FRAMING CHECK REPORT (1/2)

Format No: Rev. No.: R-00 Project Engineer: Erector:


Effective Date: 01-01-2022 Page No.: 1 of 2 Project Manager: Date:
Project Name :- Location :- Project No. & Building Name:-
Particular Observation Observation Observation Observation
Date: Date: Date: Date:
Grid: to Grid: Grid: to Grid: Grid: to Grid: Grid: to Grid:
Yes No Remark Yes No Remark Yes No Remark Yes No Remark
Anchor bolt projection is as per Drg?
Nut of the anchor bolts are tightened?
Anchor Bolt
Pedestals

Lock nuts are provided with anchor bolts?


Plate Washers are provided with anchor bolts?
Proper Packing plates in the gap between the Base plate of Column and
RCC Column?
Turn-buckle is used in temporary bracings?
Guy Ropes

Guy ropes are provided with Columns/ Rafters?


Temporary bracings are installed at all haunches (Connection plates of
Rafter)?
Connection joint between rafter to rafter are tighten by turn of nut
Connectio

method / torque wrench


n joints

Gap between the connections plates have been filled with Shim plates?

Roof and wall bracing are installed as per Drg?


All Bracings

Flange Angle bracing are tightened?


Diagonal Rod bracing are tightened?
Diagonal Angle bracing are tightened?
Hill side washer and nut is provided with the diagonal bracings?
Hill side washer is fitted as per the drawing?
Inspected By Verified/Approved By
FRAMING CHECK REPORT (2/2)

Format No: Rev. No.: R-00 Project Engineer: Erector:


Effective Date: 01-01-2022 Page No.: 2 of 2 Project Manager: Date:
Project Name :- Location :- Project No. & Building Name:-
Particular Observation
Date:
Observation
Date:
Observation
Date: Date:
Observation

Grid: to Grid: Grid: to Grid: Grid: to Grid: Grid: to Grid:


Yes No Remark Yes No Remark Yes No Remark Yes No Remark
Machine bolts are correctly fitted in secondary framing?
All high strength bolts are fitted as per drawing requirements?
Connection Bolts

Washer installed with high strength bolts?


Thread projection of the bolts is maintained as per requirement?
High Tensile bolts are tightened by turn of the nut method?
High strength bolts are correctly tightened as per required torque/Turn of
Nut Method?
Correct sizes of bolts are used?
All bolts are fitted in all holes of connection plates?
Column is in plumb?
Framin

Main frame is correctly plumbed and aligned?


g

Crane beams are aligned?


Are stopper installed on crane beams?
Sag angles are correctly fitted and are per Drg.
Seconda
ry

Purlins are straight, Aligned and in uniform slope?


Girts/Side Runners are straight and aligned?
Girts/Side Runners are in plumb?
Final painting/Touchup is done as per requirement?
Inspected By Verified/Approved By