DOC No DS/CA006P02/00022

PAGE No 1 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

Index:
Form 1 Task Analysis Initiation
Form 2 Risk Assessment Process As per Risk Assessment Procedure.
Form 3 Written Safe Work Procedure Result

Compiled by the following team:


NAME DESIGNATION SIGNATURE
Project Manager Project Manager
Construction Manager Construction Manager
Site Engineer Site Engineer
Safety Officer Safety Officer
Risk Assessment Review 1 Review 2 Review 3 Review 4
Review Date: Date : Date : Date:

Name and Signature


of person reviewing :

AUTHORISATION
Prepared by: Approved by
Signature Date Signature Date
HSE Manager Project Manager

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 2 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

TASK ANALYSIS - FORM 1


Impact
SEQUENCE OF TASK STEPS POTENTIAL INJURIES OR HAZARDS RECOMMENDED CONTROLS
H, S, E
1. Pre-use inspection and use of all equipment. Failure of equipment will cause injuries to  Faulty equipment to be repaired/maintained or replaced.
persons and / or property damage.  Guards to be on all Machinery and appropriate PPE to
be worn.
Fuel/oil leaks could cause environmental  Engine ran machinery to have fire extinguishers
concerns. H, S, E
available locally.
 Drip trays/heavy gauge plastic to be used in case of
leaks and spill kit to be within the project for accidental
spills.
2. Wear appropriate Personal Protective Failure to use Personal Protective
Equipment. Equipment will cause injuries to employees
Gloves.
Safety boots.
H
Overalls.
Hard hat.
Hearing protection.  Enforce the use of Personal Protective Equipment AT
Eye protection. ALL times

3. Use competent employees only Failure will result in injuries to persons and /  Enforce the use of competent persons only
H, S
or property damage
4.  Competent supervisor should be appointed for every
activity to monitor the workers.
 Work task instruction should be provided for every
H, S activity.

Competent supervision Failure will cause injuries to employees and


or property damage
5. Before using the bucket Failure will result in accidents causing H, S  Ensure that bucket is in a good sound condition not
injuries to persons and / or property damage rusted or any visual cracks. Lifting handle no wear or
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
DOC No DS/CA006P02/00022
PAGE No 3 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

damage, test certificate available. Safety chain fitted.


6. Use only manual opening buckets Auto operating buckets can open during  Enforce the use of the correct buckets
lifting causing injuries to persons and / or H, S
property damage

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 4 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

TASK ANALYSIS - FORM 1 (continued)


SEQUENCE OF TASK STEPS POTENTIAL INJURIES OR HAZARDS RECOMMENDED CONTROLS
7. All buckets must be identifiable by means of Failure will allow the use of poor buckets  Ensure that all buckets are identifiable and enter in a
an I.D. and be on a register resulting in injuries to persons and / or H, S register
property damage
8. Adhere to the following Risk / Written Safe Failure will cause falling of material resulting  Adhere to Written safe work procedure
Work Procedure: in injuries to persons and / or property H, S
damage
9. Lifting the buckets using crane. Failure may result in injuries to persons and  Crane must be inspected and certified by third party.
property damage.  Enforce the use of competent operator and rigger.
 Rigger to ensure path of movement is kept free from
possible obstruction and / or persons.
 Ensure the use of certified lifting gears.
 Do not operate during adverse weather conditions.
H,S,
 Cordoned off the lifting area.
 Ensure nobody working under the suspended load.
 Ensure the visibility at all times.
 Ensure the availability and accuracy of wind speed
meter on the equipment and do not operate above 35
KPH.
10. Use guide rope on the bucket during slewingFailure will allow the bucket to bump into  Enforce the use of guide ropes
equipment or constructions leads to injury to S
the person and property damage.
11. All buckets must be third party certified to Failure will allow the use of poor buckets  Ensure that all buckets are third party certified and
ensure compliance to regulations resulting in injuries to persons and / or H, S, E entered in a register to control.
property damage

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 5 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

RISK ASSESSMENT – FORM 2


Risk Rating Calculation
A + B + C + D
Injury Severity Potential Damage / Loss Frequency or Likelihood Environmental Impact
0 No injury 0 No damage 0 Never happened before 0 No effect
1 Minor – (FAC) 1 Minor < 500 AED, No delay 1 Happened somewhere 1 Minor Effect - Short term < less 1 month
2 Major – (MTC) 2 Major > 500 AED, No delay 2 Happens occasionally 2 Major Effect - Long term > greater 1 month
3 LTI 3 Major > 10 000 AED, one day delay 3 Happened before  
4 Disabling Injuries 4 Serious > 100, 000 AED, >1 day delay 4 Happens regularly Risk Rating Matrix
5 Fatality 5 Severe > 1, 000, 000 AED, Weeks delay. 5 Daily occurrence
Risk Rating = A + B + C + D.
Result Classification: Risk Rating
16
14

Critical = 17►15 High = 14►11 Medium = 10►7 Low = 6►0 12


10
Immediate action. Action in 24 hours. Action in a week. ASAP. 8
6
4
Risk Reduction Hierarchy: 2
0
1. Engineering to reduce risk. 1
5
2. Replacement with lower risk. 2
3
4
4
3
3. Isolation of risk – Barricading or Guarding. Potential Impact
5
6
2
Probability
(C)
7
4. Reduction of exposure to risk. (A / B / D) 8
9 1
5. PPE and Training

RISK ASSESSMENT – FORM 2 (continued)


SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
DOC No DS/CA006P02/00022
PAGE No 6 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED RISK ASSOCIATED WITH HAZARD H, S, E RR BY WHOM RR
DEALT WITH WHEN
1  Faulty hand tools Bruises, cuts. Gloves, trowels in good Supervisor Before &
condition. during
 Mechanical guards not Entanglement, Skeletal Damage. the use
in place Guards in place and equipment of
H,S,E 13 regularly maintained. equipme 6
nt
 Unwanted Fuel/Oil Contamination of the soil, atmospheric Care to be taken refuelling and
Spillages pollution, risk of fire. drip trays/heavy gauge plastic to
be in place as required.
2 Injury to project Potential Death, Major/Minor Skeletal Following PPE to be worn Supervisor Before &
employees damage, cuts and bruises to all parts of appropriately to the task – during
the body, asthma. Gloves. work
Safety boots.
H,S 10 5
Overalls.
Hard hat.
Hearing protection.
Eye protection
3 Un trained employees Poor quality of work, chance for Provided trained/competent PE/FM Always
H,S 7 5
accident /incident or property lost/damage worker and supervision
4 Lack of supervision Poor quality of work, chance for Ensure the availability of PE/FM Always
accident /incident or property lost/damage competent supervisor at work
place.
H,S 10 3
Work task instruction should be
provided to the workers prior to
the commencement of activity
5 Using substandard Collapse of the buckets H,S 10 Ensure that bucket is in a good FM/ Before 3
buckets Minor/major injuries/potential death sound condition not rusted or any Supervisor and
Property damage. visual cracks. Lifting handle no during
Uncertified buckets wear or damage, Safety chain work

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 7 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED RISK ASSOCIATED WITH HAZARD H, S, E RR BY WHOM RR
DEALT WITH WHEN
fitted.
Never overload the buckets,
comply with the SWL
Enforce the use of third party
certified buckets
6 Use of auto opening Minor/major injuries/potential death Enforce the use of manual FM/ Before
buckets Property damage. opening buckets Supervisor and
H,S 7 4
during
work
7 Buckets not identified and The use incorrect equipment can cause 10 Ensure that all buckets are Supervisor Always
on register Minor/major injuries/potential death H, S identified and on register 2
Property damage
8 Failure to follow Written Minor/major injuries/potential death 10 Enforce adherence to Written
safe work procedure. Property damage. H,S safe work procedure.

9 Failure to adhere to lifting Falling materials. Crane must be inspected and FM/ Always
procedures while using Minor/major injuries/potential death certified by third party. Supervisor
crane Property damage. Enforce the use of competent
operator and rigger.
Rigger to ensure path of
movement is kept free from
possible obstruction and / or
H, S persons. 3
Ensure the use of certified lifting
gears.
12 Do not operate during adverse
weather conditions.
Cordoned off the lifting area.
Ensure nobody working under
the suspended load.

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 8 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED RISK ASSOCIATED WITH HAZARD H, S, E RR BY WHOM RR
DEALT WITH WHEN
Ensure the visibility at all times.
Ensure the availability and
accuracy of wind speed meter on
the equipment and do not
operate above 35 KPH..
10 Not using guide ropes Minor/major injuries/potential death 12 Enforce the use of guide ropes Supervisor During
H, S 2
Work
9 Uncertified buckets and Property damage. 12 Ensure that all buckets and the FM/ Always
lifting appliances lifting appliances are third party Supervisor
H, S 2
certified and entered in a register
to control.
* RR = Risk Rating

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 9 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

WRITTEN SAFE WORK PROCEDURE


1. OBJECTIVE
1. To prevent injuries to employees and / or property damage incidents.

2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
3.1. Hardhat.
3.2. Safety boots.
3.3. Overalls.
3.4. Eye protection.
Prior to work commencement

1. Must have PPE – safety footwear, gloves, hardhat, goggles, foul weather clothing etc.
2. Must have appropriate tools and equipment in good condition.
3. Must have weatherproof covers for materials and equipment, waste containers, warning tape.
4. Consider risks and hazards in work area. Refer any concerns to supervisor. Are relevant permits in place?
5. Check if it is necessary to secure area adjacent to work. Refer to supervisor if appropriate.
6. Arrange for transport of materials and equipment to site via supervisor.
7. Ensure materials and equipment are secure or removed when site unattended, eg overnight or during breaks.

Hazards

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 10 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

1. Manual handling of materials and equipment – LITE to be considered at all times.


2. Slips and trips from untidy work area.
3. Falling materials
4. Collapse of buckets
5. Hazards associated with equipment eg. striking to structures/persons
6. Contact with sharp edges
7. Consideration of weather and ground conditions must be made. If in doubt refer to supervisor.

Harm
Potential Death, Minor/major cuts and contusions, loss of limbs, fractures, concussion, to fatality, electric shock, environmental
damage

Persons in danger

1. Rigger, labours
2. Other workers/visitors in vicinity

Control measures

No lone working

SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE


DOC No DS/CA006P02/00022
PAGE No 11 of 11
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 045
Job Description: Using a Concrete, Material and/or Sand Bucket.

1. Ensure the availability of all required certification for the lifting equipment attached to the bucket
2. Use proper buckets only.
3. Do not use any buckets that is not identified and on register.
4. Also adhere to the following Risk / Written Safe Work Procedure:
i. Usage of crane.
ii. Slinging and slewing.
iii. Slinging and slewing tower crane.
5. Use guide rope during slewing of any bucket.
6. Use only Third party Certified Buckets.
7. Never overload any bucket, comply with the Safe working load.