFPS. 08 in work requirement ls 1 -

BFPS. 09 Allow for expenses for stakeholder meeting for the Project ls 1 -

BFPS. 10 Provision of special maintenance equipment as per requested by the ls 1 -


Employer.

Power receiving lines, MV Switchgear, Lightning Protection Systems


and Miscellaneous work to be delegated to power supply company -
Electricité du Cambodge (EDC)

BFPS. 11 For Intake Station ls 1 -

BFPS. 12 For Water Treatment Plant ls 1 -

Allow for sediment filter net in Sangke River at intake including all
BFPS. 13 tethering and anchoring ls 1 -

Allow 5% (as per PCC) for Contractor's overheads and profits on items
BFPS. 14 BFPS . 1 to 13 above % 5 -

Subtotal of Part BFPS, CARRIED TO GRAND SUMMARY -

Bidder's Signature or Initials ...........................................


Page 99/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.1. BILL DW - DAYWORK SCHEDULE
Schedule 1: Labour
DW.1. 01 Unskilled Labourer days 25 8.00 200.00
DW.1. 02 Banksman/Slinger days 25 8.00 200.00
DW.1. 03 Carpenter days 25 12.00 300.00
DW.1. 04 Mason/ Concrete Finisher days 25 12.00 300.00
DW.1. 05 Driver: Heavy Duty days 25 12.00 300.00
DW.1. 06 Driver: Light Duty days 25 10.00 250.00
DW.1. 07 Pipe Fitter days 25 12.00 300.00
DW.1. 08 Plant Operator: Heavy days 25 12.00 300.00
DW.1. 09 Plant Operator: Light days 25 10.00 250.00
DW.1. 10 Steel fixer/ Bar Bender days 25 12.00 300.00
DW.1. 11 Welder days 25 14.00 350.00
DW.1. 12 Jointer days 25 12.00 300.00
DW.1. 13 Painter days 25 12.00 300.00
DW.1. 14 Electrician days 25 14.00 350.00
DW.1. 15 Mechanical Fitter days 25 14.00 350.00
DW.1. 16 Instrumentation Fitter days 25 12.00 300.00
DW.1. 17 Plumber days 25 14.00 350.00
DW.1. 18 Chainman days 25 14.00 350.00

Sub-total of Schedule DW-1 Carried to Part Summary 5,350.00

Bidder's Signature or Initials ...........................................


Page 100/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.2. Schedule 2: Materials
DW.1. 01 Aggregate, base course material m3 20 18.00 360.00
DW.1. 02 Aggregate, course (dry) t 20 18.00 360.00
DW.1. 03 Aggregate, fine (dry) t 20 18.00 360.00
DW.1. 04 Aggregate, sub-base material m3 20 10.00 200.00
DW.1. 05 Asphalt concrete, base course t 10 110.00 1,100.00
DW.1. 06 Bitumen 60/70 t 10 900.00 9,000.00
DW.1. 07 Bitumen40/50 t 10 900.00 9,000.00
DW.1. 08 Bituminous asphaltic concrete, base course t 10 110.00 1,100.00
DW.1. 09 Bituminous asphaltic concrete, wearing course t 10 110.00 1,100.00
DW.1. 10 Borrow material m3 50 8.50 425.00
DW.1. 11 Brick, Standard size nr 4,000 0.06 240.00
DW.1. 12 Cement; Ordinary Portland t 3 100.00 300.00
DW.1. 13 Cement; Sulphate resistant t 3 110.00 330.00
DW.1. 14 Concrete, Grade 15/20 m3 5 92.00 460.00
DW.1. 15 Concrete, Grade 20/20 m3 10 92.00 920.00
DW.1. 16 Concrete, Grade 25/20 m3 10 95.00 950.00
DW.1. 17 Concrete, Grade 30/20 m3 10 98.00 980.00
DW.1. 18 Concrete, Grade 40/20 m3 5 100.00 500.00
DW.1. 19 Formwork, steel m2 60 32.00 1,920.00
DW.1. 20 Formwork, timber (smooth) m2 30 14.00 420.00
DW.1. 21 Fuel, diesel ltr 150 1.10 165.00
DW.1. 22 Fuel, petrol ltr 60 1.10 66.00
DW.1. 23 Fuel, kerosene ltr 60 0.90 54.00
DW.1. 24 Kerbs, cast in-situ concrete m 100 15.00 1,500.00
DW.1. 25 Kerbs, pre-cast concrete m 100 15.00 1,500.00
DW.1. 26 Masonry block, concrete, 400 x 200 x 100 mm nr 1000 3.50 3,500.00
DW.1. 27 Paint, emulsion ltr 12 6.00 72.00

DW.1. 28 Paint, enamel ltr 6 8.00 48.00

DW.1. 29 Paving stones, interlocking precast concrete, 60mm m2 625 9.00 5,625.00

DW.1. 30 Paving stones, interlocking precast concrete, 80mm m2 400 12.00 4,800.00

DW.1. 31 Steel Pipe, ND 80mm, Straight Pipe m 10 24.00 240.00

DW.1. 32 Steel Pipe, ND 100mm, Straight Pipe m 10 34.83 348.30

DW.1. 33 Steel Pipe, ND 150mm, Straight Pipe m 10 45.00 450.00

DW.1. 34 Steel Pipe, ND 200mm, Straight Pipe m 10 65.00 650.00

DW.1. 35 Steel Pipe, ND 250mm, Straight Pipe m 10 92.00 920.00

Bidder's Signature or Initials ...........................................


Page 101/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.1. 36 Steel Pipe, ND 300mm, Straight Pipe m 10 120.00 1,200.00

DW.1. 37 Steel Pipe, ND 350mm, Straight Pipe m 10 130.00 1,300.00

DW.1. 38 Steel Pipe, ND 400mm, Straight Pipe m 10 150.00 1,500.00

DW.1. 39 Steel Pipe, ND 500mm, Straight Pipe m 10 220.00 2,200.00

DW.1. 40 Steel Pipe, ND 600mm, Straight Pipe m 10 266.00 2,660.00

DW.1. 41 Steel Pipe, ND 800mm, Straight Pipe m 10 355.00 3,550.00

DW.1. 42 Welded Flange for Steel Pipe, ND 80mm nr 5 9.00 45.00

DW.1. 43 Welded Flange for Steel Pipe, ND 100mm nr 5 11.00 55.00

DW.1. 44 Welded Flange for Steel Pipe, ND 150mm nr 5 20.00 100.00

Bidder's Signature or Initials ...........................................


Page 102/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.1. 45 Welded Flange for Steel Pipe, ND 200mm nr 5 25.00 125.00

DW.1. 46 Welded Flange for Steel Pipe, ND 250mm nr 5 110.00 550.00

DW.1. 47 Welded Flange for Steel Pipe, ND 300mm nr 5 220.00 1,100.00

DW.1. 48 Welded Flange for Steel Pipe, ND 350mm nr 5 350.00 1,750.00

DW.1. 49 Welded Flange for Steel Pipe, ND 400mm nr 5 650.00 3,250.00

DW.1. 50 Welded Flange for Steel Pipe, ND 500mm nr 5 1,100.00 5,500.00

DW.1. 51 Welded Flange for Steel Pipe, ND 600mm nr 5 1,500.00 7,500.00

DW.1. 52 Welded Flange for Steel Pipe, ND 800mm nr 5 2,200.00 11,000.00

DW.1. 53 H-section Steel t 10 1,050.00 10,500.00

DW.1. 54 Channel Steel t 10 1,050.00 10,500.00

DW.1. 55 Pipe, HDPE, 63 mm diameter m 20 4.50 90.00

DW.1. 56 Pipe, HDPE, 110 mm diameter m 20 15.00 300.00

DW.1. 57 Pipe, HDPE, 160 mm diameter m 20 28.00 560.00

DW.1. 58 Pipe, HDPE, 225 mm diameter m 20 52.00 1,040.00

DW.1. 59 Reinforcement, high tensile strength steel t 1 820.00 820.00

DW.1. 60 Reinforcement, mild steel t 0.25 837.01 209.25

DW.1. 61 Sand m3 15 18.00 270.00

DW.1. 62 Wood, hardwood timber m3 5 800.00 4,000.00

DW.1. 63 Wood, softwood lumber m3 15 700.00 10,500.00

DW.1. 64 Wood, plywood, marine grade, 20 mm m2 15 16.00 240.00

DW.1. 65 Wood, plywood, standard grade, 20 mm m2 30 15.00 450.00


Sub-total of Schedule DW-2 Carried to Part Summary 132,827.55

Bidder's Signature or Initials ...........................................


Page 103/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.3. SECTION C - DAYWORK SCHEDULE (Cont'd)
Schedule 3: Plant & Equipment

Equipment cost for days in service including upkeeping and


maintenance of equipment excludes operators and fuels.

DW.1. 01 Air compressor 5000-6000 litres with small tools days 30 30.00 900.00
DW.1. 02 Asphalt coring machine, up to 200mm dia. days 30 25.00 750.00
DW.1. 03 Asphalt paver days 30 200.00 6,000.00
DW.1. 04 Asphalt/concrete saw days 30 20.00 600.00
DW.1. 05 Bulldozer up to 100 HP days 30 80.00 2,400.00
DW.1. 06 Bulldozer with ripper (32tons, Class D8) days 30 160.00 4,800.00
DW.1. 07 Bulldozer (21tons, Class D7) days 30 140.00 4,200.00
DW.1. 08 Bulldozer (15tons, Class D6) days 30 100.00 3,000.00
DW.1. 09 Bucket loader up to 3 m3 days 30 80.00 2,400.00
DW.1. 10 Bucket loader over 3 m3 days 30 100.00 3,000.00
DW.1. 11 Concrete mixer, 6 m3 days 30 60.00 1,800.00
DW.1. 12 Concrete mixer, 9m3 days 30 80.00 2,400.00
DW.1. 13 Concrete pump, 50m3/hr days 30 150.00 4,500.00
DW.1. 14 Concrete pump, 70m3/hr days 30 180.00 5,400.00
DW.1. 15 Concrete vibrator (poker/screed) up to 50mm dia days 30 5.00 150.00
DW.1. 16 Dump truck up to 5 tons days 30 50.00 1,500.00
DW.1. 17 Dump truck from 5 to 10 tons days 30 60.00 1,800.00
DW.1. 18 Dump truck over 10 tons days 30 70.00 2,100.00
DW.1. 19 Excavator up to 0.2 m3, wheeled days 30 35.00 1,050.00

Bidder's Signature or Initials ...........................................


Page 104/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
DW.1. 20 Excavator up to 1 m3, wheeled days 30 120.00 3,600.00
DW.1. 21 Forklift up to 5 tonnes days 30 60.00 1,800.00
DW.1. 22 Generator up to 200 kVA days 30 70.00 2,100.00
DW.1. 23 Grader up to 140 HP days 30 140.00 4,200.00
DW.1. 24 Hiab truck, 6 tonne or greater, with lifting arm days 30 60.00 1,800.00
DW.1. 25 Lorry mounted crane, up to 25 tonnes days 30 120.00 3,600.00
DW.1. 26 Mobile crane, 20 tonne days 30 110.00 3,300.00
DW.1. 27 Mobile crane, 45 tonne days 30 150.00 4,500.00
DW.1. 28 Pick up truck, up to 2 tonnes days 30 35.00 1,050.00
DW.1. 29 Pick up truck, over 3 tonnes days 30 40.00 1,200.00
DW.1. 30 Plate compactor days 30 7.00 210.00
DW.1. 31 Pneumatic breaker days 30 7.00 210.00
DW.1. 32 Pneumatic roller over 10 tons days 30 90.00 2,700.00
DW.1. 33 Portable lighting set with generator days 30 25.00 750.00
DW.1. 34 Vibratory roller, random type up to 3 tons days 30 45.00 1,350.00
DW.1. 35 Vibratory roller, random type up to 8 tons days 30 65.00 1,950.00
DW.1. 36 Water pump, 2 inch days 30 7.00 210.00
DW.1. 37 Water pump, 4 inch days 30 10.00 300.00
DW.1. 38 Welding machine, HDPE electrofusion, 300mm dia. days 30 40.00 1,200.00
DW.1. 39 Welding machine, HDPE butt welding, 300mm dia. days 30 40.00 1,200.00

Sub-total for Schedule DW-3 Carried to Part Summary 85,980.00

Bidder's Signature or Initials ...........................................


Page 105/105

PROVINCIAL WATER SUPPLY AND SANITATION PROJECT (PWSSP)


BATTAMBANG WS - ICB No.: PWSSP/MISTI/CW-1 BILL FOR DAYWORKS

Total
ITEM ITEM DESCRIPTION- Lot 1 QUANTITY RATE Amount
(USD) (USD)
Schedule DW-1: Labour
Sub-total for labour 5,350.00
Percentage addition for profit and overhead [5%] 267.50
Total for Labour Carried to Summary 5,617.50
Schedule DW-2: Materials
Sub-total for material 132,827.55
Percentage addition for profit and overhead [5%] 6,641.37
Total for Material Carried to Summary 139,468.92
Schedule DW-3: Plant & Equipment
Sub-total for plant & equipment 85,980.00
Percentage addition for profit and overhead [5%] 4,299.00
Total for Plant & Equipment Carried to Summary 90,279.00
Total for Labour 5,617.50
Total for Materials 139,468.92
Total for Plant & Equipment 90,279.00
CARRIED TO GRAND SUMMARY 235,365.42