B12

SEPTIC TANK ESTIMATE COPY


S.No Description Nos L B D Qty Rate unit Amount
(in Feet) (in Feet) (in Feet)
1 Earth Work Excavation
Earth Work Excavation for Septic 1 x 1 13 5 7 455.00 9 cft 4,095
Tank

2 Filling
Supplying and Filling with river sand. 1 x 1 13 5 0.33 21.45 51 cft 1,094

3 P.C.C
Providing and laying PCC 1:5:10 1 x 1 13 5 0.33 21.45 135 cft 2,896

4 Reinforced Concrete Work:


Providing and laying RCC 1:1.5:3 1 x 2 13 5 0.5 65.00 220 cft 14,300

5 Reinforcement
Reinforcement for R.C.C work including
straightening, cutting, bending, placing
in position & binding all TMT bars As per item 4 -65 65 221.00 63 13,923

6 Brick Work - 230mm:


Brick Work in cement mortar
Septic tank 1 x 1 34 0.75 6 153.00 156 cft 23,868
Cross wall (Baffle wall) 1 x 1 5 6 30.00 50 Sqft 1,500

7 Plastering
Plastering with cement mortar 1:5
(1 cement : 5 fine sand) of 12mm thickness. 1 x 1 34 6 204.00
Bottom of RCC slab 1 x 1 13 5 65.00
Crosss wall 1 x 2 5 6 60.00
329.00 30 Sq.ft 9,870

8 Manhole Lumpsum 2,000

9 Plumbing line Inlet, Outlet & Vent pipe etc Lumpsum 2,500

( Rupees Seventy six thousand fourty six only) Rs. 76,046