Professional Documents
Culture Documents
Hydropower
Project
(10 MW)
Ilam, Nepal
Bi- Annual
Progress
Report (Ashoj
2078 B.S. to
Falgun 2078
B.S.)
Submitted to:
Department of
Electricity
Development
Siddhi Hydropower
Company Pvt. Ltd.
Chaitra, 2078
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
ABBREVIATIONS
€ Euro
mm Millimeter
cm Centimeter
m Meter
km Kilometer
kg Kilogram
m2 Square meter
cu m or m3 Cubic meter
kW Kilowatt
kV Kilovolt
MW Megawatt
GW Gegawatt
Hz Hertz
FY fiscal year
SALIENT FEATURES
Accessibility
By Airways
Kathmandu to Bhadrapur : Direct flight (to and fro)
By Vehicle, nearest road head “Harkate Bazaar”
Kathmandu – Phidim : 740 km (Black topped)
Bhadrapur – Harkate : 30 km (Black topped)
Harkate – Ramyang Gaun : 10 km (Earthen road)
Ramyang Gaun to the Project‟s Components sites : 18 km (New construction)
Transmission Line
Length and Voltage : 16 km (33 kV)
Connection point : Fikkal Sub-station, Ilam
Hydrology
Catchment Area at Intake : 65 km2
3
Annual Average Flow : 4.53 m /s
Design Discharge : 3.60 m3/s
Compensation Flow : 0.10 m3/s
Flood
Design Flood Discharge (1 in 100 years) at Weir : 349 m3/s
Design Diversion Discharge (1 in 5 years) : 125.70 m3/s
Diversion Weir
Type : Concrete Free flow, Ungated
Length : 23 m
Weir crest level : 816.00 masl
Width of undersluice : 3.0 m
Sill level of undersluice : 813.50 masl
Intake
Type and numbers of Intake : Side intake, orifice Type, 2 Nos.
Opening dimension : 3.2 m x 1.0 m (W x H)
Invert level of intake : 815.00 masl
Gravel trap
Length/ Width/ Height : 5.0 m x 3.0 m
Gate : 1 No, 1.0 m (H) x 1.0 m (W)
Settling Basin
No of Chambers : Two chambers
Dimension (length x width x overall depth) : 43.00 m x 4.8 m x 5.0 m
Trapping efficiency : 90 %
Nominal size of trapped particles : 0.20 mm
Headrace Canal
Length and Type : 600 m, RCC culvert
Finished section : 2.0 m x 1.5 m
Slope : 1/1000
Headrace Tunnel
Length and Type : 1200 m, Inverted D-Shape
Diameter : 2.5 m
Slope : 1/1000
Surge Tank
Dimension : 4.5 m dia, 25 m height
Capacity : Over 180 seconds of design flow
Penstock pipe
Length and Type : 1800 m, Exposed on surface
Diameter : 1.4 m
Thickness : 8 - 26 mm
Number of expansion joints 30
Number of support piers 300
Powerhouse
Type : Surface
External Dimension (LxWxH) : 29.7 m x 11.6 m x 17.0 m
Tailrace canal
Type / length : Rectangular RCC / 100m after tailrace junction
Dimension : 1.8 m x 1.4 m
Turbines
Turbine type / layout/ unit : Pelton / horizontal/ 2 nos.
Rated output : 5000 kW each
Rated efficiency at 100 % load : 90 %
Rated speed : 500 rpm
Governor
Type : Electronic, PI (D)
Actuator : Oil-hydraulic, self-closing w/o electric power
Generator
Type / layout/ unit : Brushless Syn 3Ø / horizontal/ 2 nos.
Rated capacity : 5900 kVA each
Rated efficiency : 96 %
Rated speed / Frequency : 500 rpm / 50 Hz
Power factor : 0.85
Transformer
Type/ nos. of unit : Step up, Single phase / 3+1 spare.
Rated capacity/ efficiency : 4300 kVA / 99 %
Voltage level : 6.3/33 kV
Frequency : 50 Hz
Switchyard
Type : Outdoor
Size : 30 m x 15 m
Financial Results
Project IRR : 14.86%
Equity IRR : 19.70%
NPV, NRs. „K : 670,051
BCR : 1.42
Energy generation cost per unit, NRs/kWh : 3.43
DSCR : 1.18 (1st Yr.), 1.27 (2nd Yr.), 1.34 (3rd
Yr.) …. 2.45 (11th Yr.) & 2.67 (12th Yr.)
Average DSCR : 1.87
Table of Contents
1. BACKGROUND ..................................................................................................... 1
2. OBJECTIVE ........................................................................................................... 1
3. PROJECT INTRODUCTION .................................................................................. 1
4. PROJECT LOCATION and ACCESSIBILITY ......................................................... 1
5. KEY ACHIEVEMENTS TILL DATE ........................................................................ 2
5.1. Transfer of Generation License to Siddhi Hydropower Company Pvt. Ltd .............. 2
5.2. Renewal of Generation License ............................................................................. 2
5.3. Power Purchase Agreement (PPA) Documentation: .............................................. 2
5.4. Connection Agreement .......................................................................................... 2
5.5. Transfer of Transmission Line License to Siddhi Hydropower Company Pvt. Ltd. .. 2
5.6. Renewal of Transmission Line Survey license ....................................................... 2
5.7. Industry Registration .............................................................................................. 2
5.8. Contract for Consulting Services ............................................................................ 2
5.9. Engineering Study on „Bankable Detailed Feasibility Study‟ ....................................... 3
5.10. Financial Closure ................................................................................................... 3
5.11. Tendering and Contracting..................................................................................... 3
5.12. Coordination Committee ........................................................................................ 4
6. PROJECT PROGRESS ......................................................................................... 5
6.1. Detail Engineering Design...................................................................................... 5
6.2. Camp Facilities ...................................................................................................... 5
6.3. Access Road Development Programme ................................................................ 7
6.3.1 Description of Road Alignment ............................................................................... 7
6.3.2 Construction of Access Road ................................................................................. 8
6.4. Civil Works ........................................................................................................... 10
6.4.1 Construction Works .............................................................................................. 10
6.4.2 Expert Visit ........................................................................................................... 11
6.4.3 Field Mobilization.................................................................................................. 12
6.4.4 Field Program....................................................................................................... 13
6.5. Electromechanical Works..................................................................................... 13
6.6. Transmission Line System ................................................................................... 13
6.6.1. NEA Team Visit ................................................................................................... 13
7. PROJECT OBSTRUCTION ................................................................................. 14
7.1. Pre-Monsoon and Monsoon Period...................................................................... 14
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
List of Tables
List of Plates
Cover Photo:
1. BACKGROUND
Siddhi Khola is one of the tributary of Mechi River which flows in Province-1 of Nepal. Siddhi
Khola Hydropower Project is promoted by Siddhi Hydropower Company Pvt. Ltd
The proposed Project is located at Rong Gaupalika and Suryodaya Municipality of Ilam District
of Nepal. The project is of capacity 10 MW having the gross head of 343 m and design
discharge of 3.60 m3/s. The project boundary having coordinates of: Latitudes-26° 49‟ 39” N
to 26° 50‟ 43” N and Longitudes-88° 08‟ 00” E to 88° 09‟ 50” E.
The generation license for the project was issued from Government of Nepal (GoN), Ministry
of Energy (MoE), and Department of Electricity Development (DoED) on 2072/06/13 B.S. and
later renewed on 29th kartik 2074 B.S. Further financial closure agreement was signed on 28th
Siddhi Hydropower Company Pvt. Ltd. Department of Electricity Development (DoED)
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
Poush, 2074 B.S. with Prime Commercial Bank Limited as a lead bank and Nepal Investment
Bank Limited as a co-lead bank.
2. OBJECTIVE
The main objective is to highlight the Bi-Annual activities that has been carried out during the
last six months i.e. from Ashoj 2078 B.S. to Falgun 2078 B.S.
3. PROJECT INTRODUCTION
Siddhi Khola Hydropower Project (SKHP) is located in Rong Gaupalika and Suryadaya
Municipality in Ilam district, Province No. 1 of Nepal. The project structures are laid out mainly
in Rong Gaupalika whereas only part of the diversion weir and left bank abutment structures
lie in Suryadaya Municipality. The headwork site is located in Suryadaya Municipality, downhill
of Kharbani Village on the left bank of Siddhi Khola and is proposed at an elevation of 816
masl on a relatively flat terrain. Powerhouse is located in Rong Gaupalika, downhill of
Ranbhede village on the right bank of Siddhi Khola. It is approximately 2 km upstream from
the confluence of Siddhi Khola with Mechi River. The elevation of the proposed powerhouse
site is approximately 473 m which gives the gross head of about 343 m. The power produced
will be fed to Phikkal Sub-station, located at Phikkal of Illam District through 33 kV
Transmission Line of about 16 km length. The design discharge and gross head of 3.6 m³/sec
and 343.00 m respectively has been proposed for generating installed capacity of 10 MW.
5.5. Transfer of Transmission Line License to Siddhi Hydropower Company Pvt. Ltd.
The developer had submitted an application letter for transfer of 33 kV transmission line
survey license to Siddhi Hydropower Company Pvt. Ltd. on 10th Shrawan 2074 B.S.
Later, the transmission line survey license was transferred in the name of Siddhi
Hydropower Company Pvt. Ltd. on 05th Bhadra 2074 B.S.
Similarly, the developer has awarded the contract for carrying out Feasibility Study Report
(FSR) and IEE of Transmission Line System to Samyak Consulting Engineers Pvt. Ltd. on
11th Poush, 2073 B.S.
The Developer has published tender notice to execute civil, hydro-mechanical and
transmission line works for SHC from national level Contractors through national daily
newspaper. A number of Contractors have submitted the bid documents and the
evaluation of bids is in progress. Evaluation, negotiation and award of those contracts is
expected to be completed by the end of Chaitra 2074 B.S.
As mentioned in the previous progress report, the consultant coordinating with the
developer has vigorously carried out desk study. Various alternatives for the project layout
were studied in the topographical maps. To produce various project layout alternatives,
the components of the projects were plotted in the tentative location in the topographical
maps.
Financial Closure Agreement has been successfully signed on 28th Poush 2074 B.S. with
Prime Commercial Bank Limited as a lead bank and Nepal Investment Bank Limited as a
co-lead bank.
Notice Publication
The invitation of the bid for Civil Works, Hydro Mechanical Works, Transmission Line and
Infrastructure Development was done on 13th Kartik 2074 B.S.
The submitted bid documents by aforementioned three contractors were opened in the
presence of Management and Evaluation Committee and bidding contractors.
Bid Evaluation
Samyak Consulting Engineers Pvt. Ltd. (SCE) completed the technical evaluation of the
bid documents and submitted to Siddhi Hydropower Company Pvt. Ltd. on 30th Falgun
2074 B.S.
Among the three competitive bidders that had participated in the open competitive bidding
Mainachuli NIrman Sewa Pvt. Ltd. had quoted the least price (amount) for all the works
that included Civil Works, Hydro mechanical works, Transmission Line and Infrastructure
Development.
Contract Approval
Based on the technical evaluation of Samyak Consulting Engineers Pvt. Ltd., the
Management and Evaluation Committee (MEC) had prepared the evaluation report for the
submission to the Board. Hence, the Board had concurred the evaluation report and the
contract was awarded to Mainachuli Nirman Sewa Pvt. Ltd.
Mr. Devendra karki Project Engineer, Siddhi Hydropower Company Pvt. Ltd.
Mr. Sachhidanand Yadav Chief, Biratnagar Regional Office, Nepal Electricity Authority
Based on the meeting, NEA has formed a committee of 4 members; 2 members from Nepal
Electricity Authority and 2 members from Biratnagar Regional Office for visiting the site for
power evacuation procedure.
Siddhi Hydropower Company Pvt. Ltd. Department of Electricity Development (DoED)
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
6. PROJECT PROGRESS
Remarkable progresses has been achieved during these past six month at the project site.
Various construction works were carried out and completed on the field of camp, access road,
civil works, hydro mechanical works and electromechanical works which are described below
in subsequent sub headings.
There are two stretches of road; one to the headworks site and the other to the
powerhouse site. The existing black topped road is available up to Harkate. Further, an
earthen road is available from Harkate to Rambyang Village (i.e. up to Rambyang School).
From Rambyang i.e. School area, the access road bifurcates into two different ways. One
leads to the headworks site (i.e.: North East direction) and the other leads to the
Siddhi Hydropower Company Pvt. Ltd. Department of Electricity Development (DoED)
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
Powerhouse site (South East direction). The land acquisition and track opening of these
roads has been carried out by the Developer (SHC).
SHC has opened up track road of 5 km length from Rambyang to the Headworks site.
Further, SHC has also opened up track road of 1 km length from Rambyang Puchhar
(Bhanjyang) towards the powerhouse site.
From Rambyang Puchhar (Bhanjyang), an access road bifurcates, one towards Syphon
2 (river crossing) area and another towards the powerhouse sites. These access road
passes through barren land, cultivation land, forest and wet land. The average ground
slope of this area is 35 degree.
Plate 5 newly constructed earthen road by the locals from Rambyang Village Junction (school Area)
Along the headworks site, about five Cross Drainage structures are required for vehicular
movement. Presently, there is a suspension bridge over Siddhi Khola at about 100 m
downstream from dam site. And about 4 cross drainage structures are required along the
Rambyang Puchhar. Further, 3 cross drainage structures are required along access road
towards Surge tank. Similarly, 2 cross drainage structures are required along the access
road towards powerhouse site.
However, these tracks of access road has to be widened up, upgraded with appropriate
road geometrics for ease mode of heavy equipment transportation during the construction.
For this, detailed survey of road alignment was conducted and access road design report
was prepared.
6.3.2Construction of Access Road
Construction of remaining 1.5 km long Access Road towards headworks site was
completed on the month of Chaitra, 2074 B.S.
Construction of 1.5 km access road from Rambyang Chautara to Powerhouse was
initiated. However, due to heavy rainfall in project area, road construction was stopped.
The construction was resumed from 2nd week of Bhadra, 2076 B.S. However, due to recent
Covid-19 outbreak across Nepal, the ongoing construction works was stopped. However,
the construction activities at site was resumed from 1st Week of Ashoj, 2077 B.S. giving
priority to the remaining 500 m access road towards powerhouse. By the end of Magh,
Siddhi Hydropower Company Pvt. Ltd. Department of Electricity Development (DoED)
Siddhi Khola Hydropower Project (SKHPP) Progress Report as of Ashoj 2078 to Falgun 2078
2077 B.S., the access road connecting powerhouse was finally completed.
However, Due to the heavy monsoon, the access road gets disturbed after the
accumulation of heavy debris. The Developer has to engage in maintenance of the
access/construction road time and again.
Stone masonry works for tailrace canal of 100 m length has been contructed and
completed.
Excavation work of settling basin area at headworks site has been initiated.
Plate 9: Site clearance work of Intake and gravel trap area at headworks
6.4.2Expert Visit
An expert visit was made by team of technical experts on the month of Chaitra 2074. The
team of experts comprises the following individuals-
Based on the investigation during the field trip, all the required materials like cement,
reinforcement bar, gabion-wire etc. should be transported from Kakarvitta. Gravel, sand,
boulder and aggregate are available at the Siddhi Khola and Mechi Khola. Boulders
required for construction of causeway and retaining walls are locally available.
6.4.3Field Mobilization
A team of technical experts has been mobilized to site from the month of Falgun 2074
B.S. for construction and supervision of access road development and land acquisition
programme.
6.4.4Field Program
i. Discharge Measurement :
Although the inception study was in progress, in order to obtain dry season monthly flows,
spot discharge measurement of the Siddhi Khola using current meter had been carried
out. The date and measured discharge is presented in Table 1.
7. PROJECT OBSTRUCTION
Later again after the pandemic still on the threat, second nationwide lockdown was
declared from Baisakh 16, 2078 B.S. as a result of which all the construction activities had
to be stopped. Later from Shrawan 1, 2078 B.S., the lockdown was uplifted and the
construction site was resumed.
8. BANK VISIT
A team of three members from the financing banks namely Prime Commercial Bank Ltd. and
Nepal Investment Bank Limited visited the site from 12th December 2018 to 14th December
2018 (26th – 28th Mangsir, 2075). This was a routine inspection visit as a requisite of Financial
Closure Agreement concluded between the Company and the consortium banks.
Kartik 2078 Site clearance of Intake, Gravel trap and Connecting canal
Mangsir 2078 Access road maintenance of both Headworks and Powerhouse site
Poush 2078 Access road maintenance of both Headworks and Powerhouse site