GIGASOL3.O&M.SWI.0001
63.005MW GIGASOL3 SOLAR POWER PLANT
Revision:
A

SAFE WORK INSTRUCTION


TITLE /DESCRIPTION OF ACTIVITY: Replacement of Busted 32A SCB Fuse Pg. 1
Company: Gigasol3, Inc. Department: Operations and Maintenance

Risk Assessment
Created By: O&M Assistant Supervisor JCE-0001
No.
Initial Issue Date 20 Nov. 2022 Next Review Date Yearly
SCOPE (List whom this procedure applies to and the specific location this work can be conducted in)
1. Plant Supervisor/Asst. Supervisor – Overall Supervision of the Plant
2. Duty Engineer – Commands and assign works to Technicians
3. Safety Officer – Ensures Safety and Health in the work place is enforced
4. Technicians – Field workers assigned in the activities
5. Driver – Assist the Field Workers on the Transportation
6. Warehouse Personnel – Provides materials needed for the site
Location: String Combiner Box Area from Zone 1 to Zone 8
AUTHORIZATIONS: (List specific operator competency requirements, e.g. area induction, qualifications, certificates, OHS
training, supervision. List who can approve that competency has been achieved)
1. Mandatory Eight (8) – hour OSH Orientation
2. National Certification (NC II) which grants personnel to become qualified and to work
on specific job description (e.g. Electrical works – Electrical Certification)
3. Authorized by Gigasol Palauig
4. With Fit-To-Work clearance from physician

HAZARDS: (List all the potential hazards and associated consequence, e.g. chemical exposure – inhalation or skin
absorption, leading to irritation, burns, acute or chronic injury).
1. Fire: burns
2. Physical: contact with sharp edges of tools and equipment. Tripping from loose rocks
and tree branches
3. Ergonomic: awkward and repetitive motion can cause strain to muscle and joints of the
body
4. Biological: Insect and snake bites
5. Weather: extreme heat index and humidity can lead to heat stress and dehydration;
thunderstorms
6. Gravity: Fall from slopes; falling branches and other objects
7. Electricity: contact with energized DC Cable Strings and SCB Equipment
8. Psycho-social hazard: fatigue; ineffective communication

SAFETY CONTROLS: 1. Administrative


• Conduct toolbox meeting
• Regular monitoring and inspection of tools and equipment
• Availability of drinking water for hydration
• Monitoring of Weather conditions and Adjustment of work schedules during extreme dry/
wet condition. If caught up by Thunderstorm during work, seek shelter.
• Availability of certified first aider and first aid kit at the workplace
• No smoking at work areas
2. PPE
• Hard hat
• Safety eye wear
• Electrical gloves (IP Rated)
• Safety shoes/ boots
• Reflectorized Vest/Clothing

Safe Work Instruction Template v1 Responsible Officer: HSSE Officer


Date of first issue: November 20, 2022 Date of last review: N/A
Document No:
GIGASOL3.O&M.SWI.0001
63.005MW GIGASOL3 SOLAR POWER PLANT
Revision:
A

TITLE /DESCRIPTION OF ACTIVITY: Replacement of Busted 32A SCB Fuse Pg. 2


PRESTART (List tasks to be completed before commencement of work, e.g. conduct a prestart safety check of
equipment; review chemical SDS, risk assessment; prepare work area, equipment and/or operator)
REQUIREMENTS: 1. Ensure include String Monitoring in the Daily Activity to ensure the proper guidance of
Rectification of Busted 32A SCB Fuse upon SCADA Confirmation.
2. Briefed the workers on the safety protocols and adherence to PPE protocols
3. Issuance and inspection of tools, equipment, supplies and first aid kit
4. Weather check for possible postponement or re-position of manpower

INSTRUCTIONS: (List step by step procedures for the task. You can use photos, flow charts, diagrams etc.
Please see steps in Attached Work Method Statement
EMERGENCY (Emergency response procedures e.g. power isolation procedures, first aid response)
PROCEDURES: In case of injured worker
1. Activate medical assistance
2. Apply first aid and secure injured worker
3. Transport injured worker to the Site HSE Office for further evaluation and possible
referral
4. Refer injured worker to nearest hospital for medical/ surgical intervention
5. Prepare and submit incident report in compliance with Gigasol Palauig policies

FURTHER (e.g. Company procedures, relevant legislation, definitions, reference to other safety information)
INFORMATION: Gigasol Palauig Emergency Response Team

APPROVALS
Title Name Signature Date

Gigasol3 Site Engineer Roger Purisima Jr.

Gigasol3 HSSE Officer Ron-Ron Colorado

Gigasol3 Plant Manager Ariston Posadas

Safe Work Instruction Template v1 Responsible Officer: HSSE Officer


Date of first issue: November 20, 2022 Date of last review: N/A