Date: 05/06/2023

Day: Monday
Attended By: Dhruv
Requirements Yes No Comments
Read Emails & notes from prev work shifts
Check all Wind Farms PME % Dynamic VAr Available Status OHWF DSTAT2@50% T@90%; HHWF DVar2@50% T@80%
Check All Wind Farms (PPC) Power Plant Controler
Check all Wind Farms Met Masts Availability Status HWF & HHWF MM2 No Comms NBHWF MM1 Wind Speed Error CGWF MM1
Daily Work Plan Received for all W/F
Data Gaps & Comments for All W/F
Check FM 119, 138 & 207 for All W/F
Confirm status of all stopped turbines with LT at 5:00pm
SMS Sent for Intruder Alarm at 5:00 pm SWF: T21
Check Palisade screen Dispatch, Status regularly
SMS Sent for Breakdowns HHWF:T09
Work Needs To Be Done / Information
HWF: Rob called to informed that they are switching off the whole windfarm for 15 min for electranet upgrade.@7:45 AM
OHWF: Called Nick to ask about the STATCOM system Warning, he will inform regarding soon. @10:00 AM

WLF: informed Bradley about Dvar Percentage Available priority 2 "ON" and PME 2 is also tripped. He advised that he will forward same to ASMC to have a look. @12:25 PM
Deleted Jarrod Sharp Contact number, as Venkatesh requested to do so.
HHWF: T09 staying down overnight.
NBH: T46 staying down due to Generator DE Bearing Failure

2nd Shift Attended By : Pragnesh


Requirements Yes No Comments
Read Emails & notes from prev work shifts
Check all Wind Farms PME % Dynamic VAr Available Status OHWF DSTAT2@50% T@90%; HHWF DVar2@50% T@80%
Check All Wind Farms (PPC) Power Plant Controler
Check all Wind Farms Met Masts Availability Status HWF & HHWF MM2 No Comms NBHWF MM1 Wind Speed Error CGWF MM1
Power Monitoring analysis
All Wind Farm Daily Reports Email sent
Capacitor check & Email sent
Schedule SMS for over night breakdowns
Check Elec Gen Brushes wornout warn event 421 & Email
Check Mech Gearoilfilter Chokedwarn event 48 & Email
Check Palisade screen Dispatch, Status regularly
Work Needs To Be Done / Information
Breakdown - sms schedule - HWF - 28;