for the Sub-Clause 6.9 [Contractor’s Personnel]


Contractor

Specific 1. The Contractor must employ appropriately skilled and experienced


Actions personnel;
2. If requested by the Engineer, the Contractor must remove any person
so requested from the Site and appoint a replacement (if necessary).

Time to act 1. For the duration of the Contract;


2. When requested.

Comment The Engineer may request a person to be removed from the Site for 4 reasons
as follows:
1. Persists in misconduct;
2. Is incompetent or negligent;
3. Fails to conform with the Contract; or
4. Acts in a way which is unsafe, unhealthy or damages the environment.
No other reasons are provided within this Sub-Clause.

Model Letter None.