Professional Documents
Culture Documents
Method of Statement (Open Cut)
Method of Statement (Open Cut)
Table of Contents
1. Introduction ……………………………………………………………………………… 2
2. Scope of Work ……………………………………………………………………………… 2
3. Process of Cable Laying ……………………………………………………………………………… 3-8
4. Roles & Responsibilities ……………………………………………………………………………… 8-9
a) Project Manager
b) Safety Supervisor
c) Field Supervisor
d) Worker
1
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
1. Introduction
Properly performed, this method of Trenchless Technology has zero settlement to the
ground surface, since there is no excavation displacement is used instead of
excavation.
2. Scope of Work
This method statement covers the method utilized to construct an underground cable
laying. This method statement will apply for the followings:
Project Name :
Project No. :
PO No. :
Client :
Scope : Underground Cable Laying (Open Cut).
2
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
i. Mapping
In areas where the local authority enforces the requirement of utility
mapping as the pre-requisite for the cable route approval, then the
utility mapping contractor appointed by TNB shall be engaged. The
contractor is required to determine, locate and map all existing
underground utilities or services within the proposed cable routes. They
must also produce coordinated plans or utility mapping plans for
submission to local authority.
3
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
Figure 1.0 - Cross section of direct buried cable in unpaved & paved
surfaces
4
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
Rollers must be used where cables are installed in an open trench using a
pulling rope and eye; cable rollers are to be used at frequent intervals to
support the cables and must never be more than 3 meters apart.
Care must be taken to ensure that the cable does not enter or leave the rollers
at an angle hat exceeds the bending radius of the cable. The rollers are to be
placed securely to prevent movement. Before driving any spikes to secure the
rollers, care must be taken to avoid other utilities' equipment, which may exist
below.
The pulling rope must be equipped with a swivel and be attached to the cable
by a stocking grip with pulling eye the cable shall by manually, before the pull
commences, to stop the winch from moving with subsequent uneven pulling of
the cable. The cable shall be drawn into the trench smoothly with a minimum of
stops and at an average speed of between 9-12 meters per minute, to avoid
irregular movement.
5
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
v. Cable Laying
The drum should be mounted on jacks, cable trailer or cable stands such that the
cable is preferably pulled from the top and always in the direction opposite to
that indicated by the arrow. lighter cables may be laid by mounting the cable drum
on its side on a truck-mounted turntable and laying the cable directly into the
trench. When pulling from large drums, i.e., over 2m in diameter, the cable
should be supported to prevent stressing the cable, from the drum to the trench
on a suitable ramp. Alternatively, cables can be rolled directly into a trench from
the drum mounted on an excavator moving along the trench.
To limit the chance of damage to the cable prior to removing the cable drum
battens, a check should be done to ensure that the drum-spindle is level and
permits even rotation of the drum. During pulling there is a tendency for cable
slack to accumulate on the drum, slack shall be avoided and one possible
method to achieve this is to limit drum rotation by using plank brake shoes against
one or both flanges of the drum. If the inner end of the cable on the drum end
protrudes through the side of the drum, then it should be watched during pulling to
ensure it is not damaged. it is advisable to tie a rope to the drum end, and pull
through any slack cable that appears.
6
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
vi. Backfilling/Resurface
Backfilling properly used cable slab and sand as per spec mentioned,
after that supply and resurface the existing road with a layer of
50mm thickness of premix, patching the hole/ damaged road also
include others related works as per Authority instruction and
satisfaction of client.
7
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
Permanent Patch
- Mill & Pave (50mm
Temporary Patch thick) &
(cover cable trench) Overlay/Resurface
(50mm thick)
Excavation on paved - Sub base (200mm
road tick), Road base
(300mm tick) &
Premix (100-120mm
tick)
1. Project Manager
The Prime responsibility for site safety rests with him.
2. Safety Supervisor
The Site Safety Supervisor is responsible to the Project Manager for the day-to-
day implementation of the safety program.
8
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
He must be familiar with all the safety requirements in the contract along with
the safety local regulations and applicable safety codes and practices.
Carryout regular site safety audits and reports, correct unsafe work practices
and potential hazards.
Investigate and report all accidents including “near miss” incidents and
recommend preventive measures.
Maintain a record of all injuries and damages on site and submit reports as
required.
Assist with safety training.
Attend weekly supervisor’s meeting and discuss accident prevention techniques
and safety performance.
Ensure maintenance of good hygiene standards and availability of first aid
treatment.
Advise field supervision on safe working methods.
Enforce the observance of the work permit procedures.
Promote an understanding among the work force that accident prevention is an
indispensable part of any efficient construction activity.
3. Field Supervisor
4. Workers
The workmen, also has responsibilities for accident prevention, for not even the
best supervisor can watch over each man every minute of the working day.
9
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
Machine
Diamond Cutter Sand
Operator
Premix Gang
Colpave(SS1-K &
Lorry
RS1-K)
Premix (ACWC
14/20 & ACBC
20/28)
10
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
2. Traffic Control Work area not properly Ensure there is adequate advance
identified with Traffic Control signage, flaggers, cones, flashers &
Devices. strobes as required.
Trucks & workers getting hit by Pull off roadway as far as safely
other vehicles in traffic control possible. Use Caution Entering &
zone. Exiting vehicles.
4. HDD Works Damaging Existing Utilities Use safe and appropriate potholing
techniques to the planned drill path's
depth to expose any hidden
11
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
underground utilities.
Cable exposed to watery area Make sure the digging area is dry
and if the area is watery, use a water
pump to dry the area.
8. Cable Installation In Trench Trench Wall Collapse While Installing Cable in Trench
Trench
While Standing At Edge Lines, Enter The Trench. Do Not
Install From The Edge
9. Cable Installation Installing Cable In Energized Use Extreme Caution. Always Have
("Hot") Pedestals, Switchgear, Another Qualified Person at The
Transformers Location. Tape The Ends Before
Installation And Secure The Cable,
Don't Leave A Dangerous Situation
Mixing Phases Phase All Cable Before Installation
10. Testing & Grounding Grounding Accidental Contact Test & Ground All Equipment Before
with Energized Parts Performing Any Tasks. Spike All
Conductors Before Cutting Using a
Shotgun, FR Clothing, Safety
Glasses & Face Shield
11. Jointing Wrong Phasing Always make sure the cables are
marking correctly before jointing.
Defect on Joints Always make sure joints are in a
good condition before start jointing. If
there is a defect on joints, cut off the
joints & re joint the cables.
12. Termination Works Accidental Contact with Rubber up Energized Equipment If
Energized Parts Terminating or Working in Close
Proximity to Other Energized Parts.
Rubber Gloves Must Be Worn While
Terminating Secondary, Overhead
and URD
Mixing Phases- Flash or Phase All Cable Before Terminating
Outage
Sharp Edges or Corners Wear Leather Gloves While
Terminating
Damage to Conductors Being Ensure Proper Tools Are Used to
Terminated Avoid Damaging the Conductors
13. Final Testing Grounds Still on When Testing Ensure Grounds Are All Removed
Before Testing
Forgetting to Test A Cable Double Check to Ensure All Cables
Before Energizing Have Been Tested Before Placing
into Service
Testing Equipment Not Verify Testing Equipment Is in
Working Properly Working Order at Each Switch Point,
Equipment Must Be Clean, Within
Test Dates and Functional
Mixing Phases Check Phasing (Hot Phase/Bottle)
Before Energizing
Stray Voltages and Neutral Be Aware of The Possibility of Such
Imbalances Conditions and Test
13
METHOD OF STATEMENT CABLE LAYING (OPEN CUT WORKS)
By: Pelita Dinamik Engineering Sdn. Bhd.
14