Professional Documents
Culture Documents
Akkialur Bridge
Akkialur Bridge
Akkialur via Somapur road (Hangal Constituency) in Hangal taluk, Haveri district
Earth work excavation for Foundation by mechanical means for all works & depth
upto 3 m, as per drawing and technical specifications, including setting out,
shoring, strutting, barricading, caution lights, including dressing of excavated
2 surfaces, disposing off or levelling the excavated earth or sorting & stacking the
selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of
labour, tools, usage of machinery & other appurtenaces required to complete the
work
For Pile Cap
In Abutment A1 1 2.900 12.90 2.265 84.734
In Pier P1 1 5.100 12.60 2.515 161.614
In Pier P2 1 5.100 12.60 2.515 161.614
In Pier P3 1 5.100 13.00 2.515 166.744
In Pier P4 1 5.100 13.00 2.510 166.413
In Pier P5 1 5.100 13.00 2.485 164.756
In Pier P6 1 5.100 13.30 2.535 171.949
In Pier P7 1 5.100 13.30 2.465 167.201
In Pier P8 1 5.100 13.30 2.495 169.236
In Pier P9 1 5.100 13.30 2.485 168.558
In Pier P10 1 5.100 12.60 2.515 161.614
In Abutment A2 1 2.000 16.80 2.800 94.080
In retaining wall towards A1 1 5.150 8.80 0.150 6.798
1
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
In retaining wall towards A2 1 5.150 9.10 0.150 7.030
Total 1852.34 Cum
Providing Steel Liner 10 mm thick for Curbs and 6 mm thick for Steining of
3
Wells including Fabricating and Setting out as per Detailed Drawing.
For Piles
In Abutment A1 5 Circum= 0.148 7.000 5.180
In Pier P1 6 Circum= 0.178 7.000 7.459
In Pier P2 6 Circum= 0.178 7.000 7.459
In Pier P3 6 Circum= 0.178 7.000 7.459
In Pier P4 6 Circum= 0.178 7.000 7.459
In Pier P5 6 Circum= 0.178 7.000 7.459
In Pier P6 6 Circum= 0.178 7.000 7.459
In Pier P7 6 Circum= 0.178 7.000 7.459
In Pier P8 6 Circum= 0.178 7.000 7.459
In Pier P9 6 Circum= 0.178 7.000 7.459
In Pier P10 6 Circum= 0.178 7.000 7.459
In Abutment A2 6 Circum= 0.178 7.000 7.459
Total 87.224 t
Supplying, Fitting and Placing un-coated TMT Fe 500 & above bar
4 Reinforcement in Foundation complete as per Drawing and Technical
Specifications.
Reinforcement in piles
In Abutment A1 5 Weight= 1.332 6.658
In Pier P1 6 Circum= 1.474 8.842
In Pier P2 6 Circum= 1.474 8.842
In Pier P3 6 Circum= 1.474 8.842
In Pier P4 6 Circum= 1.474 8.842
In Pier P5 6 Circum= 1.474 8.842
In Pier P6 6 Circum= 1.474 8.842
In Pier P7 6 Circum= 1.474 8.842
In Pier P8 6 Circum= 1.474 8.842
In Pier P9 6 Circum= 1.474 8.842
In Pier P10 6 Circum= 1.474 8.842
In Abutment A2 6 Circum= 1.474 8.842
Total 103.922 t
2
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as
5 per Drawing and Technical Specifications and removal of excavated earth with
all lifts and lead upto 1000 m.(1000mm diameter)
1000mm diameter
In Abutment A1 5 A= 0.786 15.000 58.913
Total 58.913 Cum
Providing and laying in position Plain cement concrete for levelling course for
all works in foundation. The granite/trap/basalt crushed graded coarse
aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in
layers not exceeding 150 mm thickness, well compacted using plate vibrators,
7 including all lead & lifts, cost of all materials of quality, labour, Usage charges of
machineries, curing, and all the other appurtenances required to complete the
work as per technical specifications. (The cost of steel reinforcement & formwork
shall be paid separately) Mix 1:3:6 (M10) Using 40 mm nominal size graded
crushed coarse aggregates
For Pile Cap
In Abutment A1 1 2.9 12.9 0.15 5.612
In Pier P1 1 5.1 12.6 0.15 9.639
In Pier P2 1 5.1 12.6 0.15 9.639
In Pier P3 1 5.1 13 0.15 9.945
In Pier P4 1 5.1 13 0.15 9.945
In Pier P5 1 5.1 13 0.15 9.945
In Pier P6 1 5.1 13.3 0.15 10.175
3
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
In Pier P7 1 5.1 13.3 0.15 10.175
In Pier P8 1 5.1 13.3 0.15 10.175
In Pier P9 1 5.1 13.3 0.15 10.175
In Pier P10 1 5.1 12.6 0.15 9.639
In Abutment A2 1 2 16.8 0.15 5.040
In retaining wall towards A1 1 5.15 8.8 0.15 6.798
In retaining wall towards A2 1 5.15 9.1 0.15 7.030
Total 123.929 Cum
Supplying, Fitting and Placing un-coated TMT Fe 500 & above bar
8 Reinforcement in Foundation complete as per Drawing and Technical
Specifications.
Reinforcement in pile cap (250 kg/cum)
In Abutment A1 1 250 kg/cum 49.140 12.285
In Pier P1 1 250 kg/cum 109.224 27.306
In Pier P2 1 250 kg/cum 106.272 26.568
In Pier P3 1 250 kg/cum 106.272 26.568
In Pier P4 1 250 kg/cum 106.272 26.568
In Pier P5 1 250 kg/cum 106.272 26.568
In Pier P6 1 250 kg/cum 112.320 28.080
In Pier P7 1 250 kg/cum 112.320 28.080
In Pier P8 1 250 kg/cum 112.320 28.080
In Pier P9 1 250 kg/cum 112.320 28.080
In Pier P10 1 250 kg/cum 106.272 26.568
In Abutment A2 1 250 kg/cum 51.893 12.973
Total 297.724 t
9 Centering 25% of Concrete Qty of Pile cap
For Pile cap 1 0.250 1190.9 297.724
297.724 Sqm
4
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
In Abutment A1 1 2.600 12.60 1.500 49.140
In Pier P1 1 4.800 12.30 1.850 109.224
In Pier P2 1 4.800 12.30 1.800 106.272
In Pier P3 1 4.800 12.30 1.800 106.272
In Pier P4 1 4.800 12.30 1.800 106.272
In Pier P5 1 4.800 12.30 1.800 106.272
In Pier P6 1 4.800 13.00 1.800 112.320
In Pier P7 1 4.800 13.00 1.800 112.320
In Pier P8 1 4.800 13.00 1.800 112.320
In Pier P9 1 4.800 13.00 1.800 112.320
In Pier P10 1 4.800 12.30 1.800 106.272
In Abutment A2 1 1.700 16.50 1.850 51.893
Total 1190.897 Cum
5
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
Providing and laying in position Reinforced cement concrete for all Sub
structures of building, Irrigation works, Sub structure works of bridges, Drain
works & other parallel works from 0.50m to 3.50 m height. The
granite/trap/basalt crushed graded coarse aggregates and fine aggregates as
per relevant IS Codes machine mixed with super plasticisers, laid in layers, well
13 compacted using needle vibrators, providing weep holes wherever necesary,
including all lead & lifts, cost
of all materials of quality, confirming to the requirements of relevant IS codes,
labour, Usage charges of machinery, curing and all otherappurtenances required
to complete the work as per technical specifications. (The cost of steel
reinforcement & formwork to be paid separately) M-30
In Stem
In Abutment A1 1 8.200 1.50 4.800 59.040
In Pier P1 (Step 1) 1 8.200 1.90 1.750 27.265
In Pier P1 (Step 2) 1 8.200 1.60 3.500 45.920
for water cuts 4 1.050 2.10 5.250 23.153
In Pier P2 (Step 1) 1 8.200 1.90 2.450 38.171
In Pier P2 (Step 2) 1 8.200 1.60 3.500 45.920
for water cuts 4 1.050 2.10 5.950 26.240
In Pier P3 (Step 1) 1 8.200 2.10 2.150 37.023
In Pier P3 (Step 2) 1 8.200 1.60 4.500 59.040
for water cuts 4 1.050 2.10 6.650 29.327
In Pier P4 (Step 1) 1 8.200 2.10 2.900 49.938
In Pier P4 (Step 2) 1 8.200 1.60 4.500 59.040
for water cuts 4 1.050 2.10 7.400 32.634
In Pier P5 (Step 1) 1 8.200 2.10 3.600 61.992
In Pier P5 (Step 2) 1 8.200 1.60 4.500 59.040
for water cuts 4 1.050 2.10 8.100 35.721
In Pier P6 (Step 1) 1 8.200 2.30 3.250 61.295
In Pier P6 (Step 2) 1 8.200 1.60 5.500 72.160
for water cuts 4 1.050 2.10 8.750 38.588
6
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
In Pier P7 (Step 1) 1 8.200 2.30 3.900 73.554
In Pier P7 (Step 2) 1 8.200 1.60 5.500 72.160
for water cuts 4 1.050 2.10 9.400 41.454
In Pier P8 (Step 1) 1 8.200 2.30 4.400 82.984
In Pier P8 (Step 2) 1 8.200 1.60 5.500 72.160
for water cuts 4 1.050 2.10 9.900 43.659
In Pier P9 (Step 1) 1 8.200 2.30 4.650 87.699
In Pier P9 (Step 2) 1 8.200 1.60 5.500 72.160
for water cuts 4 1.050 2.10 10.150 44.762
In Pier P10 (Step 1) 1 8.200 2.10 2.750 47.355
In Pier P10 (Step 2) 1 8.200 1.60 4.500 59.040
for water cuts 4 1.050 2.10 7.250 31.973
In Abutment A2 1 8.200 1.30 3.200 34.112
Sub Total 1624.576 Cum
Supplying, fitting and fixing in position true to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH
14
specifications complete including all accessories as per drawing and Technical
Specifications.
In abutments 6 45 55 65 965250
In Piers 30 45 55 65 4826250
Grand Total 5791500 cc
7
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
Back filling behind abutment, wing wall and return wall complete including
15
compaction as per drawing and Technical Specification (A. Granular material)
Bebing abutment walls
2 8.200 Area= 60.484 991.934
(0.5 x b x h))
Below side stone pitching (v=1/3pir2h) 1 Volume= 1072.53 1072.531
Grand Total 2064.5 Cum
Supplying fitting & placing TMT bar reinforcement to super structure complete
16
as per Specifications
In Deck Slab 1 125.000 kg/cum 503.316 62.915
In Main , cross girders and kerb 1 250.000 kg/cum 449.163 112.291
Grand Total 175.2 t
Providing and laying in position Reinforced cement concrete for all Super
structures of building , Road works, Water works, Irrigation works & super
structure works of bridges upto 3.50 m height. The granite/trap/basalt crushed
graded coarse aggregates and fine aggregates as per relevant IS Codes
machine mixed with super plasticisers laid in layers, well compacted using
18 needle vibrators. The cost includes all lead & lifts, cost of all materials, quality
confirming to the requirements of relevant IS codes , labour, Usage charges of
machinery, curing and all other appurtenances required to complete the work as
per technical
specifications. (The cost of steel reinforcement, dowel bars & formwork
to be paid separately) M-30 Design Mix Using 20 mm nominal size graded
crushed coarse
In Deck Slab 11 18.600 8.200 0.300 503
In Main T-Girders 33 18.600 0.300 1.500 276
In Cross T-Girders 55 5.500 0.300 1.500 136
In Kerb 11 18.600 0.600 0.300 37
Grand Total 952 Cum
Providing and laying Pitching on Slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete as per
19
drawing, including cost of all materials, labour, loading, unloading, lead, lift,
transporting etc., complete.
380.031 Cum
8
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
Providing and laying of Filter media with granular materials/ stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with smaller size towards
20
the soil and bigger size towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and Technical Specification.
Behind abutment A1 2 8.200 0.60 4.800 47.23
Behind abutment A2 2 8.200 0.60 3.200 31.49
78.72 Cum
219 No/m
Drainage Spouts using 100 mm GI pipe complete as per drawing and Technical
22
specification
On deck slab 2 43 86
86 Nos
PCC M15 Grade leveling course below approach slab complete as per drawing
23
and Technical specification
Below approach slab 2 7.000 3.50 0.15 7.350
7.350 Cum
9
ITE MEASUREMENT
M DESCRIPTION OF WORK No. Qty unit
No. L B D
Provision of an Reinforced cement concrete Crash barrier at the bridge deck &
approaches to bridge structure, constructed withReinforced cement concrete
with TMT reinforcement conforming to MORT&H specificatios and as per details
given
in IRC-5 including dowel bars, 25 mm dia, 450 mm long at expansion joints filled
25 with pre-moulded asphalt filler board etc, keyed to the structure on which it is
built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the and
approved drawing and at locations directed by the Engineer, all as specified (A.
Crash Barrier for Bridges (Height 950 mm) as per details given IRC-5 (fig-1)
(Area 0.254 m2 for 1 m length) )
On Deck 2 215 429.200
429.200 m
33.400 m
Providing and filling joint sealing compound as per drawings and technical
27
specifications with coarse sand and 6 per cent bitumen by weight
In Approach Slab 4 3.50 14.000
14.000 Rm
Supplying and filling in plinth, foundations of Bridges with sand under floors,
29
including watering, ramming, consolidating and dressing complete.
Below Pile cap 12 5.40 12.90 0.20 167.184
167.184 Cum
10