Case Study:
Jawa-1 Power Plant Project
As part of a 1,760-megawatt combined-cycle gas turbine power plant project in
Indonesia, on behalf of GE, deugro moved approximately 80,000 freight tons of cargo,
including two 435-metric-ton gas turbine 9HA.02 units, two 460-metric-ton generator
stators (GEN STATs) units, and 52 heat recovery steam generators (HRSGs) with a length
of 30 meters and weights of up to 240 metric tons.
2 of 6 | www.deugro.com
Furthermore, space limitations for
the HRSG module storage at the
Port of Tanjung Priok, as well as a
limited feasibility to transfer the gas
turbine and gas turbine generators,
had to be taken into consideration.
Based on a route survey, deugro
Jakarta calculated the maximum
transport dimensions and weight
for the road freight and identified
the cargo items that could not be ready upon vessel arrival and, alongside the vessel, the cargo was
delivered by road but had to be at the same time, to avoid barge discharged directly from the vessel
transported by barge. congestion at the site jetty. to the barge using the vessel’s on-
board cranes in a double banking
For the oversized and heavy lift This case study refers to one of operation.
cargo, deugro Jakarta created a the most challenging components
concept in which the entire barge to be moved: a 438-metric-ton gas Prior to its arrival, the barge was
cargo was discharged directly from turbine with a volume of 12.11 x prepared with all the necessary
the vessel onto the barges at the 5.44 x 5.36 meters. equipment to receive the cargo,
Port of Tanjung Priok. This led to including stools, beams, steel
significant cost and time savings, plates for load spreading, and
as well as risk mitigation, since Arrival of the gas turbine notch wedges. Precise planning as
double-handling, storage in the at POD Tanjung Priok, well as barge- and cargo-specific
port and reloading onto barges Jakarta designs of the load spreading were
were avoided. required to stay within the technical
After over 8,550 nautical miles capacities of the locally available
In line with this concept and from Antwerp, Belgium via the barges.
the jetty’s limitation, a vessel Suez Canal to Jakarta, Indonesia,
arrival schedule was developed, the 438-metric-ton gas turbine Based on the grillage arrangement
matching the vessel sequence and was received by the barge at the and stowage plans provided by
arrival dates with barge and jetty Port of Tanjung Priok. Once the dteq engineers with the exact
availability to always have a barge tug maneuvered the barge safely measurements for the final
3 of 6 | www.deugro.com
» deugro’s
positioning, the gas turbine was ST-N-001 considering the criteria
unhooked after it was placed in of weather-restricted operations,
its final position on the prepared whereby departure was limited
transport stools and beams. To distribute to a maximum of Beaufort 5. In
the loads to the strong points of addition, for the voyage planning,
concept for the the barge deck, load spreading the location of subsea pipelines had
was applied according to dteq’s to be vetted. Once the seafastening
oversized and calculations to reduce the was accepted, the mooring lines
deck pressure and to meet the were released and the barge was
heavy lift cargo permissible uniform load of the pulled into the anchorage area
barge. in the harbor—ready to start its
led to significant 100-nautical-mile voyage from the
dteq created the design for the Port of Tanjung Priok to the job-site
cost and time seafastening on the accelerations jetty in West Cilamaya.
derived from the stowage-specific
savings, as motion analysis. The motions
for the barge transport were
well as risk calculated based on DNVGL-
mitigation. «
The challenges
• Limitations of the site jetty
in West Cilamaya, allowing
only one barge to berth at
a time
• The road from the port
to the construction site,
leading through several
space-limited villages
• Space limitations for the
HRSG module storage at
the Port of Tanjung Priok
• Various seasons with
continuously changing
weather conditions
4 of 6 | www.deugro.com
Roll-off operation at the
job-site jetty in West
Cilamaya
5 of 6 | www.deugro.com
Road transportation from Because the road from the jetty to
the jetty to the job site the job site had a ground-bearing
capacity of 4.8 metric tons, dteq’s
After successful roll-off, and transport engineers developed a
supported by escorts, flagmen, transport solution that remained
spotters and traffic management below this figure, while keeping the
as per site requirements, the trailer configuration short enough
convoy traversed seven kilometers to be able to navigate the purpose-
on the purpose-built road to built roadway.
the construction site and the
designated staging area using a Once the trailer was parked in its
Goldhofer THP multi-axle trailer. final position, the cargo was handed
over to the receiving team, and
To ensure safe maneuvering of deugro, in collaboration with dteq,
the cargo on the challenging road executed another extraordinary
infrastructure and the paths on project.
the construction site, as well as
successful delivery and on-site A mutual understanding, the
storage, dteq prepared detailed ability to tackle various seasons
swept path analyses, including and respond to continuously
turning simulations. These changing conditions, along with
determined safe and detailed open communication and solution-
transport paths and ensured that at oriented thinking, allowed deugro
each step there was sufficient space and its partners to complete this
for the trailers to maneuver. transport on time, on budget,
successfully and safely.