Project: Three Storey Residential

Apartment Building DAILY PROGRESS REPORT

Owner: Mr. Samuel Alvarado

DATE VISITED July 3-8, 2023 WORKING HOURS 7am to 5pm


TIME AVE. MANPOWER (MP) 12
Complete PPE, One Bagger Mixer, Welding
CONTRACTOR MATERIALS
Machine, Steel Cutter, Basic Tools, etc.
PROJECT CONSTRUCTION OF 3-STOREY APARTMENT BUILDING
DATE ITEM No. ACTIVITIES WEATHER

• Fabrication of roof beam formworks at 2nd Floor Dietary Kitchen


• Started constructing roof framing (purlins and channels) at the lower roof beam of Morning:
July 3, 2023 SUNNY
1 Dietary Kitchen
MP : 12 Afternoon:
• Continuation of 6" Thk CHB Wall on ground floor at Dietary Kitchen GLOOMY
• Continuation of concrete plastering at Perimeter Walls.

• Continuation of roof framing fabrication on lower roof at Dietary Kitchen Morning:


July 4, 2023 • Fabrication of formworks for stairs at Dietary Kitchen SUNNY
2
MP : 13 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen. Afternoon:
•Continuation of concrete plastering at Perimeter Walls. SUNNY

• Continuation of roof framing fabrication on lower roof at Dietary Kitchen Morning:


July 5, 2023 • Fabrication of formworks for stairs at Dietary Kitchen SUNNY
3 Afternoon:
MP : 14 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen.
•Continuation of concrete plastering at Perimeter Walls. SUNNY

• Continuation of roof framing fabrication on lower roof at Dietary Kitchen


• Fabrication of formworks for stairs at Dietary Kitchen Morning:
July 6, 2023 SUNNY
4 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen.
MP : 15 Afternoon:
•Continuation of concrete plastering at Perimeter Walls. SUNNY
•On-going site clearing at perimeter wall

• Continuation of roof framing fabrication on lower roof at Dietary Kitchen


Morning:
• Fabrication of formworks for stairs at Dietary Kitchen
July 7, 2023 SUNNY
5 •Continuation of laying out 6" Thk CHB Walls at 2nd Floor of Dietary Kitchen.
MP : 16 Afternoon:
•Continuation of concrete plastering at Perimeter Walls.
SUNNY
•On-going site clearing at perimeter wall