PALANPUR-SAMAKHYALI (248 RKM /605 TKM)

FORMATION

TRACK READINESS

PACKAGE-1 (82 RKM/ 195 TKM) PACKAGE-2 (75 RKM/ 196 TKM) PACKAGE-3 (91 RKM/ 214 TKM)
PRIORITY-1 (T21) PRIORITY-2 PRIORITY-2 PRIORITY-1 (T21) PRIORITY-2 PRIORITY-1 (T21)

Palanpur Disa Mitha Radhanpur Santalpur Kidiyanagar Samakhyali


30 RKM 52 RKM 28 RKM 47 RKM 58 RKM 33 RKM

1. Feed will be extended from 1. TSS location at Bhilidi needs 1. Approval of Sectioning Diagram. 1. Approval of Sectioning diagram. 1. Scope of S&T Works needs to be 1. Scope of S&T Works needs to be
Palanpur yard. LOP/ CSD approval to be finalized. 2. Drawing Approval Pending. 2. NS item approval for 66kV TSS finalize. finalize.
pending. 2. SIP/ESP-Mismatch. LOP/CSD a. KM: 87 - 90 and 99-101. equipment supply. This is an island 2. Scope of General Electrical to be 2. Scope of General Electrical to be
2. Scope of S&T Works needs to not yet prepared for Lorwada 3. Scope of S&T Works to be and Power will be fed from finalized. finalized.
be finalize. Section. finalize. Santalpur TSS. 3. Quantity variation approval of 3. Quantity variation approval of
3. Location Plan for Disa SSP 3. Drawing Approval Pending. 4. Scope of General Electrical to be 3. Drawing Approval Pending. Height Gauge, Earthfilling for TSS, Height Gauge, Earthfilling for TSS,
needs to be finalized. a. Bridge mast drawing at Bhildi finalized. a. KM: 120 - 122, 123-128 , 136- OHE foundation etc. OHE foundation etc.
4. LOP and CSD approval of Disa (KM 30). 5. Quantity variation approval of 140, 145-147 and 154-157. 4. Approval of Sectioning Diagram. 4. Approval of Sectioning Diagram.
Yard (KM 27.6) b. LOP & CSD of Diyodar- Height Gauge, Earthfilling for TSS, b. PSI and OHE Depot at Radhanpur 5. Drawing Approval Pending 5. Location Plan approval pending for
5. Quantity variation approval of Mitha section, Jasali Yard. OHE foundation etc. Depot. a. KM: 223 - 225 SSP at Kidiyanagar & Chitrod.
Height Gauge, Earthfilling for TSS, c. Bhildi, Dhanakwada, Mitha- 4. Location Plan approval of b. Adesar - SP 6. Drawing Approval Pending for KM:
OHE foundation etc. SSP and Jasali SP. Chansara SSP 170 - 173, 180-189 and 223-225
6. Scope of General Electrical to 4. Scope of General Electrical 5. Scope of S&T Works needs to be
be finalized. to be finalized. finalize.
7. Approval of Sectioning Diagram 5. Approval of Sectioning 6. Scope of General Electrical to be
Diagram finalized.
7. Quantity variation approval of
Height Gauge, Earthfilling for TSS,
OHE foundation etc.
23-June-2020

DALIGANJ-MAILANI ( RKM 189 /221 TKM)


DALIGANJ Bakshi ka Talab Kamlapur Sitapur Jn Hargaon Khiri Town Deokali Rajaganj Golagokaharn Mailani Jn
Ataria Nath
YARDS Khariabad Jharekapur OEL Lakhimpura Bahelia
Mohibullapur Itaunja Sidhauli Pharedahan Bankeyganj
Buzurgr

CHAINAGE (KM) 7 10 19 28 40 53 64 81 87 100 111 118 127 132 141 144 155 159 167 177 192
FOUNDATION COMPLETED
MAST ERECTION COMPLETED
BRACKET ERECTION COMPLETED
WIRING COMPLETED
SED COMPLETED
TWC COMPLETED
DALIGANJ - SITAPUR SECTION (84 RKM / 101 TKM) SITAPUR - MAILANI SECTION (104 RKM / 120 TKM)
PRIORITY-1 (DAL-STP) PRIORITY-1 (SITAPUR-LAKIMPUR) PRIORITY-2 (LAKIMPUR-MAILANI)
Aishbagh Bakshi Ka Aataria Sidhauli Bariajalalpur Khairabad Sitapur Jharekapur
OEL (SP) Lakimpur (SSP) Pharedhan Golagokahran Bankeyganj
(SP) Talab (TSS) (SP) (SSP) (TSS) (SSP) (SSP) (SP)
(SSP) (SSP) (TSS)

Feed Extension 84 RKM 45 RKM 60 RKM

1. Bakshi Ka Talab Aishbagh SP: 30.07.2020 1. Khairabad TSS: 1. Power Feeding through Khairabad TSS. 1. Power Feeding through Phardhan TSS.
TSS: 20.07.2020 Aataria SSP: Commissioned 30 Dec 2020(TDC) 2. TDC: 31.03.2021 subject to incoming Tx line.
(Testing ) 2. Revised approved
2. 132KV TL still Sidhauli SP: Commissioned location plan received on 15.01.20
not reached TSS. Bariajalalpur SSP : Commissioned 3. Equipment Foundation and
Control Room building approved on
Sitapur SSP : Commissioned 27.02.20 and 04.06.20 respectively
Progress Scope Compl. Bal. Scope Compl. Bal. Scope Compl. Bal.
Foundation 2000 2000 0 1010 800 210 1090 97 993
Mast Erection 1687 1687 0 934 729 205 945 80 865
Bracket Erection 2030 2030 0 847 1253
Wiring 84 84 0 45 60
Height Gauge Erection 38 38 0 15 1 14 20
TW Checking 101 101 0 55 75
CRS COMPLETED FOR DALIGANJ - Bakshi Ka Talab TSS: Khairabad TSS: Jharekapur SSP: 30.10.20 (TDC) Golagokaran SSP: 31-Jan-21 (TDC)
SITAPUR SECTION ON 25th FEB 1. Still 132KV TL not reached Site 1. Due to unavailiability of OEL SP: 30.10.20 (TDC) Bakenganj SP: Drawing not approved
2020 2. 95% of Civil work completed. permission for tree cutting from
3. All Equipment Erection Reserve forest, location shifted to Lakimpur SSP: 30.10.20 (TDC)
completed new location and got approval for
4. Cable termination under new location plan on 15.01.20.
process. 2. Civil work started at approved 1. Quantity Variation for Height Gauge,OHE work 1. Approval of Sectioning Diagram.
5. Testing will be completed by location. and Civil work pending for approval from client. 2. Drawing Approval Pending.
15th July 2020 a. KM: 163 - 195
SITAPUR 3. Quantity Variation for Height Gauge,OHE work and Civil work pending for approval
a.STAFF QUARTERS: from client.
1.NS Proposal for 1st Floor staff
quarters pending. Pharedhan:
a.TSS
1. Equipment foundation drawing approval received on 11.06.20. work started TDC
31.03.2020
b.Staff Quarters:
1. Drawing approval pending from client.
2. NS proposal Pending for 1st Floor
C. OHE PSI DEPOT:
1. Drawing approval pending from client.
23-June-2020

KASGANJ-MAILANI ( RKM 212 /289 TKM)


Kasganj City Manpur Bitroi Badaun Makrandpur Ramganga Bareilly City Dohna Sethal Shahi Mala Puranpur(PP) Kurraiya Sehramau
Nagaria Bridge
YARDS Ujhani Bamiana
Soro Shukarshetra Bareilly Jn Izzatnagar Bhojipura Bijauria Pilhibit Jnnj Shahgarh Dhoodhiyak Dhoodhiyak Mailani Jnhurd
Kachhla (H) Ghatpuri Buzurgr hurd hurd

CHAINAGE (KM) 417 406 399 393 387 375 362 349 337 330 324 319 315 311 304 299 286 280 273 260 247 235 225 215 208 215 202 192
FOUNDATION COMPLETED
MAST ERECTION COMPLETED
BRACKET ERECTION COMPLETED
WIRING COMPLETED
SED COMPLETED
TWC COMPLETED
Kasganj-Bareilly City (107 RKM / 136 TKM) Bareilly City - Pilibhit (55 RKM / 78 TKM) Pilibhit - Mailani (73 RKM / 90 TKM)
PRIORITY-1 (KSJ-BC) PRIORITY-2 (Bareilly City-Pilibhit) PRIORITY-3 (Pilibhit-Mailani)
SRN BTRI BMY RGB
BEM (TSS) GTP (SSP) BC (SSP) BPR (TSS)
Pilhibit Jn SP Mala SSP Puranpur TSS Sehramau SSP
SSP (SP) (SP) (SP) Bijauria SSP

Feed Extension 56 RKM 67 RKM 87 RKM

1.KSJ TSS SRN SSP Commissioned 1.BEM TSS: work under progress GTP SSP 1.BPR TSS successfully charged PP TSS
OHE & Civil Drawing CRB-roof slab,shuttering &
Commissioned Mala SSP
1.BEM 2. CRS of BC-PBE section sucessfully done on Approved reforcement work in Revised
OHE depot-Terrace slab casted. Finishing BMY SP 23.02.2021 progress Sehramau approved
BTRI SP SSP location
work in progress Roof Slab Casted & Electrical equipment
Commissioned Tower Wagon Shed- Structure completed. Commissioned Staff Quartes Type-III & IV Roof slab casted, Pilhibit Jn SP Equipment foundation foundation drawing awaited
External plaster completed. Brick work in progress Under Progress completed awaited
Tower Wagon Siding- Cable tracing work RGB SP Type-II Block-1&2 Grund floor roof slab casted OHE depot-approved
completetd. Block 3 Plinth beam casted location awaited
Staff Quarter- Commissioned Bijauria SSP Charging done TWS/siding-approved
Type-II Block-1,2&3- Plinth level location awaited
Type-III slab casted finshing work in Staff Quarter-approved
progress. BC SSP Commissioned location awaited

Progress Scope Compl. Bal.

Foundation CRS Inpection 1800 0 1800


Completed
Mast Erection CRS 1440 0 1440
CRS Inpection Completed Inpection
Bracket Erection Completed 1820 0 1820

Wiring 90 0 90

Height Gauge Erection 20 0 20

TW Checking 90 0 90