Rohan abuilders (India) Pvt.

Ltd
Project :-Sussen Asia Pvt.Ltd.Shirtwal
Job Hazard Analysis Sheet No. 2…... of ……1..

PROJECT / TASK: Backfilling, levelling Metteling &


CONTRACTOR: RBIPL JOB No.:006
Compaction

SUPERVISOR: Vilas Kadam LOCATION: Road Work DATE:

JOB STEP HAZARDS Control Measure ACTION


Break the job into steps. List the hazard or type of harm List the necessary control measures to be followed to Person who will ensure this
Listing work which may be hazardous. identified with each step eliminate the identified hazards happens

Backfilling, levelling, Metteling & Vehicle Movement (Hit Hazard) Documents of mobile plants/vehicle to be
Compaction cleared before entering the site.

Check for Horn, Lights, brakes, rear view glass


and reverse horn to be done. Mr R.A.Guttedar

Valid licence to be checked for the


Driver/Operator.

Access to be cleared from all unwanted


materials or traffic to enter the work area.

Area will be isolated with the help of


barricading or providing supervision for
compaction equipment.

Fall hazard Continues supervision to be provided.

Do not overload the vehicle carrying the soil


for backfilling.

Barricading have to be done wherever there is


an area lower than the road after backfilling
and proper signage to be displayed if there is
any deep.

Daily tool box to be given to all. Continuous


supervision to be provided.

Eye hazard Safety goggle to be provided.

Dust Hazard Nose mask to be provided.

Working at night Proper Area lighting to be provided other than


equipment or Vehicle light.

Job Hazard Analysis Attendees: Mr. Dhake ,Mr.R.A.Guttedar


Name Signature Date
Written by: Safety Officer RBIPL Mr. Dhake
Site Engineer: Mr.R.A.Guttedar
Reviewed by: Project Manager Mr.Vinod Narkhede
RBIPL
SAPL Officer / Engineer: