DATE VISITED July 3-8, 2023 WORKING HOURS 7am to 5pm
TIME AVE. MANPOWER (MP) 12 Complete PPE, One Bagger Mixer, Welding CONTRACTOR MATERIALS Machine, Steel Cutter, Basic Tools, etc. PROJECT CONSTRUCTION OF 3-STOREY APARTMENT BUILDING DATE ITEM No. ACTIVITIES WEATHER
• Fabrication of roof beam formworks at 2nd Floor Dietary Kitchen
• Started constructing roof framing (purlins and channels) at the lower roof beam of Morning: July 3, 2023 SUNNY 1 Dietary Kitchen MP : 12 Afternoon: • Continuation of 6" Thk CHB Wall on ground floor at Dietary Kitchen GLOOMY • Continuation of concrete plastering at Perimeter Walls.
• Continuation of roof framing fabrication on lower roof at Dietary Kitchen Morning:
July 4, 2023 • Fabrication of formworks for stairs at Dietary Kitchen SUNNY 2 MP : 13 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen. Afternoon: •Continuation of concrete plastering at Perimeter Walls. SUNNY
• Continuation of roof framing fabrication on lower roof at Dietary Kitchen Morning:
July 5, 2023 • Fabrication of formworks for stairs at Dietary Kitchen SUNNY 3 Afternoon: MP : 14 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen. •Continuation of concrete plastering at Perimeter Walls. SUNNY
• Continuation of roof framing fabrication on lower roof at Dietary Kitchen
• Fabrication of formworks for stairs at Dietary Kitchen Morning: July 6, 2023 SUNNY 4 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen. MP : 15 Afternoon: •Continuation of concrete plastering at Perimeter Walls. SUNNY •On-going site clearing at perimeter wall
• Continuation of roof framing fabrication on lower roof at Dietary Kitchen
Morning: • Fabrication of formworks for stairs at Dietary Kitchen July 7, 2023 SUNNY 5 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen. MP : 16 Afternoon: •Continuation of concrete plastering at Perimeter Walls. SUNNY •On-going site clearing at perimeter wall