You are on page 1of 180

BASEMENT Covered area 1 4907 sft 4907 sft 8.

00 ft ht Total column 25 nos


GF Covered area 1 4907 sft 4907 sft 10.00 ft ht Total int col = 7 nos
TYPICAL FLR Cov. area 5 4907 sft 24535 sft 10.00 ft ht T. corner col 5 nos
ROOF FLOOR(PITCH) 0 4907 sft 0 sft 10.00 ft ht T. long s. col 11 nos
times of flat roof area= 1.004988 4931.5 sft 34349 sft T. short s.col 2 nos

Soil data PL 3.00 ft design/est footing 16 '' dia 18 '' dia 20 '' dia
Soil capac 1.00 tsf -5.00 ft 0.95 tsf 35.00 ton 49.00 ton 59.00 ton
Soil capac 1.25 tsf -7.50 ft -6.50 ft 48.00 ton 63.00 ton 77.00 ton
Soil capac 1.50 tsf -10.00 ft 2.0 ft sand copm 60.00 ton 74.00 ton 89.00 ton
L1=101.00 ft B1=59.00 ft 5959.00 bay spacing 17.29 17.5 13.75 17.54X2 17.38
L2=79.50 ft B2=38.50 ft 3060.75 bay spacing 18.7 17.5 19.58 23.58
L=0.00 ft B=0.00 ft 0.00 gable end col s
1 10 5.75 deg gable end col s
roof extension all around= 0.00 ft 0.00 ft

length WT design/est pile


30 ft long -8.00 ft 20 '' dia
40 ft long Geffi 50 ft long
50 ft long 0.8 71.20 ton
DESIGN OF CIRCULAR PILE (WSD)
fc' fy Total load Dia of pile Embeded length Loose layer Stiff layer Lenth obtaine
3.00 ksi 40.00 ksi 110.00 kip 1.67 ft 50.00 ft 22.00 ft 28.00 ft 24.00 ft
x-Area Ic R of gyration rReduction fUltimate Axial load Dia. of Column Ag Pc
2.19 sft 0.38 ft^4 0.42 ft 0.3802 289.34 kip 20.04 in 315.26 sq in 236.44 kip
As 2.9386 sq in Dia. of Core (Dc) 14.0400 in
Single main bar As 0.4400 sq in Ac 154.7405 sq-in.
No of Bar (reqd) 6.6785 no ps 0.0350
No of Bar (pro) 8.0000 no tie as #3 0.1100 sq-in.
Ps (pro) 63.3600 kip g 8.0000 in
P(pro)=Pc+Ps 299.8029 kip ps 0.0039 <
P(pro)/P(actual) 1.0362 sq-in.
% of steel 1.12 % CC 3 in
spacing of pile (smaller in loose soil, -nsf significant )
function of piles mf mf dia s
point bearing piles in hard stratum 2 2.5 1.67 = 3.3ft
point bearing piles on hard bedrock 2 2 1.67 = 3.3ft
friction piles 3 5 1.67 = 5.0ft

Depth(ft) L2-L1 SPT value Correcte Average SPT Soil type qu=2Cd tsf Nc

d SPT
0 0 0 0
5 5 12 12 6 cohesive 0.75 9
10 5 18 16.5 15 cohesive 2 9
15 5 7 7 12.5 cohesive 1.7 9
20 5 6 6 6.5 cohesive 0.63 9
25 5 9 9 7.5 cohesive 1 9
30 5 13 13 11 cohesionless
35 5 15 15 14 cohesionless
40 5 16 15.5 15.5 cohesionless
45 5 18 16.5 17 cohesionless
50 5 21 18 19.5 cohesionless
55 5
60 5

Dia of Pile 20 in.


Skin friction End bearing Depth in ft Skin friction End bearing Pile Value Pile Value Pile Value
fsa(T/sq-ft) fsa(T/sq-ft) ksf ksf Ps, kip Pe, kip Ps + Pe, kip

0.000 0.000 5.000 0.000 0.000 0.000 0.000 0.000


0.010 0.000 10.000 0.020 0.000 0.000 0.000 0.000
0.090 0.000 15.000 0.180 0.000 0.523 0.000 0.523
0.110 5.290 20.000 0.220 10.580 4.710 23.070 28.304
0.070 3.450 25.000 0.140 6.900 5.757 15.046 26.036
0.080 4.100 30.000 0.160 8.200 3.663 17.881 32.534
0.190 9.220 35.000 0.380 18.440 4.187 40.209 59.049
0.180 8.620 40.000 0.360 17.240 9.943 37.593 66.376
0.130 13.500 45.000 0.260 27.000 9.420 58.875 97.078
0.090 19.200 50.000 0.180 38.400 6.803 83.733 128.740
0.110 21.600 55.000 0.220 43.200 4.710 94.200 143.917
0.110 22.800 60.000 0.220 45.600 5.757 99.433 154.907
65.000
70.000
75.000

BH NO PILE SIZE F.S. X-AREA


1 1.50 ft 2.5 1.77 sft
Ultimate skin friction
Depth in m Depth in ft N CORR, N SKIN AREA .02 Nc SA / FS 4 Nc Dp / FS G+H
Qs Qp
ft2 cumu kips kips kips
1.5 5 4 4 23.57 0.75 9.60 10.35
3 10 4 4 47.14 1.51 9.60 11.11
4.5 15 8 8 70.71 4.53 19.20 23.73
6 20 13 13 94.29 9.81 31.20 41.01
7.5 25 19 17 117.86 16.03 40.80 56.83
9 30 50 32.5 141.43 36.77 78.00 114.77
10.5 35 50 32.5 165.00 42.90 78.00 120.90
12 40 50 32.5 188.57 49.03 78.00 127.03
13.5 45 50 32.5 212.14 55.16 78.00 133.16
15 50 50 32.5 235.71 61.29 78.00 139.29
16.5 55 259.29
18 60 282.86
19.5 65 306.42857142857
778.17

consistancy v soft soft medium stiff v stiff hard


concrete
timber
N 0 2 4 8 16 32
soft
qu (t/sft) 0 0.25 0.5 1 2 4 medium
stiff
unit weight 100 110 120 130
120 130 140 +
pile :
compactness v loose loose medium dense v dense Qp = Ap ( c Nc' + q' Nq' )
relative density Dd
relative density Dd
0% 15 % 35 % 65 % 85 % 100 % Qs = ∑p ∆L f

N 0 4 10 30 50 favg = 40
φ 28 30 36 41
moist ∂ < 100 95-125 110-130 110-140 >130 favg = 20 Nc
submerged ∂ < 100 95-125 110-130 110-140 >130

CLAY FILL OVER GRANULAR SOIL : GRANULAR SOIL


ultimate skin friction ultimate skin friction
moist U.W. = 16.00 KN/M3 moist U.W.
saturated U. W. = 18.50 KN/M3 saturated U.
L
φ clay 36.00 degree φ clay
Eff u.w. of fill ∂ 17.20 KN/M3 Eff u.w. of fill ∂
soil-pile friction angle € = .5-.7φ 0.7 25.20 soil-pile friction angle € = .5-.7
height of the clay fill Hf 3.00 m height of the sand fill Hf
pile dia 0.50 m pile dia
earth pressure coeff k' =1-sin φ 0.41 earth pressure coeff k' =1-sin φ
p= dia * 22/7 1.57 p= dia * 22/7
THE FILL is ABOVE THE WATER TABLE ∂effective =∂moist THE WATER TABLE on top of the clay
242.37889
1

Q = p k' ∂' H^2 tan € /2 Q

= 23.59 kn

= 5.30 kips
* IF THE SOIL & THE FILL ARE ABOVE THE WATER TABLE ∂effective =∂moist

PILE
Qp = Ap * qp = Ap (c Nc' + q' Nq' + ∂ D N∂' ) ≈ Ap (c Nc' + q' Nq' ) ≈ Ap q' N

1. Meyerhof method:
CON. PILE LENGTH , L = 50 FT ULTIMATE POINT LOAD ?
SOIL TYPE SANDY = 0 =c
X - SEC 16 = 16 INCH Qp = 537.78 kips
UNIT WT SOIL = 110 PCF Qp =Ap ql= 56.42 kips
for φ =30 ,Nq' = 55
φ = 30 DEG design ult Qp= 56.42 kips
2. Vesics method :
Lc = 50 ft ULTIMATE POINT LOAD ?
for φ =30 & Lc=50 , Nq' = 36 Qp = 234.72 kips

3. Janbu's method :
n' 90 deg ULTIMATE POINT LOAD ?
for φ =30 & n'=90 , Nq' = 19 Qp = 185.78 kips

COYLE METHOD :

FS = 4 Qp= 244.44
L/D = 37.5 Qs= 65.26
for φ =30 & L/D=37.5 , Nq' = 25 FIG 9.16 Qu=Qp+Qs= 309.71 kips
K = 0.2 FIG 9.19 Qa =Qp+Qs= 77.43 kips
s = c+ ∂' tan φ COHES
concrete
s= qu / 2 timber

Cc = .009 ( LL - 10 ) soft
medium
Cc = .30 (eo - .27 ) stiff
consistancy
S = Cc/(1+eo) * H Log((po + ∆p)/po)
N
φ = 25 + .15Dd
qu (t/sft)
φ = 30 + .15Dd
unit weight
N = 15 + .5*(N'-15)
GRANU
N = N' ( .77 LOG10 20/p' ) p' => .25 tsf compactness
relative
pile : density Dd
Qp = Ap ( c Nc' + q' Nq' )
N
Qs = ∑p ∆L f φ
moist ∂
f avg (psf) = 40 N‾c for high displacement driven pile submerged ∂

f avg (psf) = 20 N‾c for low displacement driven pile


COLMN NO LOAD Qa Qa DEPTH M DEPTH FT NO OF NO OF
(TON) (kips) PILES PILES
A1 356.0 61.8 123.54 19.5 64.0 2.9 3
A2 511.0 61.8 123.54 19.5 64.0 4.1 4
A3 713.0 73.2 146.44 19.5 64.0 4.9 5
A4 760.0 73.2 146.44 19.5 64.0 5.2 5
A5 765.0 73.2 146.44 19.5 64.0 5.2 5
A6 761.0 73.2 146.44 19.5 64.0 5.2 5
A7 918.0 73.2 146.44 19.5 64.0 6.3 6
A8 740.0 73.2 146.44 19.5 64.0 5.1 5
A9 753.0 73.2 146.44 19.5 64.0 5.1 5
A10 750.0 73.2 146.44 19.5 64.0 5.1 5
A11 755.0 73.2 146.44 19.5 64.0 5.2 5
A12 713.0 73.2 146.44 19.5 64.0 4.9 5
A13 349.0 73.2 146.44 19.5 64.0 2.4 2
C13 330.0 73.2 146.44 19.5 64.0 2.3 2
E1 327.0 61.8 123.54 19.5 64.0 2.6 3
E2 487.0 61.8 123.54 19.5 64.0 3.9 4
E3 1377.0 81.6 163.126 21 68.9 8.4 8
E4 1550.0 96.3 192.516 21 68.9 8.1 8
E5 1531.0 96.3 192.516 21 68.9 8.0 8
E6 1513.0 96.3 192.516 21 68.9 7.9 8
E7 1796.0 87.5 175.06 21 68.9 10.3 10
E8 1505.0 87.5 175.06 21 68.9 8.6 9
E9 1526.0 83.8 167.68 21 68.9 9.1 9
E10 1515.0 83.8 167.68 21 68.9 9.0 9
E11 1528.0 83.8 167.68 21 68.9 9.1 9
E12 1480.0 83.8 167.68 21 68.9 8.8 9
E13 675.0 83.8 167.68 21 68.9 4.0 4
I1 569.0 95.5 191 19.5 64.0 3.0 3
I2 949.0 95.5 191 19.5 64.0 5.0 5
I3 1037.0 91.2 182.3 19.5 64.0 5.7 6
I4 1048.0 101.2 202.3 19.5 64.0 5.2 6
I5 1061.0 68.8 137.692 21 68.9 7.7 8
I6 1056.0 68.8 137.692 21 68.9 7.7 8
I7 1282.0 68.8 137.692 21 68.9 9.3 9
I8 1086.0 68.8 137.692 21 68.9 7.9 8
I9 1104.0 68.4 136.722 21 68.9 8.1 8
I10 1096.0 68.4 136.722 21 68.9 8.0 8
I11 1100.0 68.4 136.722 21 68.9 8.0 8
I12 1100.0 68.4 136.722 21 68.9 8.0 8
I13 741.0 68.4 136.722 21 68.9 5.4 6
K1 451.0 84.5 169 19.5 64.0 2.7 3
K2 581.0 84.5 169 19.5 64.0 3.4 3
K3 570.0 93.4 186.7 19.5 64.0 3.1 3
K4 625.0 100.9 201.8 19.5 64.0 3.1 3
K5 511.0 100.9 201.8 19.5 64.0 2.5 2
L1 314.0 93.1 186.1 19.5 64.0 1.7 2
L2 481.0 93.1 186.1 19.5 64.0 2.6 3
L3 485.0 93.4 186.7 19.5 64.0 2.6 3
L4 384.0 93.4 186.7 19.5 64.0 2.1 2
C1 368.0 61.8 123.54 19.5 64.0 3.0 3
C2 500.0 61.8 123.54 19.5 64.0 4.0 4
D1 195.0 61.8 123.54 19.5 64.0 1.6 2
D2 261.0 61.8 123.54 19.5 64.0 2.1 2
D3 214.0 61.8 123.54 19.5 64.0 1.7 2
F1 250.0 61.8 123.54 19.5 64.0 2.0 2
F2 493.0 61.8 123.54 19.5 64.0 4.0 4
G1 360.0 61.8 123.54 19.5 64.0 2.9 3
LIFT 4
301

PILE CAP DESIGN for 5 piles


Column Load No of Piles Load per Pile Column L
fs f'c R j
24000 3000 0.204 0.855 810 5 169.99 15
Let d P Vf=1.1sqrt(f'c) Vp=2sqrt(f' bo b Pile bo=pi(pile V
c) dia+d)
38 849.94 60.25 109.54 222 110.04 176.00 84.9942228
Check for d Column Pile Flexure From moment= Asl Asb Pile No for Ml
punching=P/(V punching=P/( Shear=V/(b
pb0) Vpbopile) Vf) sqrt(M/Rb)
OK 34.94988968 8.81690399 12.81993 18.582397587113 8.6328388758079 9.940844766 2
Area Area for Ass
Size(mm) Area(cm)2 Area(in)2 forAsl @ @
20 3.1416 0.48691878 0.941422 1.0840615884495 6.2065959828771 5.389938617
22 3.801336 0.58917173 0.941422 1.0840615884495 7.5099811392813 6.521825726
25 4.90875 0.7608106 0.941422 1.0840615884495 9.6978062232455 8.421779089
28 6.157536 0.95436082 0.941422 1.0840615884495 12.164928126439 10.56427969
32 8.042496 1.24651209 0.941422 1.0840615884495 15.888885716165 13.79824286

9.17 ft
" c/c

6.2

d (in) =
@

20
D

15

20
"c/c

5.39
D @

20
Effetive length
36.00 ft
Ps
52.89 kip

0.0350

s
4.2ft
3.3ft
8.4ft

Ab sft Qult end deph/pile a As sft Qult Q


bearing friction allowable
ton dia ton ton

1.77 5.97 3.33 0.65 23.57 5.75 3.90 1.125


1.77 15.91 6.67 0.65 23.57 15.32 10.41 3
1.77 13.52 10.00 0.65 23.57 13.02 8.85 2.55
1.77 5.01 13.33 0.65 23.57 4.83 3.28 0.945
1.77 7.96 16.67 0.65 23.57 7.66 5.21 1.5
31.65

Ps + Pe, kip

s = c+ ∂' tan φ
s= qu / 2
Cc = .009 ( LL - 10 )

Cc = .30 (eo - .27 )


7.54
7.54 S = Cc/(1+eo) * H Log((po + ∆p)/po)
15.09
24.51 φ = 25 + .15Dd
32.06
61.29 φ = 30 + .15Dd
61.29
61.29 N = 15 + .5*(N'-15)
61.29
61.29 N = N' ( .77 LOG10 20/p' ) p' => .25 tsf

clay

cohesive strength adhesion to pile


psf psf psf psf
0 750 0 700
750 1500 700 900
1500 3000 900 1300

Qp = Ap ( c Nc' + q' Nq' )


Qs = ∑p ∆L f

40 ñ psf

favg = 20 Nc psf

GRANULAR SOIL FILL OVER CLAY :


ultimate skin friction
= 16 KN/M3
= clay 17.2 KN/M3
20 m
34.00 degree
Eff u.w. of fill ∂ 16.50 KN/M3
soil-pile friction angle € = .5-.7φ 0.6 20.40
height of the sand fill Hf 2.00 m
0.31 m
earth pressure coeff k' =1-sin φ 0.44
p= dia * 22/7 0.96
THE WATER TABLE on top of the clay layer
/L1 -L1 = 8.930988
L1^2 8.93099 L1 -242.38 = 0
L1 = 11.73079 M

= p k' ∂' H tan € L1 + L1^2 p k' ∂' tan € /2

= 140.74 kn

= 31.64 kips
≈ Ap (c Nc' + q' Nq' ) ≈ Ap q' Nq'

ULTIMATE FRICTIONAL RESISTANCE ?

K = 1.3
DELTA 0.8 φ = 24
L 15 D = 20 ft
at 0.00ft f = 0
at 20.00ft gama L' = 2.2 kip/ft2
at 20.00ft f = 1.27 kip/ft2
Qs = 271.4936 kips
ALLOWABLE LOAD CARRYING CAPACITY ?
FS = 4
Qp ult avg. = 158.9719 kips
Qallow = Qp+Qs = 107.6164 kips

Meyerhof : based on avg. corrected N for granular soil


coeff. avg cor N dia / width LENGTH
Qp = 0.80 9 16 50 40.00 kips
Qp = 8.00 9 16 50 128.00 kips
Qs = 0.04 9 16 50 96 kips
Qs = 0.02 9 16 50 48 kips
88.00 kips
saturated clay φ= 0 undrained condition
Qp = N'c cu Ap = 9 cu Ap =

COHESIVE clay

cohesive strength adhesion to pile


psf psf psf psf
0 750 0 700
750 1500 700 900
1500 3000 900 1300
v soft soft medium stiff v stiff hard

0 2 4 8 16 32

0 0.25 0.5 1 2 4

100 110 120 130


120 130 140 +
GRANULAR SOIL
v loose loose medium dense v dense

0% 15 % 35 % 65 % 85 % 100 %

0 4 10 30 50
28 30 36 41
< 100 95-125 110-130 110-140 >130
< 100 95-125 110-130 110-140 >130
LOAD PER BORE
PILE HOLE
119 11 1
128 11 2
143 11 3
152 12 4
153 12 5
152 12 6
153 12 7&8
148 12 9
151 5 10
150 5 11
151 5 12
143 5 13
175 5 14
165 5 17
109 11 21
122 11 22
172 11 23
194 12 24
191 12 25
189 12 26
180 12 27&28
167 12 29
170 5 30
168 5 31
170 5 32
164 5 33
169 5 34
190 O-4 38
190 O-4 39
173 O-8 40
175 O-3 41
133 13 42
132 13 43
142 13 44&45
136 13 46
138 14 47
137 14 48
138 14 49
138 14 50
124 14 51
150 O-5 52
194 O-5 53
190 O-7 54
208 O-2 55
256 O-2 56
157 O-6 57
160 O-6 58
162 O-7 59
192 O-7 60
123 11 15
125 11 16
98 11 19
131 11 20
107 11 18
125 11 35
123 11 36
120 11 37

Column B Pile Cap Pile dia Pile cap


Width(l) Breadth(s)
20 9.17 18 9.17
Ml Ms
dy dx
1.65 1.9 560.96 645.96
Pile No for Ms Use steel

size
2 20

38
ft
9.17
DESIGN OF SPREAD FOOTING-ULTIMATE, RECTANGULAR

DATA : Solution :
Fc' ksi 2.50 ¢Vc PS 170.0 psi
Fy ksi 60.00 ¢Vc BS 85.0 psi
Qa ksf 3.00 Pressure at 5ft depth 750.00 psf
Column size-long inch 18.00 Eff bearing pressure 2,250.00 psf
Column size-short inch 18.00 Required footing area 176.89 ft2
As # 0.31 long side 13.30 ft
DL kips 250.00 kips short side 13.30 ft
LL kips 148.00 kips Let long side of sq. footing 13.50 ft
BASE ,below 6.00 ft Let short side of sq. footing 13.50 ft
avg. unit wt of fill soil/conc 125.00 pcf A-provided 182.25 ft2
Ratio of sides=l/s 1.00 Upward pressure by f.c.l. 3.30 ksf
punching shear at d/2 beam shear at d
let d 27.0 long short
bo 180.0
V - kips 555.2 167.1 167.1
Vc -kips 826.2 371.8 371.8
ok ok ok
BENDING moment at col face long short
Mu 9,625.6 Kip" 9,625.6 Kip"
LET a 1.11 inch 1.11 inch
As = M/(PHI *Fy(d-a/2)) 6.74 in² 6.74 in²
a 1.17 1.17
As total 6.75 6.75
As(min) 10.94 in² 10.94 in²
As(min)=200/fy 14.58 in² NLT 14.58 in² NLT

Let use for long bar # 9 14.6 nos @


# 8 18.5 nos @
# 7 24.3 nos @
# 6 33.1 nos @
# 5 47.0 nos @

# 4 72.9 nos @

Reinf in band width "B"=

Let use for 9 14.6 nos


8 18.5 nos
7 24.3 nos
6 33.1 nos
5 47.0 nos
4 72.9 nos
check dev leng if not ok provide pedestal or
2-smaller size dowel bars for each col bar
From chart A11 ld 37.92 40.00
actual length 69.00

transfer of for # 5 7.44


Ld for comp do # 6 10.56
# 7 14.4
# 8 24
d 27.00

lap splice(comp)for dowels


for #8 .0005× # 8 25.00
total dowel len 41.00
min dowel steel 1.62

Bearing stress partially loa psi 1856.79


max permissible psi 1781.25

clear cover 3.00


Total thickness of footing 31.50

Actual length f 25.00 in


Ld for bottom tension bars
#3 Ldb = .04 3.2 8.2 in
#4 5.8 11.0 in
#5 9.1 13.7 in
#6 12.9 16.4 in
#7 17.5 19.2 in
Ldb > .03 *db*fy/sqrt(fc')

Actual length f 9.00 in


Ld for compresion dowel bars
#3 Ldb = .02 5.5 4.5 in
#4 7.3 6.0 in
#5 9.1 7.5 in
#6 11.0 9.0 in
#7 12.8 10.5 in
Ldb > .0003 *db*fy

Modification fa(fy / 60000) As-req/As-pro


tension 0.67 c42/

For hooked bar = 1200db / sqrt(fc')


Shallow foundation

q net (all) = q all - ∂ Df


Ncor = at 2B or at 3BFrom bott of found for design
Meyerhof's theory for 1" of estimated max settlement, .75" diff settlement

q net (all) = 1.5 * Ncor / 4 ksf B<=4'

q net (all) = 1.5 * (Ncor / 6) * ((B+ ksf B>4'

floor(2.56,.25 2.5 Bowles 1977 :


q net (all) = Ncor / 2.5 * Fd St ksf B<=4'

q net (all) = (Ncor / 4) * ((B+1)/B) ksf B>4'

Fd = 1 + .33 D/ TH FACTOR <= 1.33


St = TOLERABLE SETTLEMENT IN INCH

Mat foundation : for a max raft settlement 2", diff sett would be .75", Fd=1

q net (all) = .5 * Ncor ksf

q net (all) = .25 Ncor [ 1+ .33 Df / ksf


<= .33 Ncor St

q net = Q/A - ∂ Df

N = 15 + .5*(N'-15)
11.1 " c/c
8.8 " c/c N = N' ( .77 LOG10 20/p' ) p' => .25 tsf
6.7 " c/c
4.9 " c/c
3.4 " c/c

2.2 " c/c

As(S.D.) * 2/(b+1) REMAINING


#REF! 14.58 0.00
@ 11.1 " c/c 12.5 #DIV/0!
@ 8.8 " c/c 11.1 #DIV/0!
@ 6.7 " c/c 9.7 #DIV/0!
@ 4.9 " c/c 8.3 #DIV/0!
@ 3.4 " c/c 6.9 #DIV/0!
@ 2.2 " c/c 5.6 #DIV/0!
OK

11.25
13.5
15.75
18
OK

"

in² na

NOT OK

inch
inch
ff settlement

be .75", Fd=1
A. COST OF CONCRETE FOR 100 CFT : 1 1.5 3 COST OF MATERIALS 165 /ft3 5810 /m3
A-1 COST OF MATERIALS COST OF LABOUR & EQUIPMENT 16 /ft3 547 /m3
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.) AMOUNT (Tk.) without 20.0 % markup 180 /ft3 6357 m3
a) stone CHIPS I/C BREAKING 82 CFT 85 6970 with 20.0 % markup 216 /ft3 7629 m3
b) 100 % sylhet sand 42 CFT 27 1134 1 IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB .

c)CEMENT 22 BAG 380 8360 2 IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL

TOTAL MATERIAL COST : 16464 3 RCC IN TIE BEAMS & LINTEL


A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) : 4 RCC IN TEE, ELL, RECTANGULAR BEAMS
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.) AMOUNT (Tk.) 5 RCC IN FLOOR/ROOF SLAB
d) H. MASON 1 NOS. 300 300 6 RCC IN SUNSHED, CORNICE, RAILING, DROPWALL
e) MASON 4 NOS. 250 1000 7 RCC IN STAIR CASE SLAB & STEPS

f) SKILLED LABOUR 6 nos. 200 1200 1 IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB .

g) LABOUR 34 nos. 150 5100 2 IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL

h) MIXTURE MACHINE 1 DAY 800 800 3 RCC IN TIE BEAMS & LINTEL
I) VIBRATOR 1 DAY 400 400 4 RCC IN TEE, ELL, RECTANGULAR BEAMS
j) FULE & LUBRICANTS 1 DAY 500 500 5 RCC IN FLOOR/ROOF SLAB
FOR 600CFT : 9300 6 RCC IN SUNSHED, CORNICE, RAILING, DROPWALL
SO FOR 100CFT COST IS Total 1550 7 RCC IN STAIR CASE SLAB & STEPS

1 COST ANALYSIS FOR 100 CFT RCC (1:1.5:3) IN FOOTINGS OF COLUMN, STEEL SHUTTER IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB AT
RAFT & FLOOR SLAB AT PLINTH LEVEL WITH STONE CHIPS. COST OF SHUTTERING( for 36 cft )
Sl.No Description of Works Quantity Unit
CONCRETE 16464 1 PLATE 83.88 LBS
LABOUR,EQIP. 1550 2 ANGLE 157.39 LBS
SHUTTERING 2367.52 3 FI BAR 47.6 LBS
TOTAL 20382 4 FRAME 24.67 SFT
Contractors profit 0.1 2038.152 5 NUTS BOLTS 1 KG
Over head expences 0.025 509.5381
VAT & IT 0.075 1528.614 TAKING USE FOR 16 TIMES
COST FOR 100 CFT GRAND TOTAL 24458 6 LABOUR FOR SHUTTERING 24.67 SFT
SO COST PER CUM = TK. 8631 SO FOR 100CFT

2 RCC IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL STEEL SHUTTER FOR RCC IN PADESTALS, COLUMN,COLUMN CAPITA
A. CONCRETE 16464 COST ANALYSIS OF SHUTTERING (FOR
B. LAB/EQIP 1550 SL. NO.DESCRIPTION OF WORKS QTY UNIT
C. SHUTTER 15216 1 PLATE 158.68 LBS
33230 2 ANGLE 255.2 LBS
Contractors profit 0.1 3322.966 3 FI BAR 68 LBS
Over head expences 0.025 830.7414 4 FRAME 46.67 SFT
VAT & IT 0.075 2492.224 5 NUTS BOLTS 1.5 KG
COST FOR 100 CFT GRAND TOTAL 39876
SO COST PER CUM = TK. 14072 TAKING USE FOR 16 TIMES
6 PROPS 24 RFT
TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTTERING 40 SFT
FOR 10 CFT
SO FOR 100 CFT TOTAL

3 RCC IN TIE BEAMS & LINTEL STEEL SHUTTER RCC IN TIE BEAMS
COST ANALYSIS OF SHUTTERINGSO( FOR
A. CONCRETE 16464
B. LAB/EQIP 1550 SL. NO.DESCRIPTION OF WORKS QTY UNIT
C SHUTTER 8698.52 1 PLATE 65.86 LBS
26713 2 ANGLE 92.49 LBS
Contractors profit 0.1 2671.252 3 FI BAR 7.96 LBS
Over head expences 0.025 667.8131 4 FRAME 19.37 SFT
VAT & IT 0.075 2003.439 5 NUTS BOLTS 1 KG
GRAND TOTAL FOR 100 CFT 32055
TAKING USE FOR 16 TIMES
SO COST PER CUM = TK. 11312 6 PROPS 7 RFT
TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTT 19.37 SFT
SO FOR 6.94 CFT
SO FOR 100 CFT

4 RCC IN TEE, ELL, RECTANGULAR BEAMS STEEL SHUTTER RCC IN TEE, ELL, RECTANG
COST ANALYSIS OF SHUTTERING( FOR
A. CONCRETE 16464 SL. NO.DESCRIPTION OF WORKS QTY UNIT
B. LAB/EQIP 1550 1 PLATE 294.44 LBS
C SHUTTER 9401.3958 2 ANGLE 425.32 LBS
27415.396 3 FI BAR 147.22 LBS
4 FRAME 86.6 SFT
5 NUTS BOLTS 4 KG
Contractors profit 0.1 2741.53958
Over head expences 0.025 685.384896 TAKING USE FOR 16 TIMES
VAT & IT 0.075 2056.15469 6 PROPS 14 RFT
COST FOR 100 CFT GRAND TOTAL 32898.475 TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTT 86.6 SFT
SO COST PER CUM = TK. 11610 SO FOR 30 CFT
SO FOR 100 CFT

5 RCC IN FLOOR/ROOF SLAB STEEL SHUTTER FOR RCC IN FLOOR/ROOF SL


COST ANALYSIS OF SHUTTERING (FOR 160 CFT )
A. CONCRETE 16464 SL. NO.DESCRIPTION OF WORKS QTY UNIT
B. LAB/EQIP 1550 1 PLATE 1088 LBS
C SHUTTER 8273.0859 2 ANGLE 1642.68 LBS
26287.1 3 FI BAR 0 LBS
FRAME 320 SFT
5 NUTS BOLTS 12 KG
Contractors profit 10% 2628.70859
Over head expences 2.50% 657.177148 TAKING USE FOR 16 TIMES
VAT & IT 7.50% 1971.53145 6 PROPS
COST FOR 100 CFT GRAND TOTAL 31544.503 a) cost of pipes & accasories 63 NOS
b) ms/gi cross pipe or I beam 144 RFT
SO COST PER CUM = TK. 11132
TAKING USE FOR 30 TIMES

7 LABOUR FOR SHUTT 320 SFT


FOR 160 CFT
SO FOR 100 CFT

6 RCC IN SUNSHED, CORNICE, RAILING, DROPWALL COST ANALYSIS OF SHUTTERING(FOR

A. CONCRETE 16464 SL. NO.DESCRIPTION OF WORKS QTY UNIT


B. LAB/EQIP 1550 1 PLATE 204 LBS
C SHUTTER 12879.01 2 ANGLE 267.96 LBS
30893.01 3 FI BAR 44.2 LBS
4 FRAME 60 SFT
5 NUTS BOLTS 0 KG
Contractors profit 0.1 3089.301
Over head expences 0.025 772.32525 TAKING USE FOR 16 TIMES
VAT & IT 0.075 2316.97575
COST FOR 100 CFT GRAND TOTAL 37071.612
7 LABOUR FOR SHUTT 60 SFT
SO COST PER CUM = TK. 13083 FOR 7.5 CFT
SO FOR 100 CFT

7 RCC IN STAIR CASE SLAB & STEPS COST ANALYSIS OF SHUTTERING(FOR 1


SL. NO.DESCRIPTION OF WORKS QTY UNIT
1 PLATE 122.4 LBS
A. CONCRETE 16464 2 ANGLE 140.94 LBS
B. LAB/EQIP 1550 3 FI BAR 0 LBS
C SHUTTER 6072.6367 4 FRAME 36 SFT
24086.637 5 NUTS BOLTS 2.5 KG

TAKING USE FOR 16 TIMES


Contractors profit 0.1 2408.66367 6 PROPS 14 RFT
Over head expences 0.025 602.165919 TAKING USE FOR 30 TIMES
VAT & IT 0.075 1806.49776
COST FOR 100 CFT GRAND TOTAL 28903.964
7 LABOUR FOR SHUTT 36 SFT
SO COST PER CUM = TK. 10200 FOR 17.49 CFT
SO FOR 100 CFT
stone CHIPS I/C BREAKING sylhet sand 100 % stone CHIPS I/C BREAKING
1 1.5 3 1
steel shutter w
total cost with markup total cost without markup total cost with mark
Tk 8631 /m3 Tk. 245 /ft3 Tk 6905 /m3 Tk. 196 /ft3 Tk 8256 /m3
Tk 14072 /m3 Tk. 399 /ft3 Tk 11258 /m3 Tk. 319 /ft3 Tk 7775 /m3
Tk 11312 /m3 Tk. 321 /ft3 Tk 9050 /m3 Tk. 256 /ft3 Tk 9775 /m3
Tk 11610 /m3 Tk. 329 /ft3 Tk 9288 /m3 Tk. 263 /ft3 Tk 11389 /m3
Tk 11132 /m3 Tk. 315 /ft3 Tk 8906 /m3 Tk. 252 /ft3 Tk 10221 /m3
Tk 13083 /m3 Tk. 371 /ft3 Tk 10466 /m3 Tk. 297 /ft3 Tk 10347 /m3
Tk 10200 /m3 Tk. 289 /ft3 Tk 8160 /m3 Tk. 231 /ft3 Tk 10326 /m3
steel shutter cost with markup steel shutter cost without markup wooden shutter cost with m

Tk 1003 /m3 Tk. 28 /ft3 Tk 802 /m3 Tk. 23 /ft3 Tk 628 /m3

Tk 6444 /m3 Tk. 183 /ft3 Tk 5155 /m3 Tk. 146 /ft3 Tk 147 /m3
Tk 3684 /m3 Tk. 104 /ft3 Tk 2947 /m3 Tk. 84 /ft3 Tk 2146 /m3
Tk 3981 /m3 Tk. 113 /ft3 Tk 3185 /m3 Tk. 90 /ft3 Tk 3761 /m3
Tk 3503 /m3 Tk. 99 /ft3 Tk 2803 /m3 Tk. 79 /ft3 Tk 2593 /m3
Tk 5454 /m3 Tk. 155 /ft3 Tk 4363 /m3 Tk. 124 /ft3 Tk 2718 /m3
Tk 2572 /m3 Tk. 73 /ft3 Tk 2057 /m3 Tk. 58 /ft3 Tk 2697 /m3

OF COLUMN,RAFT & FLOOR SLAB AT PLINTH LEVEL Analysis of wooden Shuttring in individual and continuous footings of column Considering 100 cft.
Cost of shuttering
Rate Amount ( Tk.) Considering Base 6'x6'x14" to 10"
25 2097 Volume of concrete: 6'-0" x 6' x 1'-0" (approx.) =
25 3934.75 i) Cost of shuttring wood:
25 1190 Planks required:
65 1603.55 add 15 %
75 75
8900.3
556.26875 ii) Labour for shuttring in /c making,placing & removing:
12 296.04
852.30875 iii) Supplying, fitting and fixing, rupban /equivalent sheet & heassian tape (where necessary) & remov
2367.52431 same for making shutter water-tight.

ADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL Cost for 100.00


NALYSIS OF SHUTTERING (FOR 10 CFT)
RATE (Tk.) AMOUNT (Tk.) Analysis of wooden Shuttring R.C.C. work in raft/ mat . Considering 100 cft. of work
25 3967 Cost of shuttering
25 6380 Considering A MAT OF
25 1700 Volume of concrete: (approx.) =
65 3033.55 i) Cost of shuttring wood:
75 112.5 120.00 ' 4.00 '
Total 15193.05 add 15% for batten, supports & wastage =
Total 949.565625
115 2760
Total 92 ii) Labour for shuttring in /c making,placing & removing:
12 480
Total 1521.56563 iii) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape(where necessary)
15215.66 for making shutter water-tight sufficiently

Cost for 100.00


UTTER RCC IN TIE BEAMS & LINTEL
LYSIS OF SHUTTERINGSO( FOR 6.94 CFT) Analysis of wooden Shuttring R.C.C. work in foundation beam .Considering 100 cft. of wor
Cost of shuttering
RATE (Tk.) AMOUNT (Tk.) Considering

25 1646.5 Volume of concrete: (approx.) =


25 2312.25 i) Cost of shuttring wood:
25 199 Planks & batten required:
65 1259.05 20.00 ' 3.00 '
75 75 24.00 ' 0.25 '
Total 5491.8 7.00 ' 0.25 '
Total 343.2375 add 15% for batten, supports & wastage =
120 840
Total 28
12 232.44 ii) Labour for shuttring in /c making,
SO FOR 6.94 CFT TOTAL 603.6775 placing & removing:
SO FOR 100 CFT TOTAL 8698.523 iii) Supplying, fitting and fixing, rupban or
equivalent sheet & heassian tape
(where necessary)
for making shutter water-tight sufficiently
ER RCC IN TEE, ELL, RECTANGULAR BEAMS
NALYSIS OF SHUTTERING( FOR 30 CFT) iv) Nails and wires
RATE (Tk.) AMOUNT (Tk.)
25 7361 Cost for 100.00
25 10633
25 3680.5 Analysis of wooden Shuttring R.C.C. work IN Padestals, column capitals, lift walls and wall
65 5629 Cost of shuttering
75 300 Assuming column size
27603.5 Volume of concrete: (approx.) =
Total 1725.21875 i) Cost of shuttring wood:
120 1680 Planks & batten required: 2
Total 56 2
12 1039.2 4
SO FOR 30 CFT TOTAL 2820.41875
SO FOR 100 CFT TOTAL 9401.396 add 5.00 % wastage
@
Using 6
ii) Bamboo Props in / c inclined support
4.00
Using 6 times
R RCC IN FLOOR/ROOF SLAB iii) Labour for shuttring in /c making,placing & removing:
40.00 sft
RATE (Tk.) AMOUNT (Tk.) iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
25 27200 (where necessary) for making shutter water-tight sufficiently
25 41067 40.00 sft
25 0 v) Nails and wires
65 20800
75 900 Cost for 100.00 cft of co
89967
Total 5622.9375
Analysis of wooden Shuttring R.C.C. work in
1500 94500 Cost of shuttering
130 18720 Assuming beams 10
113220 Volume of concrete:
Total 3774 i) Cost of shuttring wood: 2
Planks & batten required: 9
12 3840
FOR 160 CFT TOTAL 13236.94 add 10.00 % for door / window ope
SO FOR 100 CFT TOTAL 8273.086 Tk.
Using 6.00 times @
NALYSIS OF SHUTTERING(FOR 7.5 CFT) ii) Bamboo Props in / c inclined support

RATE (Tk.) AMOUNT (Tk.) iii) Labour for shuttring in /c making,placing & removing:
25 5100 2.00 10.00
25 6699 1.00 3.00
25 1105
65 3900
75 0 iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
16804 (where necessary) for making shutter water-tight sufficiently
Total 1050.25
v) Nails and wires

12 720
FOR 7.5 CFT TOTAL 1770.25 Cost for 100.00 cft of co
SO FOR 100 CFT TOTAL 23603.33

ALYSIS OF SHUTTERING(FOR 17.49 CFT) Analysis of wooden Shuttring R.C.C. work i


RATE (Tk.) AMOUNT (Tk.) Cost of shuttering
25 3060 Assuming slabs 10
25 3523.5 Volume of concrete:
25 0 i) Cost of shuttring wood: 0.7
65 2340 Planks & batten required: 4
75 187.5
9111 add 5.00 % for door / window ope
Total 569.4375 Tk.
130 1820 Using 6.00 times @
Total 60.6666667 Batten : Gargan 5 10
add 5.00 %
16 BWG MS SHEET 110 sft
12 432
FOR 17.49 CFT TOTAL 1062.104 ii) Bamboo Props in / c bracket
SO FOR 100 CFT TOTAL 6072.637

iii) Labour for shuttring in /c making,placing & removing:


1.00 10.00
4.00 10.00

iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
(where necessary) for making shutter water-tight sufficiently

Cost for 100.00 cft of co


Analysis of wooden Shuttring R.C.C. work in s
Cost of shuttering
Assuming slabs 8.75
Volume of concrete: 9
i) Cost of shuttring wood: 1
Planks & batten required: 9
2
5
2 5
1

add 5.00 % for door / window ope


Tk.
Using 6.00 times @

ii) Bamboo Props in / c bracket

iii) Labour for shuttring in /c making,placing & removing:


1.00 8.75
9.00 4.00
2.00 8.75

iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
(where necessary) for making shutter water-tight sufficiently

Cost for 100.00 cft of co


stone CHIPS I/C BREAKING sylhet sand 100 % COST OF MATERIALS 165 /ft3
1.5 3 COST OF LABOUR & EQUIPMENTS 16 /ft3
wooden shutter without 20.0 % markup 180 /ft3
total cost with markup total cost without markup with 20.0 % markup 216 /ft3
Tk. 234 /ft3 Tk 6880 /m3 Tk. 195 /ft3 in individual and continuous footings of column
Tk. 220 /ft3 Tk 6480 /m3 Tk. 184 /ft3 in raft/ mat
Tk. 277 /ft3 Tk 8145 /m3 Tk. 231 /ft3 in foundation beam
Tk. 323 /ft3 Tk 9491 /m3 Tk. 269 /ft3 IN Padestals, column capitals, lift walls and walls .
Tk. 290 /ft3 Tk 8518 /m3 Tk. 241 /ft3 in tie beams & lintels
Tk. 293 /ft3 Tk 8622 /m3 Tk. 244 /ft3 in floor & roof slabs
Tk. 293 /ft3 Tk 8605 /m3 Tk. 244 /ft3 in stair case slab & steps
wooden shutter cost with marku wooden shutter cost without marku

Tk. 18 /ft3 Tk 523 /m3 Tk. 15 /ft3 in individual and continuous footings of column

Tk. 4 /ft3 Tk 122 /m3 Tk. 3 /ft3 in raft/ mat


Tk. 61 /ft3 Tk 1788 /m3 Tk. 51 /ft3 in foundation beam
Tk. 107 /ft3 Tk 3134 /m3 Tk. 89 /ft3 IN Padestals, column capitals, lift walls and walls .
Tk. 73 /ft3 Tk 2161 /m3 Tk. 61 /ft3 in tie beams & lintels
Tk. 77 /ft3 Tk 2265 /m3 Tk. 64 /ft3 in floor & roof slabs
Tk. 76 /ft3 Tk 2248 /m3 Tk. 64 /ft3 in stair case slab & steps

ootings of column Considering 100 cft. of work

6.00 ' 6.00 ' 1.00 '


36.00 cft

24.00 ' 1.00 ' 0.08 ' = 2


for batten, supports & wastage = 0.3
@ tk 500.00 per cft 2.30 cft
Using 6 times = tk 191.67

24 sft @ tk 12.00 tk 288.00


assian tape (where necessary) & removing the
24 sft @ tk 1.00 tk 24.00
LS = tk 30.00
Total of Cost = tk 533.67
Cost for 100.00 cft of conc work = tk 1482.41

. Considering 100 cft. of work

30.00 ' 30.00 ' 4.00 '


3600 cft
Planks & batten required:
0.13 ' = 60.00 ' cft
9 cft
69.00 cft tk 500.00 per cft
Using 6 times = tk 5750.00

480.00 ' sft @ tk 12.00 tk 5760.00


& heassian tape(where necessary)

480.00 ' sft @ tk 1.00 = tk 480.00


L.S. = tk 500.00
Total of Cost = tk 12490.00
Cost for 100.00 cft of conc work = tk 346.94

on beam .Considering 100 cft. of work

10.00 ' 3.00 ' 1.50 '


45 cft

0.13 ' = 7.50 ' cft


0.13 ' = 0.75 ' cft
0.13 ' = 0.22 ' cft
1.2703125 cft
9.74 cft tk 500.00 per cft
Using 6 times = tk 811.59

74.53 ' sft @ tk 12.00 = tk 894.30

74.53 ' sft @ tk 1.00 = tk 74.53

L.S. = tk 500.00
Total of Cost = tk 2280.41
Cost for 100.00 cft of conc work = tk 5067.59

s, column capitals, lift walls and walls .


Considering 100 cft. of work
10.00 ' 1.00 ' 1.00 '
10.00 cft

10 1.25 1.5 = 3.125


10 1 1.5 = 2.5
3 0.25 1.5 = 0.375
= 6
wastage = 0.30
Tk. 500.00 per cft 6.30
times Tk. 525.00

@ Tk. 72.00 Each= 48.00


@ Tk. 60.00 Each= 10.00
@ Tk. 6.00 Per stf= 240.00
ent sheet & heassian tape

@ Tk. 1.00 Per stf= 40.00


L.S. = Tk. 25.00

Cost for 100.00 cft of conc work = 8880.00

s of wooden Shuttring R.C.C. work in tie beams & lintels


Considering 100 cft. of work
0.833 0.75
6.25 cft
10 0.833 1.5 2.08 cft
1.08 0.16 1.5 0.19 cft
2.28 cft
for door / window openings wastage 0.23
500.00 per cft 2.50 cft
Tk. 60.00 per cft = tk 208.72
2.00 nos '@' tk 50.00
Using 6.00 times tk 16.67

0.83 = 16.66
0.83 = 2.50
19.16 6 tk 114.95

nt sheet & heassian tape

19.16 1.00 tk 19.16


L.S. = Tk. tk 23.00
Total of (c) 382.50
Cost for 100.00 cft of conc work = = 6122.38

s of wooden Shuttring R.C.C. work in floor & roof slabs


Considering 100 cft. of work
10 0.375
37.50 cft
10 10 1 5.83 cft
10 0.375 1.5 1.88 cft
7.71 cft
for door / window openings wastage 0.39
500.00 per cft 8.09 cft
Tk. 83.33 per cft = tk 674.48
0.25 0.167 2.09 cft
wastage 2.19 cft tk 900.00 /cft tk 328.78
2.55 lbs/sft 280.50 lbs 16 times tk 15.00 /lb tk 262.97

25.00 nos '@' tk 65.00


Using 6.00 times tk 270.83
NAILS 1 kg 65 tk 65.00

10.00 = 100.00
0.38 = 15.00
115.00 6 tk 690.00
nt sheet & heassian tape

115.00 1.00 tk 115.00

Total of (c) 2407.06

Cost for 100.00 cft of conc work = = 6418.83


of wooden Shuttring R.C.C. work in stair case slab & steps
Considering 100 cft. of work
4 0.5
4 0.833 0.5 0.5 25.00 cft
8.75 4 1.5 4.38 cft
4 0.5 1.5 2.25 cft
8.75 1.125 1.5 2.46 cft
4 0.25 0.16 0.80 cft
1.125 0.25 0.16 0.45 cft
8.75 0.25 0.16 0.35 cft
10.69 cft
for door / window openings wastage 0.53
500.00 per cft 11.22 cft
Tk. 83.33 per cft = tk 935.02

10.00 nos '@' tk 50.00


Using 6.00 times tk 83.33
NAILS 1 kg 65 tk 65.00

4.00 = 35.00
0.50 = 18.00
1.13 = 19.69
72.69 6 tk 436.13
nt sheet & heassian tape

72.69 1.00 tk 72.69

Total of (c) 1592.17

Cost for 100.00 cft of conc work = = 6369.43


5810 /m3 R.C.C. work in individual and contin
547 /m3
6357 m3
7629 m3 WOODEN SHUTTER
continuous footings of column CONCRETE
LABOUR,EQIP.
wooden SHUTTER
olumn capitals, lift walls and walls . TOTAL
Contractors profit 0.1
Over head expences 0.025
VAT & IT 0.075
COST FOR 100 CF 21206.62
continuous footings of column SO COST PER CU 7483.82

A. COST OF CONCRETE FOR 100 CFT :


olumn capitals, lift walls and walls . A-1 COST OF MATERIALS
SL. NO. DESCRIPTION OF WORK
a)COST OF brick CHIPS

b) SAND fm 1.8
c)CEMENT

TOTAL MATERIAL COST FOR 100 CFT conc


A-2 COST OF LABOUR & EQUIPMENTS( for
SL. NO. DESCRIPTION OF WORKS
d) H. MASON
e) MASON
f) SKILLED LABOUR

g) LABOUR
h) MIXTURE MACHINE
I) VIBRATOR
j) FULE & LUBRICANTS

FOR 600CFT :
TOTAL LABOUR & EQUIPMENT COST FOR
Analysis of wooden Shuttring in R.C.C. work in i
Considering 100 cft. of work , Cost of shuttering
Considering Base 6'x6'x14" to 10
Volume of concrete: 6'-0" x 6' x 1'-0" (approx.)
i) Cost of shuttring wood:
Planks required:
24.00 ' 1.00 '
add 15% for batten, supports & wastage

Using
ii) Labour for shuttring in /c making,
placing & removing:
iii) Supplying, fitting and fixing, rupban /
equivalent sheet & heassian tape
(where necessary) & removing the
same for making shutter wate

Cost for 100.00 cft of conc work

STEEL SHUTTER IN FOOTINGS OF COLUMN,RAFT & F


COST OF SHUTTERING( for 36 cft )
Sl.No. Description of Works
1 PLATE
2 ANGLE
3 FI BAR
4 FRAME
5 NUTS BOLTS

TAKING USE FOR


6 LABOUR FOR SHUTTERIN
Cost for 100.00 cft of conc work
C.C. work in individual and continuous footings of column at plinth level. R.C.C. work IN Padestals, column capitals, lift wa

WOODEN SHUTTER STEEL SHUTTER WOODEN SHUTTER STEE


tk 14442.00 CONCRETE tk 14442.00 CONCRETE tk 15341.00 CONCRE
tk 1828.33 LABOUR,EQIP. tk 1828.33 LABOUR,EQIP. tk 1828.33 LABOUR,EQ
tk 1401.85 steel SHUTTER tk 2072.87 wooden SHUTTER tk 7230.00 steel SHUTT
17672.1851852 TOTAL 18343.19965278 TOTAL 24399.3333333
1767.21851851852 1834.31996527778 Contractors profit 0.1 2439.9333333333
441.80462962963 458.579991319444 Over head expences 0.025 609.98333333333
1325.41388888889 1375.73997395833 VAT & IT 0.075 1829.95
21206.62 22011.84 COST FOR 100 CF 29279.20
7483.82 7767.98 SO COST PER CU 10332.63

COST OF CONCRETE FOR 100 CFT : 1 1.5 3 A. COST OF CONCRETE FOR 100 CFT : 1
COST OF MATERIALS A-1 COST OF MATERIALS
QTY UNIT RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORK QTY UNIT
83 CFT 66 5478 a)COST OF brick CHIPS 83 CFT
42 CFT 17 714 b) SAND fm 1.8 42 CFT
22 BAG 375 8250 c)CEMENT 22 BAG
TAL MATERIAL COST FOR 100 CFT concrete : 14442 TOTAL MATERIAL COST FOR 100 CFT concrete :
COST OF LABOUR & EQUIPMENTS( for 600 cft) : A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) :
QTY UNIT RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORKS QTY UNIT
1 NOS. 350 350 d) H. MASON 1 NOS.
4 NOS. 300 1200 e) MASON 4 NOS.
6 nos. 200 1200 f) SKILLED LABOUR 6 nos.
34 nos. 180 6120 g) LABOUR 34 nos.
1 DAY 1000 1000 h) MIXTURE MACHINE 1 DAY
1 DAY 600 600 I) VIBRATOR 1 DAY
1 DAY 500 500 j) FULE & LUBRICANTS 1 DAY
FOR 600CFT : 10970 FOR 600CFT :
TAL LABOUR & EQUIPMENT COST FOR 100 CFT WORKS : 1828.33 TOTAL LABOUR & EQUIPMENT COST FOR 100 CFT WORKS :
ysis of wooden Shuttring in R.C.C. work in individual and continuous footings of column at plinth level. Analysis of wooden Shuttring
sidering 100 cft. of work , Cost of shuttering R.C.C. work IN Padestals, column capitals, lift walls and wall
6.00 ' 6.00 ' 1.00 ' Considering 100 cft. of work Cost of shuttering
ume of concrete: 6'-0" x 6' x 1'-0" (approx.) = 36 cft Assuming column size 10.00 ' 1.00 '
Volume of concrete: (approx.) =
i) Cost of shuttring wood:
0.08 ' = 2 cft Planks & batten required:
d 15% for batten, supports & wastage = 0.3 cft 2 10.00 ' 1.25 0.125 =
2.30 cft tk 500.00 2 10.00 ' 1.00 ' 0.125 =
6 times = Tk. tk 191.67 4 3 0.25 0.125 =
abour for shuttring in /c making, =
24 sft @ tk 11.00 tk 264.00 add wastage 5.00 % =
Supplying, fitting and fixing, rupban /
uivalent sheet & heassian tape Using 6.00 times
ere necessary) & removing the ii) Bamboo Props in / c incli 4.00 nos
24 sft @ tk 1.00 tk 24.00 Using 6.00 times
L.S. tk 25.00 iii) Labour for shuttring in /c making,placing & removing:
Total of Cost = tk 504.67
st for 100.00 cft of conc work = tk 1401.85 iv)Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape(where necessary
40.00 sft @ tk 1.00 /sft
EL SHUTTER IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB AT PLINTH LEVEL v) Nails and wires L.S. =
ST OF SHUTTERING( for 36 cft ) Total of
Quantity Unit Rate Amount ( Tk.) Cost for 100.00 cft of conc work =
83.88 LBS 25 2097
157.39 LBS 25 3934.75 STEEL SHUTTER IN RCC IN PADESTALS, COLUMN,COLUMN CAPIT
47.6 LBS 25 1190 COST ANALYSIS OF SHUTTERING (FOR 10 CFT)
24.67 SFT 60 1480.2 SL. NO. DESCRIPTION OF WORK QTY UNIT
1 KG 80 80 1 PLATE 158.68 LBS
8781.95 2 ANGLE 255.2 LBS
16 TIMES 548.871875 3 FI BAR 68 LBS
24.67 SFT 8 197.36 4 FRAME 46.67 SFT
746.23 5 NUTS BOLTS 1.5 KG
st for 100.00 cft of conc work = 2072.866319444
TAKING USE FOR 16 TIMES

6 PROPS 24 RFT
TAKING USE FOR 16 TIMES

7 LABOUR FOR SHUT 40 SFT


FOR 10 CFT
Cost for 100.00 cft of conc work =
stals, column capitals, lift walls and walls . RCC IN TEE, ELL, RECTANGULAR BEAMS

STEEL SHUTTER WOODEN SHUTTER STEEL SHUTTER


CONCRETE tk 15341.00 CONCRETE tk 15341.00 CONCRETE tk 15341.00
LABOUR,EQIP. tk 1828.33 LABOUR,EQIP. tk 1828.33 LABOUR,EQIP. tk 1828.33
steel SHUTTER tk 13354.50 wooden SHUTTER tk 4634.74 steel SHUTTER tk 7584.43
TOTAL 30523.833333333 TOTAL 21804.07175926 TOTAL 24753.76273293
3052.38333333333 Contractors profit 0.1 2180.40717592593 2475.37627329333
763.095833333333 Over head expences 0.025 545.101793981481 618.844068323334
2289.2875 VAT & IT 0.075 1635.30538194444 1856.53220497
36628.60 COST FOR 100 CF 26164.89 29704.52
12926.23 SO COST PER CU 9233.59 10482.72

1.5 3 A. COST OF CONCRETE FOR 100 CFT : 1 1.5 3


A-1 COST OF MATERIALS
RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORK QTY UNIT RATE (Tk.) AMOUNT (Tk.)
75 6225 a)COST OF brick CHIPS 83 CFT 75 6225
18 756 b) SAND fm 1.8 42 CFT 18 756
380 8360 c)CEMENT 22 BAG 380 8360
CFT concrete : 15341 TOTAL MATERIAL COST FOR 100 CFT concrete : 15341
MENTS( for 600 cft) : A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) :
RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.) AMOUNT (Tk.)
350 350 d) H. MASON 1 NOS. 350 350
300 1200 e) MASON 4 NOS. 300 1200
200 1200 f) SKILLED LABOUR 6 nos. 200 1200
180 6120 g) LABOUR 34 nos. 180 6120
1000 1000 h) MIXTURE MACHINE 1 DAY 1000 1000
600 600 I) VIBRATOR 1 DAY 600 600
500 500 j) FULE & LUBRICANTS 1 DAY 500 500
10970 FOR 600CFT : 10970
COST FOR 100 CFT WORKS : 1828.33 TOTAL LABOUR & EQUIPMENT COST FOR 100 CFT WORKS : 1828.33
Analysis of wooden Shuttring
lumn capitals, lift walls and walls . R.C.C. work in foundation beam .
Considering 100 cft. of work
1.00 ' Cost of shuttering
10 cft Considering 10.00 ' 3.00 ' 1.50 '
Volume of concrete: (approx.) = 45 cft

3.13 cft i) Cost of shuttring wood:


2.50 cft Planks & batten required:
0.38 cft 20.00 ' 3.00 ' 0.13 ' = 7.50 ' cft
6.00 cft 24.00 ' 0.25 ' 0.13 ' = 0.75 ' cft
0.30 cft 7.00 ' 0.25 ' 0.13 ' = 0.22 ' cft
6.30 cft @ tk 360.00 /cft
tk 378.00 add 15% for batten, supports & wastage = 1.27031 cft
@ tk 60.00 each 9.74 cft tk 380.00
tk 40.00
40.00 sft @ tk 6.00 /sft Using 6 times =
tk 240.00 ii) Labour for shuttring in /c making,
valent sheet & heassian tape(where necessary) for making shutter water-tight sufficiently placing & removing: 74.53 ' sft @ tk 12.00 =
@ tk 1.00 /sft tk 40.00
tk 25.00
(c) tk 723.00 iii) Supplying, fitting and fixing, rupban or
conc work = tk 7230.00 equivalent sheet & heassian tape
(where necessary)
ESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL for making shutter water-tight 74.53 ' sft @ tk 1.00 =

RATE (Tk.) AMOUNT (Tk.) iv) Nails and wires L.S. =


25 3967 Total of Cost =
25 6380 Cost for 100.00 cft of conc work =
25 1700
60 2800.2
80 120
Total 14967.2 RCC IN TEE, ELL, RECTANGULAR BEAMS
Total 935.45 COST ANALYSIS OF SHUTTERING( FOR 30 CFT)
100 2400 SL. NO. DESCRIPTION OF WORK QTY UNIT RATE (Tk.) AMOUNT (Tk.)
Total 80 1 PLATE 294.44 LBS 13.67 4024.9948
8 320 2 ANGLE 425.32 LBS 11.36 4831.6352
Total 1335.45 3 FI BAR 147.22 LBS 11.36 1672.4192
conc work = 13354.5 4 FRAME 86.6 SFT 40 3464
5 NUTS BOLTS 4 KG 60 240
14233.0492
TAKING USE FOR 16 TIMES Total 889.565575
6 PROPS 14 RFT 100 1400
TAKING USE FOR 30 TIMES Total 46.66666666667

7 LABOUR FOR SHUT 86.6 SFT 7 606.2


SO FOR 30 CFT TOTAL 1542.432241667
SO FOR 100 CFT TOTAL 5141.4408056

A. CONCRETE 11665
B. LAB/EQIP 1103.33
C SHUTTER 5141.44
17909.77

Contractors profit 0.1 1790.977


Over head expences 0.025 447.74425
VAT & IT 0.075 1343.23275
COST FOR 100 CFT GRAND TOTAL 21491.724
SO COST PER CUM = TK. 7584.4293996
per cft

tk 616.81

tk 894.30

tk 74.53

tk 500.00
tk 2085.63
tk 4634.74
At site cost of materials :
Cost of bricks per no. Tk 6.00 brick chips cft Tk 50.00
Viti sand cft Tk 9.00 stone chips cft Tk 80.00
Sand fm 1:8 cft Tk 15.00

Sylhet sand 2.5 cft Tk 30.00

cement per bag Tk 380.00


reinf 60 gr kg Tk 70.00
reinf 40 gr kg Tk 66.00

Brick flat soling


unit Qty u. rate
A.Material cost
bricks nos 300.00 Tk 6.50
sand fm-.5 cft 5.00 Tk 11.00

B. Labour cost
H. mason nos 0.06 Tk 350.00
mason each 0.25 Tk 250.00
skilled labour each 1.00 Tk 200.00
local carriage sundries
tools & Plants etc ls
Total

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%

RATE PER 100SFT

RATE PER SFT

5" BW(1:4)GF S.ST.


100 sft unit Qty u. rate
A.Material cost
bricks nos 480.00 Tk 6.00
sand fm-1.5 cft 17.00 Tk 15.00
cement bag 2.60 Tk 380.00
B. Labour cost
head mason each 0.10 Tk 250.00
mason each 0.50 Tk 200.00
or. labour each 1.00 Tk 100.00
curing7days@1/4 lab each 1.75 Tk 100.00
local carriage each 0.40 Tk 100.00
scaffolding T&P etc ls

Total
RATE PER SFT

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%

RATE PER 100SFT


RATE PER SFT

BW(1:6) in foundation
100 CFT unit Qty u. rate
A.Material cost
bricks nos 1,100.00 Tk 6.00
sand fm-1.5 cft 36.00 Tk 15.00
cement bag 4.00 Tk 380.00

B. Labour cost
head mason each 0.10 Tk 250.00
mason each 1.00 Tk 180.00
s. labour each 1.00 Tk 120.00
or. labour each 1.50 Tk 100.00
curing7days@1/4 lab each 1.75 Tk 100.00
local carriage,storage
sundries, T&P etc ls
Total
RATE PER CFT

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT

RATE PER CFT

250 MM THICK BRICK WORK IN SUPER STRUCTURE (1:6 )


A - 1 : MATERIALS( FOR 100 CFT)
SL. NO. DESCRIPTION OF WORKS QTY UNIT
1 BRICKS 1150 NOS
2 SAND 36 CFT
3 CEMENT 4 BAGS
4 H. MASON 0.1 NOS
5 MASON 1 NOS
6 S. LABOUR 1 NOS
7 LABOUR 1.5 NOS
8 CURING L 1.75 NOS
9 LOCAL CAR 1 LS
TOTAL FOR 100 CFT
A - 2 : SCAFFOLDING & EXTRA LABOUR COST
SL. NO. DESCRIPTION OF WORKS QTY UNIT
1 SCAFFOLD 25 SFT
2 EXTRA LA 1 NOS
3 EXTRA LA 0.5 NOS
4 SOAKING 2 NOS
5 SCREENING 0.5 NOS
TOTAL FOR 100 CFT

A. + B.

Contractors profit
Over head expences
VAT & IT
COST FOR 100 CFT(GRAND TOTAL) =

COST PER CUM =

CC 1:3:6 Found/flr
unit Qty u. rate
A.Material cost
bricks 90cft chips nos 765.00 Tk 6.00
sand fm-1.5 cft 45.00 Tk 15.00
cement bag 12.00 Tk 280.00
breaking/screening cft 90.00 Tk 6.00
B. Labour cost
head mason each 0.25 Tk 200.00
mason each 0.75 Tk 160.00
s. labour each 2.00 Tk 100.00
or. labour each 2.00 Tk 90.00
curing7days@1/4 lab each 1.75 Tk 90.00
local carriage,storage
sundries, T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
RATE PER CFT 4196.47506

ANALYSIS OF CAST IN-SITU PILES


Selected Office : : Chittagong
Item Type : Foundation Works
Item Name : Bored cast in place piles
Unit of Estimation : Lin. Metre
Quantity for Estimation : 25
Breakdown of Input Items : (All prices are in Taka
Specification Item Components
Input Items Qty for
Item Name Unit Of Estimation Estimation

Item Type : Equipment


Bored pile day 1
equipment
(750 mm)
Concrete day 1
Mixer (7/5)
Item Type : Labour
foreman day 1
masons day 1
semi-skilled day 1
labourer
Item Type : Material
Bentonite bag 1
(50kg)
Cement tonne 1
OPC
Coarse cu. metre 1
Sand
FM>2.5
crushed cu. metre 1
boulder/gra
vel
aggregate
<25mm
Total Price of Specification Item
Basic Unit Price of Specification Item
Plus Profit at 10.00%
Sub-Total
Plus Tax & VAT at 9.2896%
Total Unit Price of Specification Item

ANALYSIS OF RCC WORKS


T,L,Rib beam rcc works 1 :
100.00 cft without rod
A. Cost of mat tk/unit cost in tk
bricks nos 729 6.00 Tk 4,371.43
sand fm1.5 cft 21.43 16.00 Tk 342.86
sand fm2.5 cft 21.43 30.00 Tk 642.86
cement bag 17.14 380.00 Tk 6,514.29
total Tk 11,871.43
B. Labour cost
breaking&screening cft 85.71 8.00 Tk 685.71
local carriage,storage etc ls Tk 38.00 Tk 38.00
curing7days@1/4 lab each 1.75 100.00 Tk 175.00
for casting
head mason each 0.05 250.00 Tk 12.50
mason each 0.25 200.00 Tk 50.00
skilled labour
feeding cement 0.50 120.00 60.00
feeding sand 0.50 120.00 60.00
feeding chips 0.50 120.00 60.00
ordinary labour
bag cutting each 0.05 100.00 5.00
belcha each 0.50 100.00 50.00
lifting 2.00 100.00 200.00
pouring 2.00 100.00 200.00
on the way 2.00 100.00 200.00
polling 0.50 100.00 50.00
watering 0.05 100.00 5.00

hire charge
mixture machine ls 100.00 100.00
vibrator ls 60.00 60.00
fuel & lubricant ls 50.00 50.00
miscellaneous ls 30.00 30.00
total Tk 2,091.21

C. cost of shattering
Let beam 20×1.5×.83
concrete vol=25cft
1 shuttering wood
planks 40.00 1.50 0.13
20.00 1.08 0.13
butten 11.25 0.25 0.13
10.80 0.17 0.13
total
using 6 times total
2 bamboo post 6times
3 slbullah10nos×10ft 8times
4 nails
5 labour for shuttering 20.00 1.50 2.00
20.00 0.83 1.00
FOR 25cft total cost
FOR 100cft total cost

gross total A+B+C

miscellaneous cost
overhead&sundries 10%
contractor's profit 10%
FOR 100CFT
COST PER CFT GF
COST PER CFT 1ST F
COST PER CFT 2nd F

Suppling,fabrication etc MS
1.00 cwt
cost of mat unit qty rate
ms rod DB cwt 1.00 3,400.00
GI wire seer 1.00 90.00
labour cost
rod binder each 0.20 200.00
helper-skilled each 0.75 140.00
local carriage,T&P ls
total
Misce. cost
overhead&sundries 7.00 %
contractor's profit 6.00 %
Rate per cwt
Rate per ton

/cft %
RCC beam/girder 8.50 lbs 1.73
(no slab in/c) 9.00 lbs 1.84
10.00 lbs 2.04
11.00 lbs 2.24
12.00 lbs 2.45
5.00 1.02

Suppling,fabrication etc MS REINFORCEMENT all floor 60DB-Fy415MPa


1.00 cwt
cost of mat unit qty rate
ms rod DB cwt 1.00 1,200.00
GI wire seer 1.00 70.00

labour cost
rod binder each 0.20 160.00
helper-skilled each 0.75 80.00
local carriage,T&P ls
total

Misce. cost
overhead&sundries 10%
contractor's profit 10%
Rate per cwt
Rate per ton

/cft %
Rec beam/girder lbs 8.50 1.73
no slab in/c lbs 9.00 1.84
lbs 10.00 2.04
lbs 11.00 2.24
lbs 12.00 2.45

PLASTER
1/4"th (1:4) cp on cealing,col,beam
100sft unit Qty u. rate
A. Material cost

sand fm-1.5 cft 3.00 Tk 15.00


cement bag 0.50 Tk 380.00

B. Labour cost

head mason each 0.25 Tk 200.00


mason each 1.00 Tk 150.00
ordinary labour each 1.00 Tk 90.00
scaffolding,curing,local carriage etc. ls
Total

C. Miscellaneous cost

overhead & sundries 10%


contractor's profit 10%

RATE PER 100SFT

RATE PER SFT

PLASTER
min 1/2"th (1:6) cp on outer wall
100sft unit Qty u. rate

A.Material cost

sand fm-1.5 cft 6.00 Tk 15.00


cement bag 0.75 Tk 380.00

B. Labour cost

head mason each 0.25 Tk 250.00


mason each 1.00 Tk 150.00
or. labour each 1.00 Tk 100.00
scaffolding,curing
local carriage etc. ls
Total

C.Miscellaneous cost

overhead & sundries 10%


contractor's profit 10%

RATE PER 100SFT


RATE PER SFT

PLASTER
min 3/4"th1:6cp inner wall
100sft unit Qty u. rate

A.Material cost
sand fm-1.5 cft 8.00 Tk 15.00
cement bag 1.00 Tk 380.00

B. Labour cost
head mason each 0.25 Tk 250.00
mason each 1.25 Tk 150.00
or. labour each 1.25 Tk 100.00
scaffolding,curing
local carriage etc. ls
Total

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%

RATE PER 100SFT

RATE PER SFT

BAILING OUT WATER


Considering 1 day operation=8 hrs

1. Hire charge of pump set in/c fuel,B8


lubricants, operator, spares,maintenance etc

1 day @ tk 1000/ per day = tk


Contractor's profit
overhead expences3.5%

VAT4.5%
GT

RATE PER HOUR

Facing BW(1:4) 8"×4"×2"


unit Qty u. rate
A.Material cost
bricks nos 745.00 Tk 5.50
sand fm-1.5 cft 10.00 Tk 8.00
cement bag 3.50 Tk 250.00
B. Labour cost
head mason each 0.25 Tk 160.00
mason each 3.00 Tk 140.00
s. labour each 1.00 Tk 80.00
or. labour each 2.00 Tk 70.00
curing7days@1/4 lab each 1.75 Tk 70.00
local carriage,storage each 0.50 Tk 70.00
scaffolding T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
RATE PER CFT

Herring bone bond soling


unit Qty u. rate
A.Material cost
bricks nos 500.00 Tk 6.00
sand fm-.5 cft 10.00 Tk 9.00
B. Labour cost
mason each 0.50 Tk 160.00
skilled labour each 1.00 Tk 90.00
local carriage
sundries T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

CBW(1:4)GF 10holes
unit Qty u. rate
A.Material cost
bricks nos 1,100.00 Tk 6.00
sand fm-1.5 cft 40.00 Tk 15.00
cement bag 6.50 Tk 380.00
B. Labour cost
head mason each 0.10 Tk 180.00
mason each 1.00 Tk 150.00
s. labour each 3.00 Tk 100.00
or. labour each 1.50 Tk 90.00
curing7days@1/4 lab each 1.75 Tk 90.00
local carriage,storage
sundries, T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
RATE PER CFT

1.5" patent stone 1:2:4


100sft unit Qty u. rate
A.Material cost
bricks nos 106.00 Tk 6.00
sand fm-1.5 cft 3.00 Tk 15.00
sand fm-2.5 cft 3.00 Tk 30.00
cement bag 2.25 Tk 360.00
B. Labour cost
head mason each 0.20 Tk 180.00
mason each 0.75 Tk 150.00
s. labour each 1.00 Tk 100.00
or. labour each 1.00 Tk 90.00
curing7days@1/4 lab each 1.75 Tk 90.00
local carriage
sundries T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

colour washing 2coat over


1000 sft unit Qty u. rate
A.Material cost
slaked stone lime kg 18.66 Tk 3.50
gum cha 1.00 Tk 10.00
blue cha 1.00 Tk 5.00
colour pigment seer 0.75 Tk 90.00
B. Labour cost
mason each 1.50 Tk 140.00
or. labour each 1.00 Tk 70.00
scaffolding,curing
local carriage etc. LS
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 1000SFT
RATE PER SFT
WHITE washing 3 coat
1000 sft unit Qty u. rate

A.Material cost
slaked stone lime kg 18.66 Tk 4.00
gum cha 1.00 Tk 10.00
blue cha 1.00 Tk 5.00

B. Labour cost
mason each 1.50 Tk 160.00
or. labour each 1.00 Tk 90.00
scaffolding,curing
local carriage etc. LS
Total

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%

RATE PER 1000SFT

RATE PER SFT

plastic paint to wall/ceiling


100 sft

unit Qty u. rate


A.Material cost
paint 1gall=300sft gall 0.33 Tk 900.00

B. Labour cost
painter each 0.50 Tk 160.00
helper each 0.50 Tk 100.00
scaffolding,sundries etc ls
Total

C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

paint to d/w fr/shutt 2


100 sft unit Qty u. rate
A.Material cost
paint 1gall=300sft gall 0.33 Tk 780.00

B. Labour cost
mason each 1.00 Tk 140.00
or. labour each 1.00 Tk 70.00
sand paper,putty,thinner
etc LS
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

Supplying , fitting and fixing alluminium sliding door with 75.5mm wide section & locking arran
Considering 6.00 '
A. Alluminium shutter

1 75.5mm, 17.79mm Outer bottom of 1.5mm thick


0.528kg/m 1

2 75.5mm, 26.8mm Outer top of 1.5mm thick


0.780kg/m 1

3 33mm, 26.8mm ,22mm shutter top of 1.5mm thick


0.536kg/m 1

4 60mm, 24mm shutter bottom of 1.5mm thick


0.736kg/m 1

5 75.5mm, 19.9mm outer side of 1.5mm thick


0.616kg/m 2

6 31mm, 26mm SLIDING FIXED SIDE of 1.5mm thick


0.422kg/m 1

7 49.2mm, 26.2mm Shutter lock of 1.5mm thick


0.661kg/m 1

8 34.4mm, 32.1mm inter lock of 1.5mm thick


0.665kg/m 2

9 31.75mm shutter divider of 1.5mm thick


0.535kg/m 1
10 7.14mm spandrel of 1.4 to 1.5mm thick
0.700kg/m 12

B. Fittings
sliding door key lock
sliding door wheel
sliding door mohiar
sliding door neoprene
bolts & screws in/c sealants

C. Labour charges for fittings & accessories(angles,screws,rivet

Skilled technechian
Semi-Skilled technechian
Machineries charges

D. Labour charge
1 labour charges for fabrication of alluminium sections in/c cutting,fitting & fixing etc
Skilled technechian
Semi-Skilled technechian
2 labour cost for civil work in dismantling ,installation,levelling,fitting/fixing in positio
Mason
Labour

E. Carriage & sundries

TOTAL (material + labour)

With Contractor's profit

With Over head expences

With VAT
TILES SFF6"×6"white gt foreign on cm 1:3
100sft unit Qty u. rate
A.Material cost
w.glazed tile3sft/doz doz 33.33 Tk 195.00
base:3/4"avg. 1:3
cement bag 1.88 Tk 250.00
sand cft 7.03 Tk 8.00
white cement bag 0.09 Tk 900.00

B. Labour cost
head mason each 2.00 Tk 160.00
mason each 2.00 Tk 140.00
skilled labour each 3.00 Tk 80.00
ord. labour in/c curing each 3.00 Tk 70.00
L.carriage,sundries,t&p LS
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

TILES SFF 6"×6"white gt local on cm 1:3


100sft unit Qty u. rate
A.Material cost
w.glazed tile3sft/doz doz 33.33 Tk 126.00
base:3/4"avg. 1:3
cement bag 1.88 Tk 250.00
sand cft 7.03 Tk 8.00
white cement bag 0.09 Tk 900.00

B. Labour cost
head mason each 2.00 Tk 160.00
mason each 2.00 Tk 140.00
skilled labour each 3.00 Tk 80.00
ord. labour in/c curing each 3.00 Tk 70.00
L.carriage,sundries,t&p LS
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

Flr mosaic 3/8" with glass w.c/gc=1:1 silver grey


100sft unit Qty u. rate
A.Material cost
w.c (40kg/bag) bag 1.20 Tk 900.00
g.c. (50kg/bag) bag 1.00 Tk 250.00
m.chips-india-w:b=8:1 bag 3.50 Tk 337.50
cost of acid lb 3.00 Tk 60.00
glass strip20×5mm rft 120.00 Tk 3.00
1" patent stone
B. Labour cost
a.For mixing/laying/compacting
head mason each 0.75 Tk 160.00
s. labour each 0.75 Tk 80.00
or. labour each 0.75 Tk 70.00
curing each 0.25 Tk 70.00
b. for glass strip laying
mason each 0.75 Tk 140.00
ordinary labour each 0.75 Tk 70.00
c.hire charge of m. machine and operation
hire charge(in/c meter
setting/elec.cost) LS
machine operator each 1.00 Tk 200.00
helper each 1.00 Tk 80.00
ord. labour each 1.00 Tk 70.00
pumic stone each 3.00 Tk 160.00
spreading/washing
oxalic acid ord.labor each 1.00 70.00
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

Flr mosaic 3/8" with glass w.c/gc=9:1


100sft unit Qty u. rate
A.Material cost
w.c (40kg/bag) bag 2.15 Tk 900.00
g.c. (50kg/bag) bag 0.20 Tk 250.00
m.chips-india-w:b=8:1 bag 3.50 Tk 337.50
cost of acid lb 3.00 Tk 60.00
glass strip20×5mm rft 120.00 Tk 3.00
1" patent stone
B. Labour cost
a.For mixing/laying/compacting
head mason each 0.75 Tk 160.00
s. labour each 0.75 Tk 80.00
or. labour each 0.75 Tk 70.00
curing each 0.25 Tk 70.00
b. for glass strip laying
mason each 0.75 Tk 140.00
ordinary labour each 0.75 Tk 70.00
c.hire charge of m. machine and operation
hire charge(in/c meter
setting/elec.cost) LS
machine operator each 1.00 Tk 200.00
helper each 1.00 Tk 80.00
ord. labour each 1.00 Tk 70.00
pumic stone each 3.00 Tk 160.00
spreading/washing
oxalic acid ord.labor each 1.00 70.00
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT

Supplying , fitting and fixing steel glazed win

Considering 5.00 '

A. Steel Materials
1 Z-section 0.75''

Chowkat

Shutter fr 2
2

With wastage

2 FI bars to make T-section

Shutter fr 2 2
With wastage

3 FI bar

chowkat
With wastage
B. Fittings
stopper handle
12" long iron cleats
6" long clamp for chowkat
2" long pin hinges

C. Work shop charges


(labour charges for manufacturing,welding,cutting,finishing in/c supply of electrod

D. Labour charges for fitting/fixing in position

Mason
Skilled labour
Screws

E. Carriage

F. Glass panes
3 mm glass panes in/c wastage
fitting/fixing with iron pins/pucca putty

TOTAL (material + labour)

With Contractor's profit

With Over head expences

With VAT

Supplying , fitting a
3/4" x

Considering 4.50 '

A. Materials
1 outer frame
3/4" x 3/16" 0.478

2 inner frame
3/4" x 3/16" 0.478
horijontal 3.50 '
vertical 4.50 '
diagonal 2.00 '

B. Work shop charges


(labour charges for manufacturing,welding,cutting,finishing in/c supply of electrod

C. Labour charges for fitting/fixing in position

Mason
Skilled labour
Screws

D. Carriage

G. TOTAL (material + labour)

With Contractor's profit

With Over head expences

With VAT
:

Suppling,fabrication etc MS rod


1.00 cwt
cost cost of mat unit qty rate
ms rod DB cwt 1.00 2,650.00
Tk 1,950.00 GI wire seer 0.50 105.00
Tk 55.00 5% OF 100 SFT labour cost
rod binder each 0.20 350.00
helper-skilled each 0.75 250.00
Tk 21.88 local carriage,T&P ls 60.00
Tk 62.50 total
Tk 200.00 Misce. cost
overhead&sundries 0.00 %
Tk 50.00 contractor's profit 10.00 %
Tk 2,339.38 TK 23.39 Rate per cwt
Rate per ton

Tk 233.94 TK 25.73 Suppling,fabrication etc MS rod


Tk 233.94 1.00 cwt
cost of mat unit qty rate

Tk 2,807.25 ms rod DB cwt 1.00 2,500.00

$302.06 TK 28.07 GI wire seer 0.50 90.00


labour cost
rod binder each 0.20 200.00
helper-skilled each 0.75 140.00

local carriage,T&P ls 15.00


cost total
Misce. cost
Tk 2,880.00 overhead&sundries 7.00 %
Tk 255.00 contractor's profit 9.00 %
Tk 988.00 Rate per cwt
Rate per ton

Tk 25.00 Analysis of deformed bar , 60 grade


Tk 100.00 Site Office : Chittagong

Tk 100.00 General Info

Tk 175.00 Item Type : Structures

Tk 40.00 Item Name : High Yield Reinforcement Bars

Unit of : Tonne
Tk 60.00 Estimation
Quantity for : 1
Estimation
Tk 4,623.00 Breakdown of Input Items (All prices are in Taka)

Tk 46.23 Input Items Specification Item Components


Unit Of Qty for
Estimatio Estimati Price for
Item Name n on Estim. Qty
Item Type :
Tk 462.30 Equipment
Tk 462.30 small hand tools (2) day 1 5

Item Type :
Labour
Tk 5,593.83 semi-skilled labourer day 1 150

TK 55.94 steel fixers day 1 150


unskilled labourer day 1 100
Item Type :
Material
G.I wire, nails etc kg 1 95

cost M. S. bar 60 grade tonne 1 53,000.00

Total Price of Specification Item :

Tk 6,600.00 Basic Unit Price of Specification Item :


Tk 540.00 Plus Profit at 10.00% :

Tk 1,520.00 Sub-Total :

Plus Tax & VAT at 9.2896% :


Total Unit Price of Specification Item :

Tk 25.00
Tk 180.00
Tk 120.00
Tk 150.00
Tk 175.00

Tk 30.00
Tk 9,340.00
Tk 93.40

Tk 934.00
Tk 934.00
Tk 11,301.40

TK 113.01

R STRUCTURE (1:6 )

RATE (Tk.) AMOUNT (Tk.)


6 6900
15 540
380 1520
220 22
150 150
120 120
100 150
100 175
50 50
L FOR 100 CFT 9627

RATE (Tk.) AMOUNT (Tk.)


10 250
100 100
100 50
100 200
100 50
L FOR 100 CFT 650

10277

10% 1027.7
3% 256.925
8% 770.775
TK. 12332.4

TK. 4352.104

cost

Tk 4,590.00
Tk 675.00
Tk 3,360.00
Tk 540.00

Tk 50.00
Tk 120.00
Tk 200.00
Tk 180.00
Tk 157.50

Tk 37.00
Tk 9,909.50

Tk 990.95
Tk 990.95
Tk 11,891.40
TK 118.91

F CAST IN-SITU PILES 400 25


600 20
750 7
s dia = 500 mm 900 4.6
1000 4.25

(All prices are in Taka)


Specification Item Components
Qty for Price for Estim.
Price for Estim. Qty Estimation Qty Unit Price

4200 1 4,200.00 168.00

750 1 750.00 30.00

250 1 250.00 10.00


150 6 900.00 36.00
100 8 800.00 32.00

500 3 1,500.00 60.00

7,600.00 1.875 14,250.00 570.00

1050 2 2,100.00 84.00

2,200.00 4.0156 8,834.32 353.37


: 33584.32
: 1343.37
: 134.34
: 1477.71
: 137.27
: tk 492.37 /ft 8229.21 /cum 1614.98

WORKS
2 : 4

118.71 TK/CFT

Tk 18.51 PER CFT

20.91 PER CFT


7.50 cft
2.71 cft
0.35 cft
0.23 cft unit rate
10.78 cft 450.00 Tk 4,853.20
Tk 808.87
4.00 no. 55.00 Tk 36.67
100.00 rft 40.00 Tk 500.00
1.00 kg 52.00 Tk 52.00
60.00 sft
16.66 sft 4.00 Tk 306.64
Tk 1,704.17
Tk 6,816.70
68 /cft
TK 20,779.34

TK 4,155.87
TK 24,935.21
TK 249.35 /cft
lifting & hoisting 3.00 TK 252.35
Tk 255.35

all floor 60DB-Fy415MPa

cost
3,400.00
90.00

40.00
105.00
7.00
Tk 3,642.00

254.94
218.52
Tk 4,115.46
Tk 82,309.20 gf

reinforcement con cost ground flr 1st floor


cost /cft of concrete /cft con+rod con+rod
Tk 317.35 249.35 566.70 Tk 569.70
Tk 336.02 249.35 585.37 Tk 588.37
Tk 373.35 249.35 622.70 Tk 625.70
Tk 410.69 249.35 660.04 Tk 663.04
Tk 448.02 249.35 697.37 Tk 700.37
Tk 186.68 249.35 436.03 Tk 439.03

floor 60DB-Fy415MPa

cost
1,200.00
70.00

32.00
60.00
7.00
Tk 1,369.00

136.90
136.90
Tk 1,642.80
Tk 32,856.00

cost /cft
Tk 126.68
Tk 134.13
Tk 149.03
Tk 163.94
Tk 178.84

am
cost

Tk 45.00
Tk 190.00

Tk 50.00
Tk 150.00
Tk 90.00
Tk 72.00
Tk 597.00

Tk 59.70
Tk 59.70

Tk 716.40

TK 7.16

all
cost

Tk 90.00
Tk 285.00

Tk 62.50
Tk 150.00
Tk 100.00

Tk 60.00
Tk 747.50

Tk 74.75
Tk 74.75

Tk 897.00
TK 8.97
cost

Tk 120.00
Tk 380.00

Tk 62.50
Tk 187.50
Tk 125.00

Tk 60.00
Tk 935.00

Tk 93.50
Tk 93.50

Tk 1,122.00

TK 11.22

1,000.00
100.00
35.00
1,135.00
51.08
1,186.08

tk 148.26

cost

Tk 4,097.50
Tk 80.00
Tk 875.00

Tk 40.00
Tk 420.00
Tk 80.00
Tk 140.00
Tk 122.50
Tk 35.00
Tk 75.00
Tk 5,965.00

Tk 596.50
Tk 596.50
Tk 7,158.00
TK 71.58

cost

Tk 3,000.00
Tk 90.00

Tk 80.00
Tk 90.00

Tk 24.00
Tk 3,284.00

Tk 328.40
Tk 328.40
Tk 3,940.80
TK 39.41

cost

Tk 6,600.00
Tk 600.00
Tk 2,470.00

Tk 18.00
Tk 150.00
Tk 300.00
Tk 135.00
Tk 157.50

Tk 30.00
Tk 10,460.50
Tk 1,046.05
Tk 1,046.05
Tk 12,552.60
TK 125.53

cost

Tk 636.00
Tk 45.00
Tk 90.00
Tk 810.00

Tk 36.00
Tk 112.50
Tk 100.00
Tk 90.00
Tk 157.50

Tk 44.00
Tk 2,121.00

Tk 212.10
Tk 212.10
Tk 2,545.20
TK 25.45

cost

Tk 65.31
Tk 10.00
Tk 5.00
Tk 67.50

Tk 210.00
Tk 70.00

Tk 32.00
Tk 459.81

Tk 45.98
Tk 45.98
Tk 551.77
TK 0.552
oat
cost

Tk 74.64
Tk 10.00
Tk 5.00

Tk 240.00
Tk 90.00

Tk 40.00
Tk 459.64

Tk 45.96
Tk 45.96

Tk 551.57

TK 0.552

cost

Tk 297.00

Tk 80.00
Tk 50.00
Tk 40.00
Tk 467.00

Tk 46.70
Tk 46.70
Tk 560.40
TK 5.60

cost
Tk 257.40

Tk 140.00
Tk 70.00

Tk 44.00
Tk 511.40

Tk 51.14
Tk 51.14
Tk 613.68
TK 6.137

5.5mm wide section & locking arrangement (bronze colour)


x 7.00 ' = 42 sft

x 6.00 ' = 6.00 rft @ tk 46.45

x 6.00 ' = 6.00 rft @ tk 61.86

f 1.5mm thick
x 5.75 = 5.75 rft @ tk 42.52

x 5.75 = 5.75 rft @ tk 58.38

x 7.00 ' = 14.00 rft @ tk 51.45

E of 1.5mm thick
x 7.00 ' = 7.00 rft @ tk 34.00

x 7.00 ' = 7.00 rft @ tk 53.84

x 7.00 ' = 14.00 rft @ tk 61.03

x 5.75 = 5.75 rft @ tk 44.71


x 2.50 = 30.00 rft @ tk 35.38

Wastage
Sub total (A)

2.00 sets @ tk 125.00


2.00 nos @ tk 30.00
46.00 rft @ tk 1.70
52.00 rft @ tk 1.50

Sub total (B)

& accessories(angles,screws,rivets,mohiar,washer,machinery etc. complete)

0.5 nos @ tk 250.00


0.5 nos @ tk 160.00

Sub total (C)

minium sections in/c cutting,fitting & fixing etc. complete.


1 nos @ tk 250.00
1 nos @ tk 160.00
ng ,installation,levelling,fitting/fixing in position
0.5 nos @ tk 150.00
0.5 nos @ tk 100.00
Sub total (D)

LS

10 %

3.50 %

4.50 %
on cm 1:3
cost

Tk 6,499.35

Tk 468.75
Tk 56.25
Tk 81.00
Tk 7,105.35

Tk 320.00
Tk 280.00
Tk 240.00
Tk 210.00
Tk 78.00
Tk 8,233.35 Tk 1,128.00

Tk 823.34
Tk 823.34
Tk 9,880.02
TK 98.80

n cm 1:3
cost

Tk 4,199.58

Tk 468.75
Tk 56.25
Tk 81.00
Tk 4,805.58

Tk 320.00
Tk 280.00
Tk 240.00
Tk 210.00
Tk 78.00
Tk 5,933.58 Tk 1,128.00

Tk 593.36
Tk 593.36
Tk 7,120.30
TK 71.20

grey
cost

Tk 1,080.00
Tk 250.00
Tk 1,181.25
Tk 180.00
Tk 360.00
Tk 781.71 Tk 3,832.96

Tk 120.00
Tk 60.00
Tk 52.50
Tk 17.50

Tk 105.00
Tk 52.50

Tk 75.00
Tk 200.00
Tk 80.00
Tk 70.00
Tk 480.00

Tk 70.00
Tk 5,215.46

Tk 521.55
Tk 521.55
Tk 6,258.55
TK 62.59

gc=9:1
cost

Tk 1,935.00
Tk 50.00
Tk 1,181.25
Tk 180.00
Tk 360.00
Tk 781.71 Tk 4,487.96

Tk 120.00
Tk 60.00
Tk 52.50
Tk 17.50
Tk 105.00
Tk 52.50

Tk 75.00
Tk 200.00
Tk 80.00
Tk 70.00
Tk 480.00

Tk 70.00
Tk 5,870.46

Tk 587.05
Tk 587.05
Tk 7,044.55
TK 70.45

, fitting and fixing steel glazed window with Z-section,T-section & FI bars etc.

x 3.00 ' = 15 sft

0.75'' 0.75'' 0.13'' 0.96lbs/rft

3 5.00 ' 15.00rft


2 3.00 ' 6.00rft
2 5.00 ' 20.00rft
2 1.50 ' 6.00rft
Total 47.00rft
With wastage 5% 49.35rft 47.23lbs @ tk 8.71

0.75'' 0.13'' 0.32lbs/rft

4 1.5 24.00rft
With wastage 5% 25.20rft 8.04lbs @ tk 7.71

1.00'' 0.13'' 0.43lbs/rft

1 5.00 ' 5.00rft


With wastage 5% 5.25rft 2.23lbs @ tk 7.71

1.74kg/sft Sub total (material)


2.00 nos @ tk 5.00
2.00 nos @ tk 10.00
4.00 nos @ tk 10.00
4.00 nos @ tk 8.00
Sub total (fittings)

15 sft @ tk 24.00
elding,cutting,finishing in/c supply of electrode)

xing in position

0.33 nos @ tk 150.00


0.33 nos @ tk 120.00
3 doz @ tk 6.00
Sub total (labour f/f)

1 no @ tk 15.00

15 sft @ tk 20.00
15 sft @ tk 6.00
Sub total

10 %

3.50 %

4.50 %

Supplying , fitting and fixing window grill made of M.S. Section


3/4" x 3/16" both inner & outer frames

x 3.50 ' = 15.75 sft


wastage 5% 16.8 rft
lbs/rft 8.0304 lbs @ tk 7.71

wastage 5%
lbs/rft
x 5 = 17.5 rft
x 4 = 18 rft
x 30 = 60 rft
100.275 rft
47.93145 lbs @ tk 7.71

Sub total (material)

15.75 sft @ tk 20.00


elding,cutting,finishing in/c supply of electrode)

xing in position

0.33 nos @ tk 150.00


0.33 nos @ tk 120.00
3 doz @ tk 6.00
Sub total (labour f/f)

1 no @ tk 15.00

10 %

3.50 %

4.50 %

Supplying/making door/window frames with seasoned wood


in/c 2coats coalter painting
assume3.25ft×7f 3.25 7.00
finished inch 2.50 5.00
gross inch 2.75 5.25
For Silkarai wood
finished wood r 1.50 cft
gross wood req 1.73 cft
A. Material cos QTY UNIT unit ratecost
cost of wood 1.73 cft ### Tk 1,383.59
coaltaring 2coats LS Tk 10.00
B. Labour cost
carpenter 0.75 each ### Tk 120.00
helper 1.00 each ### Tk 80.00
f/f in position TK 40.00
Total Tk 1,633.59
C. Miscellaneous cost
overhead & sund 10% Tk 163.36
contractor's prof 10% Tk 163.36
Total cost ###
RATE PER CFT Tk 1,309.15

Supplying/f/f 1.5"th solid wood shutter with seasoned wood


assume6.83ft×3f 6.83 3.00 20.49 sft- single leaf
finished inch 1.50 inch
gross inch 1.75 inch
For Kathal/Chapalish wood
A. Material cos QTY UNIT unit rate cost
cost of wood 2.99 cft ### Tk 2,390.50

B. Fittings cost
Iron tower bolt 1 1.00 each ### Tk 24.00
socket bolt 9"lo 1.00 each ### Tk 22.00
hinges 4" long 4.00 each ### Tk 40.00
nickle plated ha 2.00 each ### Tk 26.00
iron screw 1/2" 2.00 dzn Tk 7.00 Tk 14.00
hinged cleats and
buffer block LS Tk 37.75
C. Labour cost
carpenter 3.00 each ### Tk 480.00
helper 5.00 each ### Tk 400.00
Total Tk 3,434.25
C. Miscellaneous cost
overhead & sund 10% Tk 343.43
contractor's prof 10% Tk 343.43
Total cost ###
RATE PER SFT Tk 201.13

ANALYSIS OF 125 MM THICK BRICK IN SUPER STRUCTURE (


A - 1 : MATERIALS
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
1 BRICKS 480 NOS 3.6
2 SAND 17 CFT 9
3 CEMENT 2.6 BAGS 260
4 H. MASON 0.1 NOS 200
5 MASON 0.5 NOS 150
6 SOAKING & CLEAN 1 NOS 100
7 LABOUR 1 NOS 100
8 CURING LABOUR 1.75 NOS 100
9 SCREENING & WAS 0.25 NOS 100
10 SCAFFOLDING & CO 25 SFT 5
11 LOCAL CARRIAGE & 0.4 LS 50
TOTAL FOR 100 SFT

Contractors profit 10%


Over head expence 3%
VAT & IT 8%
COST FOR 100 SFT GRAND TOTAL

SO COST PER SQM = TK. 412.950096

ANALYSIS OF 100 MM THICK CONCRETE HOLLOW BLOCK WORK


MATERIALS
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
1 BLOCK ( IN/C CARR 113 NOS 18.25
2 CEMENT 1.15 BAGS 260
3 SAND 5.7 CFT 9
LABOUR
1 FOR BLOCK WORK 100 SFT 2
2 CURING 1 LS 175
3 SCAFFOLDING & CO 1 LS 100

LOCAL CARRIAGE 1 LS 50

TOTAL FOR 100 SFT

Contractors profit 10%


Over head expence 2.50%
VAT & IT 7.50%
COST FOR 100 SFT GRAND TOTAL

SO COST PER SQM = TK. 379.43746

ANALYSIS OF 150 MM THICK CONCRETE HOLLOW BLOCK WORK


MATERIALS QTY UNIT RATE (Tk.)
1 BLOCK ( IN/C CARR 113 NOS 30.5
2 CEMENT 1.75 BAGS 260
3 SAND 8.6 CFT 9
LABOUR
1 FOR BLOCK WORK 100 SFT 4
2 CURING 1 LS 175
3 SCAFFOLDING & CO 1 LS 100

LOCAL CARRIAGE 1 LS 80

TOTAL FOR 100 SFT

Contractors profit 10%


Over head expence 2.50%
VAT & IT 7.50%
COST FOR 100 SFT GRAND TOTAL

SO COST PER SQM = TK. 611.4684

COST ANALYSIS FOR 100 SFT 140 MM DEPTH CONCRETE CEILING BLOCK IN R

A-1 COST OF MATERIALS FOR 100 SFT FLOOR AREA


SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
a) COST OF CONCRETE CEI 75 NOS 38
TOTAL MATERIAL COST :

A-2 COST OF LABOUR & EQUIPMENTS FOR 100 SFT FLOOR AREA
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
1 FOREMAN 0.1 NOS. 300
2 TECHNITION 0.25 NOS. 250
3 SKILLED LABOUR 1 NOS. 120
4 LABOUR 1 NOS. 100

A - 3 COST OF SHUTTERING FOR 320 SFT OF FLOOR AREA


SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
1 COST OF STEEL S 83.88 LBS 13.67
2 1/12" THICK STEEL 1088 LBS 13.67
3 ANGLE UNDER STE1642.68 LBS 11.36
4 STEEL FRAME OF 320 SFT 30
5 NUTS & BOLTS 12 KG 60
TAKING USE FOR 16 TIMESSUB TOTAL
6 STEEL PROPS ;
A) 2" DIA MS/GI PI 14 RFT 100
B) COST OF ADJUS 1 LS 400

SO TOTAL COST OF PROPS 63 NOS 1800


C) 2" DIA MS/GI PIPE CROSS BAR OR MS I-BEAM 144 RFT 100

TAKING USE FOR 30 TIMES SUB TOTAL

6 LABOUR FOR SHU 320 SFT 7

TOTAL
SO COST FOR 100 SFT OF SHUTTERING : TK. 2325.94

MATERIALS
LABOUR,EQIP.
SHUTTERING
TOTAL
Contractors profit 10%
Over head expence 2.50%
VAT & IT 7.50%
COST FOR 100 SFT GRAND TOTAL

COST OF EACH BLOCK WITH LABOUR AND SHUTTERING WHEN USED IN CEILING AND ROOF TK.
R.C.C. work in individual and continuous footing
level.
60DB-Fy415MPa A. COST OF CONCRETE FOR 100 CFT :
A-1 COST OF MATERIALS
cost SL. NO. DESCRIPTION OF WORKS
2,650.00 a)COST OF brick CHIPS
52.50 b) SAND fm 1.8
c)CEMENT
70.00
187.50
60.00 A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) :
Tk 3,020.00 SL. NO. DESCRIPTION OF WORKS
d) H. MASON
0.00 e) MASON
302.00 f) SKILLED LABOUR
Tk 3,322.00 g) LABOUR
Tk 66,440.00 gf h) MIXTURE MACHINE

I) VIBRATOR

40DB-Fy276MPa j) FULE & LUBRICANTS


FOR 600CFT :
cost SO FOR 100CFT COST IS

2,500.00 Analysis of wooden Shuttring


R.C.C. work in individual and continuous footings of column at plinth level.
45.00
Considering 100 cft. of work
40.00 Cost of shuttering
105.00 Considering Base 6'x6'x14" to 10"

15.00 Volume of concrete: 6'-0" x 6' x 1'-0" (approx.) =


Tk 2,705.00 i) Cost of shuttring wood:
Planks required:
189.35 24.00 ' 1.00 '
243.45 add 15% for batten, supports & wastage =
Tk 3,137.80
Tk 62,756.00 gf Using
ii) Labour for shuttring in /c making,
d bar , 60 grade placing & removing:
tagong iii) Supplying, fitting and fixing, rupban /
equivalent sheet & heassian tape
(where necessary) & removing the
nt Bars same for making shutter water-ti

All prices are in Taka)

on Item Components Cost for 100.00 cft of conc work =


Price for
Estim. Unit
Qty for Estimation Qty Price STEEL SHUTTER IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB AT PLINT

COST OF SHUTTERING( for 36 cft )


17 85 85 Sl.No. Description of Works
1 PLATE
6 900 900 2 ANGLE
4 600 600 3 FI BAR
6.1 610 610 4 FRAME
5 NUTS BOLTS
20 1900 1900

1.03 54590 54590


TAKING USE FOR
58,685.00

58,685.00 6 LABOUR FOR SHUTTERING


5,868.50
64,553.50 SO FOR 100CFT
5,996.76

70,550.26 CONCRETE
LABOUR,EQIP.
wooden SHUTTER
TOTAL
Contractors profit 0.1
Over head expences 0.025
VAT & IT 0.075
COST FOR 100 CFT GRAND TOTAL

SO COST PER CUM =


1 1 1 6 8 3
1.47 1 1.5 9 12 4
1 1 1 6 8 3
1 1 1 6 8 3
1 1 1 6 8 3
per rft = tk 278.70

per rft = tk 371.16

per rft = tk 244.49

per rft = tk 335.69

per rft = tk 720.30

per rft = tk 238.00

per rft = tk 376.88

per rft = tk 854.42

per rft = tk 257.08


per rft = tk 1061.40

tk 4738.12
03.00% tk 142.14
= tk 4880.26 tk 116.20 /sft

each = tk 250.00
each = tk 60.00
each = tk 78.20
each = tk 78.00
ls = tk 40.00
= tk 506.20

each = tk 125.00
each = tk 80.00
L.S = tk 100.00
= tk 305.00 tk 7.26 /sft

each = tk 250.00
each = tk 160.00

each = tk 75.00
each = tk 50.00
tk 535.00 tk 12.74 /sft

= tk 100.00 tk 2.38 /sft

= TK 6326.46 tk 150.63 /sft

= TK 6959.11 tk 165.69 /sft

= TK 7180.53 tk 170.97 /sft

= TK 7503.66 tk 178.66 /sft


per lbs = tk 411.37

per lbs = tk 61.98

per lbs = tk 17.22

Sub total (material) = tk 490.57 tk 32.70 /sft


each = tk 10.00
each = tk 20.00
each = tk 40.00
each = tk 32.00
Sub total (fittings) = tk 102.00

= tk 360.00 tk 24.00 /sft

each = tk 49.50
each = tk 39.60
doz = tk 18.00
Sub total (labour f/f) = tk 107.10 tk 7.14 /sft

= tk 15.00 tk 1.00 /sft

= tk 300.00 tk 940.41 /sft


= tk 90.00 #DIV/0!
tk 390.00

= TK 1464.67 tk 97.64 /sft

= TK 1611.13 tk 107.41 /sft

= TK 1662.40 tk 110.83 /sft

= TK 1737.20 tk 115.81 /sft


per lbs = tk 61.91

= tk 369.55

Sub total (material) = tk 431.47 tk 27.39 /sft

= tk 315.00 tk 20.00 /sft

each = tk 49.50
each = tk 39.60
doz = tk 18.00
Sub total (labour f/f) = tk 107.10 tk 6.80 /sft

= tk 15.00 tk 0.95 /sft

= TK 868.57 tk 55.15 /sft

= TK 955.42 tk 60.66 /sft

= TK 985.82 tk 62.59 /sft

= TK 1030.18 tk 65.41 /sft

h seasoned wood
g
sft- single leaf

SUPER STRUCTURE (1:4)

AMOUNT (Tk.)
1728
153
676
20
75
100
100
175
25
125
20
3197

319.7
79.925
239.775
3836.4

LOCK WORK

AMOUNT (Tk.)
2062.25
299
51.3

200
175
100

50

2937.55

293.755
73.43875
220.31625
3525.06

LOCK WORK
AMOUNT (Tk.)
3446.5
455
77.4

400
175
100

80

4733.9

473.39
118.3475
355.0425
5680.68

RETE CEILING BLOCK IN ROOF SLAB

AMOUNT (Tk.)
2850
2850

FLOOR AREA
AMOUNT (Tk.)
30
62.5
120
100
312.5

AMOUNT (Tk.)
1146.6396
14872.96
18660.8448
9600
720
45000.4444
2812.527775

1400
400
1800

113400
14400
127800
4260

2240
7443

2850
313
2325.94
5488.94
548.894
137.2235
411.6705
6586.728

87.82304
dividual and continuous footings of column at plinth
level.
E FOR 100 CFT : 1 1.5 3

QTY UNIT RATE (Tk.) AMOUNT (Tk.)

83 CFT 75 6225
42 CFT 18 756
22 BAG 380 8360

TOTAL MATERIAL COST : 15341


& EQUIPMENTS( for 600 cft) :
QTY UNIT RATE (Tk.) AMOUNT (Tk.)
1 NOS. 350 350
4 NOS. 300 1200
6 nos. 200 1200
34 nos. 180 6120
1 DAY 1000 1000
1 DAY 600 600
1 DAY 500 500
10970
100CFT COST IS Total 1828.33
oden Shuttring
continuous footings of column at plinth level.

6.00 ' 6.00 ' 1.00 '


6'-0" x 6' x 1'-0" (approx.) = 36 cft

0.08 ' = 2 cft


upports & wastage = 0.3 cft
2.30 cft tk 400.00
6 times = Tk. tk 153.33
g in /c making,
24 sft @ tk 11.00 tk 264.00
nd fixing, rupban /
eassian tape
removing the
24 sft @ tk 1.00 tk 24.00

L.S. tk 25.00
Total of Cost = tk 466.33
cft of conc work = tk 1295.37

GS OF COLUMN,RAFT & FLOOR SLAB AT PLINTH LEVEL

Quantity Unit Rate Amount ( Tk.)


83.88 LBS 13.67 1146.6396
157.39 LBS 11.36 1787.9504
47.6 LBS 11.36 540.736
24.67 SFT 50 1233.5
1 KG 60 60
4768.826
16 TIMES 298.051625

24.67 SFT 7 172.69


479.69
SO FOR 100CFT 1332.4845679

tk 15341.00 CONCRETE tk 15341.00


tk 1828.33 LABOUR,EQIP. tk 1828.33
tk 1295.37 steel SHUTTER tk 1332.48
18464.7037 TOTAL 18501.817901
1846.47037037 1850.1817901235
461.617592593 462.54544753087
1384.85277778 1387.6363425926
22157.644 22202.18148

7819.43272444 7835.1498448148
1.2 1.28 2.57 3900
2.2 2.31 4.62 3900
1.2 1.25 2.53 4000
1.15 1.19 2.39 4100
1.3 1.36 2.73 4100
CIVIL WORK Estimate for a 3-storied Building at Gazipur
Subject : Ground Floor i/c. Foundation,gb,col,1fb,1fs(p),dw.

Materials Detail Mat. Cost


SL Item of works Qty Unit wastage Qty Unit
Type Quantity Unit Rate Tk.

1 R.C.C Work(1:1.5:3) with 50% Sylhet &50%Local Sand. a)With stone Chips
column 11.14 cum 0.50 % Cement 0.22 1,671 Bag 380.00 635,092.09
lintel/beam 9.66 cum 3.00 % Sylhet Sand 0.20 1,606 Cft 24.00 38,539.56
cft
lift core 14.79 cum 4.00 % Local Sand 0.20 1,621 Cft 16.00 25,942.49
7,621.99
stair1 3.03 cum 2.00 % Stone Chips 0.82 6,361 Cft 90.00 572,480.89
stair2 5.07 cum
messanine floor 172.29 cum
R.C.C Work(1:2:4) with 50%Sylhet &50%Local Sand.b)With Brick Chips
0.10 cum 0.50 % Cement 0.17 1 Bag 380.00 231.04
cum 3.00 % Sylhet Sand 0.16 1 Cft 24.00 14.02
3.53 cft
cum 4.00 % Local Sand 0.16 1 Cft 16.00 9.44
5.00 % Brick Chips 0.64 2 Cft 70.00 166.75
2 Re-inforcement work
60-Grade D. bar for col. 13.30 Ton 2.00 % 13.30437763 ton Rebar 1.00 13.57 Ton 60,000.00 814,227.91
40-Grade D. bar for gf slab. 0.00 Ton 2.00 % 0.10 ton Rebar 1.00 0.102 Ton 50,000.00 5,100.00
3 Shuttering work 586.43 Sqm. 1.00 % 6,312.365 sft
4 10" & above Brick works (1:6)
0.31 Cum 2.00 % 10.94 cft Cement 0.043 0.48 Bag 380.00 182.33
2.00 % Local Sand 0.32 3.58 Cft 15.00 53.73
2.00 % Bricks 11.00 123 Nos. 6.50 797.85
5 5"Brick work (1:5)
2.00 % Cement 0.05 0.05 Bag 380.00 20.86
0.1 Sqm. 1.08 Sft
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.35 0.38 Cft 15.00 5.76
2.00 % Bricks 5.00 5.49 Nos. 6.50 35.68
6 1/2" cement plaster (1:4) with NCF
2.00 % Cement 0.0100 1.10 Bag 380.00 417.21
10 Sqm. 107.64 Sft
2.00 % Local Sand 0.08 8.78 Cft 15.00 131.75
7 3/4"Cement plaster (1:6)
2.00 % Cement 0.01 0.01 Bag 380.00 4.17
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.08 0.09 Cft 15.00 1.32
2.00 % S.Paper 0.50 Doz. 22.00 11.00
8 Window/verandah Grill 0.1 Sqm. 5.00 % 1.0764 Sft steel 1.00 1.13 Kg 120.00 129.17
9 Dismantling works 1 L.S
10 Repairing works/others 1 L.S

TOTAL tk 2093595
azipur

La. Rate La. Cost Total Cost Remarks


Tk Tk Tk

11.00 cft 83,841.91 1,355,896.94 tk177.89/cft

11.00 cft 38.82 460.06 tk130.37/cft

1,500.00 ton 19,956.57 834,184.48 tk61.47/kg


1,500.00 ton 150.00 5,250.00 tk51.47/kg
12.00 sft 75,748.38 75,748.38

4.50 cft 49.23 1,083.14 tk 99.01 /cft

4.00 cft 4.31 66.61


4.00 cft 4.31 66.61 tk 61.89 /sft

3.50 Sft 376.74 925.70 tk 8.60 /sft

3.50 Sft 3.77 20.26 tk 18.82 /sft

25.00 Sft 26.91 156.08


100.00
100.00

tk 180197 tk 2273992
CIVIL WORK Estimate for a 3-storied Building at Gazipur
Subject : Ground Floor i/c. Foundation,gb,col,1fb,1fs(p),dw.

Materials Detail Mat. Cost La. Rate La. Cost Total Cost Remarks
SL Item of works Qty Unit wastage Qty Unit
Type Quantity Unit Rate Tk. Tk Tk Tk

1 Lay out & site preparation 1,560.00 Sqm. 16791.84 sft L.S 8,000.00
2 Earth Work 937.46 cum 33,082.96 cft 2.50 cft 82,707.41 82,707.41 tk2.50/cft
3 Soling in fdn. & floor Sqm. 2.00 % sft Bricks/Sft 3.00 15,155.36 No 6.50 98,509.83
460.12 4952.73 2.00 sft 9,905.46 111,446.37 tk22.50/sft
2.00 % sand(cft/Sft) 0.06 303.11 cft 10.00 3,031.07
4 Polythine Laying 3,252.50 Sqm. 4.00 % 35,009.91 sft Polythene 36,410.31 Sft 0.75 27,307.73 0.25 sft 8,752.48 36,060.21 tk1.03/sft
5a Sand & Khoa compaction below footing:
40 : 60 507.00 cum 5.00 % 17,892.03 cft khoa 0.40 7,514.65 cft 70.00 526,025.68 4.00 cft 71,568.12 707,093.03 tk39.52/cft
2.00 % sand 0.60 10,949.92 cft 10.00 109,499.22
5b Sand & Khoa filling for compaction below Slab:
1 :30 :20 5.00 % khoa 0.39 5,332.94 cft 70.00 373,305.92
tk44.84/cft
367.00 cum 2.00 % 12,951.43 cft sand 0.59 7,770.86 cft 10.00 77,708.58 4.00 cft 51,805.72 580,792.91
1.00 % cement 0.01569 205.19 bag 380.00 77,972.69
6 C.C Work in foundation & floor
0.50 % Cement 0.12 0.34 Bag 380.00 129.38
tk126.57/cft
0.08 cum 2.00 % 2.82 cft L/Sand 0.45 1 Cft. 10.00 12.96 10.00 cft 28.23 357.33
5.00 % B/Chips 0.90 3 Cft 70.00 186.75
7 R.C.C Work(1:1.5:3) with 50% Sylhet &50%Local Sand. a)With stone Chips
footing 169.00 cum 0.50 % Cement 0.22 1,630 Bag 380.00 619,343.57
short col 13.50 cum 2.00 % Sylhet Sand 0.20 1,551 Cft 24.00 37,219.00
cft 11.00 cft 81,762.87 1,259,634.65 tk169.47/cft
GB 11.01 cum 3.00 % Local Sand 0.20 1,566 Cft 16.00 25,055.93
7,432.99
lift core 16.90 cum 2.00 % Stone Chips 0.82 6,203 Cft 80.00 496,253.29
stair 0.214 cum 2.00 %
cum 2.00 %
R.C.C Work(1:2:4) with 50%Sylhet &50%Local Sand.b)With Brick Chips
GF 161.90 cum 0.50 % Cement 0.17 984 Bag 380.00 374,060.44
cum 2.00 % Sylhet Sand 0.16 937 Cft 24.00 22,478.89
5,713.59 cft 11.00 cft 62,849.47 744,488.68 tk130.30/cft
cum 3.00 % Local Sand 0.16 946 Cft 16.00 15,132.85
5.00 % Brick Chips 0.64 3,857 Cft 70.00 269,967.03
8 Re-inforcement work
60-Grade D. bar for col. 18.95 Ton 2.00 % 18.95208943 ton Rebar 1.00 19.33 Ton 60,000.00 1,159,867.87 1,500.00 ton 28,428.13 1,188,296.01 tk61.47/kg
40-Grade D. bar for gf slab. 12.06 Ton 2.00 % 0.10 ton Rebar 1.00 0.102 Ton 50,000.00 5,100.00 1,500.00 ton 150.00 5,250.00 tk51.47/kg
9 Shuttering work 595.70 Sqm. 1.00 % 6,412.134 sft 12.00 sft 76,945.61 76,945.61
10 Sand filling with vitty sand. 1 cum 3.00 % 35.29 cft V.Sand 1.20 43.62 Cft 9.00 392.57 3.00 cft 105.87 498.44
11 10" & above Brick works (1:6)
0.31 Cum 2.00 % 10.94 cft Cement 0.043 0.48 Bag 380.00 182.33
4.50 cft 49.23 1,083.14
2.00 % Local Sand 0.32 3.58 Cft 15.00 53.73 4.50 cft 49.23 1,083.14 tk 99.01 /cft
2.00 % Bricks 11.00 123 Nos. 6.50 797.85
12 5"Brick work (1:5)
2.00 % Cement 0.05 0.05 Bag 380.00 20.86
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.35 0.38 Cft 15.00 5.76 4.00 cft 4.31 66.61 tk 61.89 /sft
2.00 % Bricks 5.00 5.49 Nos. 6.50 35.68
13 1/2" cement plaster (1:4) with NCF
2.00 % Cement 0.0100 0.01 Bag 380.00 4.17 3.50 Sft 3.77 9.26 tk 8.60 /sft
0.1 Sqm. 1.08 Sft
2.00 % Local Sand 0.08 0.09 Cft 15.00 1.32
14 3/4"Cement plaster (1:6)
2.00 % Cement 0.01 0.01 Bag 380.00 4.17
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.08 0.09 Cft 15.00 1.32 3.50 Sft 3.77 20.26 tk 18.82 /sft
2.00 % S.Paper 0.50 Doz. 22.00 11.00
15 Window/verandah Grill 0.1 Sqm. 5.00 % 1.0764 Sft steel 1.00 1.13 Kg 120.00 129.17 25.00 Sft 26.91 156.08
16 Dismantling works 1 L.S 100.00
17 Repairing works/others 1 L.S 100.00

TOTAL tk 4319809 tk 475097 tk 4803106


SUMMARY
upto pl
item rcc rod shutter rcc
footing 5884.00 cft 12529.33 kg 633.40 sft 0.00 cft
short column 456.00 cft 2487.64 kg 1460.52 sft 0.00 cft
grade beam 1358.29 cft 2852.70 kg 5542.41 sft 0.00 cft
lift core 218.11 cft 366.25 kg 344.0328 628.97 cft
lift core 2 378.37 cft 690.02 kg 503.4577 937.05 cft
stair case1 3.77 cft 13.07 kg 9.93 sft 320.31 cft
stair case2 3.77 cft 13.07 kg 9.93 sft 537.13 cft
GROUND FLOOR 5713.59 cft 12058.90 kg 0.00 sft 0.00 cft
SUPER STR COL 0.00 cft 0.00 kg 0.00 sft 1179.03 cft
LINTEL/BEAM 0.00 cft 0.00 kg 0.00 sft 1022.89 cft
M FLOOR 0.00 cft 0.00 kg 0.00 sft 18240.58 cft

14015.89 cft 31010.99 kg 6409.75 sft 22865.98 cft

FOOTING/PILE CAP RCC


R.C.C REINF WEIGHT
% of rod shutter Description No. Length (ft)
Volume (KG)
(CFT)
114.33 408.04 1.606 % 108.48 sft PG1 2 7.872
453.75 1091.00 1.082 % 2.00 sft PG2 3 11
324.00 524.37 0.728 % 3.00 sft PG3 4 9
500.00 961.42 0.865 % 4.00 sft PG4 5 10
964.69 1754.10 0.818 % 5.00 sft PG5 7 10.5
319.87 563.96 0.793 % 6.00 sft PG6 6 8
512.00 751.95 0.661 % 7.00 sft PG7 8 8
0.00 0.00 #DIV/0! 8.00 sft 0 0
0.00 2.96 #DIV/0! 9.00 sft 0 0
0.00 1.52 #DIV/0! 10.00 sft 0 0
0.00 1.68 #DIV/0! 11.00 sft 0 0

3189 6061.009 0.855 % 173.48 sft

SHORT COLUMN UPTO PL RCC


R.C.C Volume T REINF WEIGHT COLUMN STIRRUPS Description
% of rod shutter
(CFT) (KG) ROD KG ROD KG
74.89 362.38 2.177 % 346.35 16.04 199.50 sft SC1
66.40 361.47 2.449 % 346.35 15.12 189.44 sft SC2
24.90 118.69 2.145 % 108.23 10.46 71.04 sft SC3
37.45 104.39 1.254 % 94.67 9.72 104.19 sft SC4
41.62 165.50 1.789 % 154.41 11.08 121.36 sft SC5
99.88 555.23 2.501 % 543.76 11.47 291.26 sft SC6
10.84 80.54 3.344 % 72.16 8.39 38.63 sft SC7
88.38 697.16 3.549 % 690.85 6.31 385.00 sft supportcol
11.62 42.27 1.637 % 36.94 5.33 60.09 sft
2393.72 93.92
456 2487.64 2.455 % 2.362 % 0.093 % 1460.52 sft

GRADE BEAM RCC


R.C.C Volume T REINF WEIGHT
Description
GRADE BEAM STIRRUPS
% of rod shutter
(CFT) (KG) ROD KG ROD KG
403.80 1533.51 1.709 % 956.58 576.94 1647.67 sft GB1
954.49 2731.74 1.288 % 1540.00 1191.74 3894.74 sft TB
2496.58 1768.67
1358 4265.26 1.413 % 0.827 % 0.586 % 5542.41 sft

LIFT CORE RCC


R.C.C Volume T REINF WEIGHT
Description
COLUMN STIRRUPS
% of rod shutter
(CFT) (KG) ROD KG ROD KG
99.90 161.51 0.727 % 161.51 0.00 46.52 sft BASE
118.21 204.74 0.779 % 204.74 0.00 297.51 sft WALL UPTO PL

628.97 2486.45 1.779 % 2486.45 0.00 1930.28 sft WALL ABOVE PL

2852.70 0.00
847 2852.70 1.515 % 1.515 % 0.000 % 2274.31 sft
lift core 2
204.22 407.67 0.898 % 407.67 0.00 70.87 sft BASE
174.14 282.36 0.730 % 282.36 0.00 432.59 sft WALL UPTO PL

937.05 3964.23 1.903 % 3964.23 0.00 2840.82 sft WALL ABOVE PL

4654.26 0.00
1315 4654.26 1.592 % 1.592 % 0.000 % 3344.28 sft

RCC STAIR CASE RCC


R.C.C Volume T REINF WEIGHT
Description
main STIRRUPS
% of rod shutter
(CFT) (KG) ROD KG ROD KG
stair-1 2flight stair
3.77 13.07 1.559 % 8.84 4.23 9.93 sft BASE B
38.86 209.16 2.422 % 161.66 47.50 119.65 sft 1ST FLIGHT

11.33 38.00 1.509 % 0.00 38.00 26.92 sft tread


44.31 136.94 1.390 % 94.63 42.31 136.44 sft 2ND FLIGHT

12.27 0.00 0.000 % 0.00 0.00 29.17 sft tread


265.13 132.03
111 397.17 1.616 % 1.079 % 0.537 % 322.11 sft
stair-2 3hree flight stair
3.77 13.07 1.559 % 8.84 4.23 9.93 sft BASE B
13.89 115.21 3.732 % 87.92 27.29 41.75 sft 1ST FLIGHT

10.30 0.00 0.000 % 0.00 0.00 20.40 sft tread


114.18 360.84 1.422 % 254.49 106.35 232.73 sft 2ND FLIGHT

19.74 0.00 0.000 % 0.00 0.00 39.48 sft tread


15.84 130.29 3.701 % 92.65 37.64 47.61 sft 3rd flight
5.10 0.00 0.000 % 0.00 0.00 10.20 sft tread
443.91 175.51
183 619.41 1.524 % 1.092 % 0.432 % 402.09 sft

GROUND FLOOR AREA (PANEL WISE)

PANEL NOS. LENGTH WIDTH HIEGHT VOLUME/M3


A1 5 9.25 5.848 0.127 34.34969
A2 4 8.991 5.848 0.127 26.710318944
A3 1 8.991 5.426 0.127 6.195716082
A4 1 9.25 5.426 0.127 6.3741935
A5 1 9.25 6.433 0.127 7.55716675
A6 1 8.991 6.157 0.127 7.030413549
A7 1 9.25 18.625 0.127 21.87971875
A8 1 9.25 11.524 0.127 13.537819
A9 1 8.88 6.433 0.127 7.25488008
A10 2 8.88 5.848 0.127 13.19028096
A11 1 10.93 5.848 0.127 8.11766728
A12 1 10.118 5.848 0.127 7.514598128
A13 1 9.403 5.426 0.127 6.479626106
A14 1 8.81 3.46 0.127 3.8712902
A15 1 9.25 2.478 0.127 2.9110305
A16 1 9.25 1.482 0.127 1.7409795
A17 1 8.991 0.963 0.127 0.5498041455
A18 1 4.17 6.433 0.127 3.40685247
A19 1 2.574 5.848 0.127 1.911699504
TOTAL 180.5837454485
NET 161.90 m3
septic tank 2 388 SFT 776
water tank 1 678 SFT 678
LCA 1 64 SFT 64
CLA 1 64 SFT 64
147.048 M2
THICKNESS 5 INCH 18.67986 M3

SUPER STR COLUMN RCC


R.C.C Volume T REINF WEIGHT Description
COLUMN STIRRUPS
% of rod shutter
(CFT) (KG) ROD KG ROD KG
366.81 1464.41 1.796 % 1455.27 9.14 2202.48 sft gf
366.81 1464.41 1.796 % 1455.27 9.14 2202.48 sft 1stf
445.41 1784.47 1.803 % 1773.89 10.58 2674.44 sft 2ndf
4684.43 28.86
1179 4713.30 1.799 % 1.788 % 0.011 % 7079.40 sft

SUPER STR LINTEL/BEAM RCC


R.C.C Volume T REINF WEIGHT Description
GRADE BEAM STIRRUPS
% of rod shutter
(CFT) (KG) ROD KG ROD KG
695.38 1893.88 1.225 % 1211.25 682.63 3376.29 sft TL1
327.52 892.33 1.226 % 570.49 321.84 1590.22 sft TL2
0.00 0.00 #DIV/0! 0.00 0.00 0.00 sft TL3
1781.74 1004.47
1023 2786.21 1.226 % 0.784 % 0.442 % 4966.51 sft

RCC FLOOR SLAB RCC


R.C.C REINF WEIGHT
% of rod shutter Description No. Length (ft)
Volume (KG)
(CFT)
20833.10 156946.09 3.389 % 322.77 sft RCC SLAB 3 127.39
-550.23 4058553.64 -3318.665 % 2.00 sft - GAP 1 1613
-3513.62 151510.22 -19.401 % 3.00 sft - STAIR1 1 420
-269.40 1554.09 -2.595 % 4.00 sft - STAIR2 3 19.43
-61.27 378.62 -2.780 % 5.00 sft - LCORE1 3 7.6
0.00 0.00 #DIV/0! 6.00 sft - LCORE2 0 0

16439 4368942.7 119.577 % 342.77 sft

MATERIAL REQUISITION OF MEZZANINE FLOOR


JOB NAME : AFTAB GARMENTS LIMITED
TOTAL
CONCRETE STEEL LENGTH LAPPING TOTAL WEIGHT GRAND TOTAL
WASTAGE
VOLUME (m3) (m) LENGTH (m) LENGTH (m) OF STEEL WEIGHT (Kg)
(Kg)
FIRST FLOOR
165.22 18336.74 555.18 18891.92 7461.25 2% 7610.47

SECOND FLOOR
175.83 18542.82 547.92 19090.74 7539.77 2% 7690.57

THIRD FLOOR
175.83 18542.82 547.92 19090.74 7539.77 2% 7690.57
TOTAL
516.88 55422.38 1651.02 57073.40 22540.80 2% 22991.61

AFTAB THREE FLIG


REINFORCEMENT
DESCRIPTION X -AREA MM^2 LENGTH OF GAP NOS OF VOL. MM^3
LENGTH
EACH BAR MM MM BAR
REINFORCEMENT FOR FIRST FLIGHT
10 mm dia @ 250 c/c 78.50 1699.00 8168.32 34.00 0.00
16 mm@ 175 c/c alt ckd both end 200.96 3778.32 1699.00 11.00 0.01
12mm dia @ 175 c/c 113.04 1880.00 1699.00 11.00 0.00
12mm dia @ 175 c/c 113.04 2520.00 1699.00 11.00 0.00
4 nos. 16mm dia 200.96 1699.00 4.00 0.00
10mm dia stirup @ 175 c/c 78.50 1300.00 1699.00 11.00 0.00
SUB TOTAL IN KG
REINFORCEMENT FOR 2ND FLIGHT
10 mm dia @ 150 c/c 78.50 1699.00 10826.47 74.00 0.01
20 mm dia @ 175 c/c alt ckd Both end 314.00 6730.47 1699.00 11.00 0.02
12mm dia @ 175 c/c 113.04 3946.00 1699.00 11.00 0.00
113.04 2.00 0.00
SUB TOTAL IN KG
REINFORCEMENT FOR 3RD FLIGHT
10 mm dia @250 c/c 78.50 1699.00 10070.19 42.00 0.01
16mm dia @ 175 c/c alt ckd 200.96 4557.77 1699.00 11.00 0.01
12 mm dia @ 175 113.04 1674.00 1699.00 11.00 0.00
SUB TOTAL IN KG
1.48 % TOTAL IN KG

AFTAB TWO FLIGH


REINFORCEMENT
DESCRIPTION X -AREA MM^2 LENGTH OF GAP NOS OF VOL. MM^3
LENGTH
EACH BAR MM MM BAR
REINFORCEMENT FOR FIRST FLIGHT
10 mm dia @ 250 c/c 78.50 1699.00 8496.29 35.00 0.00
16 mm@ 175 c/c alt ckd both end 200.96 5262.16 1699.00 11.00 0.01
12mm dia @ 175 c/c 113.04 1970.00 1699.00 11.00 0.00
4 nos. 16mm dia 200.96 1699.00 1699.00 4.00 0.00
10mm dia stirup @ 150 c/c 78.50 1300.00 1699.00 13.00 0.00
SUB TOTAL IN KG
REINFORCEMENT FOR 2ND FLIGHT
10 mm dia @ 250 c/c 78.50 1699.00 10467.14 43.00 0.01
16 mm@ 175 c/c alt ckd both end 200.96 8512.00 1699.00 11.00 0.02
12mm dia @ 175 c/c 113.04 1696.00 1699.00 11.00 0.00
4 nos. 16mm dia 200.96 1699.00 1699.00 0.00 0.00
10mm dia stirup @ 150 c/c 78.50 1300.00 1699.00 0.00 0.00

SUB TOTAL IN KG
1.12 % TOTAL IN KG
Y
above pl
rod shutter
0.00 kg 0.00 sft
0.00 kg 0.00 sft
0.00 kg 0.00 sft
2486.45 kg 1930.28 sft
3964.23 kg 2840.82 sft
1152.29 kg 936.55 sft
1819.03 kg 1176.50 sft
0.00 kg 0.00 sft
4713.30 kg 7079.40 sft
2786.21 kg 4966.51 sft
22991.61 kg

39913.13 kg 18930.06 sft

RCC
Clear cover casting rod BOTTOM LONG BAR
Width (ft) T (ft) t (ft) S (ft) DIA MM spacing
wastage wastage mm c/c
2.952 2.46 0 0 75.00 mm 0.00 % 0.00 % 20 96
11 1.25 0 0 75.00 mm 0.00 % 0.00 % 20 150
9 1 0 0 75.00 mm 0.00 % 0.00 % 16 175
10 1 0 0 75.00 mm 0.00 % 0.00 % 16 150
10.5 1.25 0 0 75.00 mm 0.00 % 0.00 % 16 125
8 0.833 0 0 75.00 mm 0.00 % 0.00 % 16 200
8 1 0 0 75.00 mm 0.00 % 0.00 % 16 200
0 0 0 0 75.00 mm 0.00 % 0.00 % 16 200
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 250
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 300
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 250

REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod MAIN BAR
wastage wastage
corner bar DIA MM

8 1.67 1.5 3.7 38.00 mm 1.00 % 2.00 % 4 20


8 1.67 1.33 3.7 38.00 mm 1.00 % 2.00 % 4 20
3 1.67 1.33 3.7 38.00 mm 1.00 % 2.00 % 4 20
4 2.16 1.16 3.7 38.00 mm 1.00 % 2.00 % 4 16
5 1.92 1.16 3.7 38.00 mm 1.00 % 2.00 % 4 16
12 1.92 1.16 3.7 38.00 mm 1.00 % 2.00 % 4 16
2 1.25 1.16 3.7 38.00 mm 1.00 % 2.00 % 4 20
25 1 1 3.5 38.00 mm 1.00 % 2.00 % 4 20
4 0.67 1.16 3.7 38.00 mm 1.00 % 2.00 % 4 16
71

REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage
TOP bar DIA MM

1 479.95 0.833 1 38.00 mm 1.00 % 2.00 % 2 12


1 1134.5 0.833 1 38.00 mm 1.00 % 2.00 % 3 16

REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage MAIN BAR

NO OF bott DIA MM
bar long
1 9.25 8.04 1.33 75.00 mm 1.00 % 2.00 % 12 16
1 24.15 0.82 5.91 45.00 mm 1.00 % 2.00 % 70 10
1 22.67 0.67 41 20.00 mm 1.00 % 2.00 % 70 10
3

1 13.24 10.18 1.5 75.00 mm 1.00 % 2.00 % 54 12


1 35.58 0.82 5.91 45.00 mm 1.00 % 2.00 % 94 10
1 33.77 0.67 41 20.00 mm 1.00 % 2.00 % 94 10
3

REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage MAIN BAR

corner bar DIA MM

1 4.5 0.83 1 38.00 mm 1.00 % 2.00 % 4 16


1 17.1 4.5 0.5 25.00 mm 1.00 % 2.00 % 5 16
6.00 0.83 4.5 0.50 25.00 mm 1.00 % 2.00 %
1 19.5 4.5 0.5 25.00 mm 1.00 % 2.00 % 4 16
6.50 0.83 4.5 0.50 25.00 mm 1.00 % 2.00 %
1 4.5 0.83 1 38.00 mm 1.00 % 2.00 % 4 16
1 5.6088 4.9036 0.5 25.00 mm 1.00 % 2.00 % 5 16
4.00 1.00 4.9036 0.52 25.00 mm 1.00 % 2.00 %
1 22.22528 7.59156 0.67 25.00 mm 1.00 % 2.00 % 7 20
5.00 1.00 7.59156 0.52
1 6.396 4.9036 0.50 25.00 mm 1.00 % 2.00 % 5 16
2.00 1.00 4.9036 0.52

REINFORCEMENT
rebar_length
rebar_width length1 length2
47 30 1387.5 877.2
45 30 1078.92 701.76
45 28 251.748 151.928
47 28 259 151.928
47 33 305.25 212.289
45 31 278.721 190.867
47 94 869.5 1750.75
47 58 536.5 668.392
45 33 293.04 212.289
45 30 532.8 350.88
55 30 327.9 175.44
51 30 303.54 175.44
48 28 263.284 151.928
45 18 158.58 62.28
47 13 120.25 32.214
47 8 74 11.856
45 5 44.955 4.815
21 33 137.61 212.289
13 30 77.22 175.44
subtotal 7300.318 6269.985

total 13570.3 m
T Weight of rod 12058.9 KG
0.95 %

REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod
wastage wastage MAIN BAR

corner bar DIA MM

46 0.833 0.677 14 38.00 mm 1.00 % 2.00 % 4 16


46 0.833 0.677 14 38.00 mm 1.00 % 2.00 % 4 16
46 0.833 0.677 17 38.00 mm 1.00 % 2.00 % 4 16
138

REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod
wastage wastage
corner bar DIA MM

1 1033.77 0.666 1 38.00 mm 1.00 % 2.00 % 4 12


1 486.9 0.666 1 38.00 mm 1.00 % 2.00 % 4 12
0 0 0 0 38.00 mm 1.00 % 2.00 % 0 0
2

RCC REINFORCEMENT
Clear cover casting rod BOTTOM LONG BAR BOTTOM SHORT BAR
Width (ft) T (ft) DIA MM spacing DIA MM spacing
wastage wastage mm c/c mm c/c
131.04 0.416 20.00 mm 1.00 % 2.00 % 20 150 20 150
0.82 0.416 20.00 mm 1.00 % 2.00 % 20 150 20 150
20.11 0.416 20.00 mm 1.00 % 2.00 % 16 175 16 175
11.11 0.416 20.00 mm 1.00 % 2.00 % 16 150 16 150
6.46 0.416 20.00 mm 1.00 % 2.00 % 16 125 16 125
0 0 20.00 mm 1.00 % 2.00 % 16 200 16 200

TOTAL
VOLUME OF STEEL RATIO
STEEL (m3)

0.97 0.59

0.98 0.56

0.98 0.56
2.93 0.57

AFTAB THREE FLIGHT STAIR


CONCRETE VOLUME wooden shuttering for stair
WEIGHT X-AREA NOS.OF VOL OF VOLUME TOTAL VOL Area Area of Shuttering
bottomsurf
OFONE STEPS STAIR CON. OF FLIGHT OF stair two for stair
ace & riser
KG. MM^2 STEPS CFT. CFT CON.CFT. SFT sides sft beam sft

35.60
65.56
18.35
24.60 68700.00 8.00 32.95 16.82 49.77 120.24 37.64 16.45
10.72
8.81
163.64306

77.48
182.49 76200.00 10.00 45.68 40.72 86.41 130.12 41.02
38.52
0.00
298.48172

43.97
79.09 68700.00 4.00 16.48 30.08 46.56 57.26 23.59
16.34
139.40293
601.5277 TOTAL IN CFT 182.7 TOTAL IN SFT

AFTAB TWO FLIGHT STAIR


CONCRETE VOLUME wooden shuttering for stair
WEIGHT X-AREA NOS.OF VOL OF VOLUME TOTAL VOL Area of Area of Shuttering
bottom
OFONE STEPS STAIR CON. OF FLIGHT OF stair two for stair
surface &
KG. MM^2 STEPS CFT. CFT CON.CFT. riser sft sides beam sft

36.64
91.31 57404 11 37.79 21.73 59.52 130.12 53.70 16.45
19.23
10.72
10.41
168.32187

45.02 59182 12 42.50 37.05649 79.56 132.12 19.11


147.71
16.55
0.00
0.00

209.28206
345.61534 TOTAL IN CFT 139.1 TOTAL IN SFT
REINFORCEMENT
BOTTOM SHORT BAR TOP LONG BAR TOP SHORT BAR SIDE BAR BOTTOM LONG BAR

DIA MM spacing DIA spacing DIA MM spacing DIA MM all-around DIA MM


mm c/c MM mm c/c mm c/c no
12 173 12 150 12 173 10 3 20
20 150 0 100 0 100 0 3
16 175 0 100 0 100 0 3
16 150 0 100 0 100 0 3
16 125 0 100 0 100 0 3
16 200 0 100 0 100 0 3
16 200 0 100 0 100 0 3
16 200 0 100 0 100 0 3
16 314 22 100 0 100 0 3 20
16 236 16 200 0 100 0 3 20
16 282 16 150 0 100 0 3 20

t long s DIA MM t short s b DIA MM


L m anch/lapp m b L m anch/lapp m L m
1.12804878049 0.304878 4 20 1.128049 0.304878 4 20 1.128049
1.12804878049 0.304878 4 20 1.128049 0.304878 4 20 1.128049
1.12804878049 0.304878 4 20 1.128049 0.304878 2 20 1.128049
1.12804878049 0.304878 2 20 1.128049 0.304878 2 20 1.128049
1.12804878049 0.304878 6 20 1.128049 0.304878 0 0 1.128049
1.12804878049 0.304878 8 20 1.128049 0.304878 2 20 1.128049
1.12804878049 0.304878 4 20 1.128049 0.304878 2 20 1.128049
1.06707317073 0.304878 2 20 1.067073 0.304878 2 20 1.067073
1.12804878049 0.304878 0 0 1.128049 0.304878 0 0 1.128049
MAIN BAR
EXTRA DIA MM BOTT BAR DIA MM
L m anch/lapp m TOP L m anch/lapp m L m
148.405 8.16 1 16 98.94 0.00 2 16 148.405
148.405 10.88 0 16 98.94 0.00 3 16 148.405

top long DIA MM bott&top DIA MM


L m anch/lapp m bar L m anch/lapp m short bar L m
2.67 0 12 16 2.67 0 28 12 2.29878
1.80 0 20 10 7.36 0 20 12 1.801829
12.50 31.5 20 10 6.91 3.04878 20 12 12.5

2.95 0 42 16 3.89 0 28 0 2.950561


1.80 0 20 10 10.85 0 24 12 1.801829
12.50 42.3 20 10 10.30 3.04878 24 12 12.5

t long s DIA MM t short s b DIA MM


L m anch/lapp m b L m anch/lapp m L m

1.37195121951 0 0 0 0 0 0
13.48 0 5 16 5.46 0 10 12 1
0 0
7.02256 0 4 16 6.59 0 8 12 0.95
1.37195121951 0 0 0 0 0 0 0 0
4.82 0 5 16 5.012 0 10 12 0.96

6.82 0 7 20 6.83 0 16 12 0.96

5.21 0 5 16 5.21 0 10 12 0.96

t long s DIA MM t short s b DIA MM


L m anch/lapp m b L m anch/lapp m L m
4.26829268293 0.64 0 0 4.268293 0 0 0 4.268293
4.26829268293 0.64 0 0 4.268293 0 0 0 4.268293
5.18292682927 0.8 0 0 5.182927 0 0 0 5.182927

MAIN BAR
t long s DIA MM t short s b DIA MM
L m anch/lapp m b L m anch/lapp m L m
315.173780488 18.91 0 0 0.304878 0.00 0 0 0.304878
148.445121951 8.91 0 0 0.304878 0.00 0 0 0.304878
0 0.00 0 0 0 0.00 0 0 0

TOP LONG BAR TOP SHORT BAR SIDE BAR BOTTOM LONG BAR BOTTOM SHORT BAR

DIA MM spacing DIA spacing DIA MM all-around DIA MM ONE ROD DIA MM
mm c/c MM mm c/c no LENGTH M
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
huttering for stair
TOTAL shuttering

sft.

174.33

171.13

80.85

426.3211

huttering for stair


TOTAL shuttering

sft.

200.27

151.23
351.51
BOTTOM LONG BAR BOTTOM SHORT BAR TOP LONG BAR TOP SHORT BAR

ONE ROD DIA MM ONE ROD DIA MM ONE ROD DIA MM ONE ROD
LENGTH M LENGTH M LENGTH M LENGTH M
0.9 12 0.9 12 0.9 12 0.9

1.5 22 -0.992
1.47 16 -0.75
1.7 16 -1.5

STIRRUPS set1 set2 set3


DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos
0.304878 250 6.00 10 1.78 1 10 1.20 1 10
0.304878 250 6.00 10 1.67 1 10 1.10 1 10
0.304878 250 6.00 10 1.67 1 10 1.10 1 10
0.304878 250 6.00 10 1.87 1 10 0.71 1 10
0.304878 250 6.00 10 1.72 1 10 1.21 1 10
0.304878 250 6.00 10 1.72 1 10 1.32 1 10
0.304878 250 6.00 10 1.31 1 10 0.91 1 10
0.304878 250 6.00 10 1.06 1 10 0.61 1 10
0.304878 250 6.00 10 0.96 1 10 0.45 1 10
STIRRUPS
set1
DIA MM length m nos
anch/lapp m mm/cc str spacing nos
10.88 175 838.00 10 1.12 1
10.88 200 1731.00 10 1.12 1

STIRRUPS set1 set2 set3


DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos
0 250 3.00 0 10.09 1 0 8.56 1 0
0 250 9.00 0 15.01 1 0 12.37 1 0
10.8 250 52.00 0 14.22 1 0 11.72 1 0

0 250 3.00 0 13.82 1 0 13.12 1 0


0 250 9.00 0 21.98 1 0 18.07 1 0
12.96 250 52.00 0 20.99 1 0 17.26 1 0

STIRRUPS set1 set2 set3


DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos

0 250 7.00 10 0.96 1 0 0.00 1 0


0 250 55.00 10 1.37 1 0 7.22 1 0
250 44.00 10 1.37 1
0 250 49.00 10 1.37 1 0 6.72 1 0
0 250 7.00 10 0.96 1 0 -2.09 1 0
0 250 29.00 10 1.50 1 0 4.46 1 0

0 150 73.00 10 2.31 1 0 12.15 1 0

0 250 40.00 10 1.50 1 0 4.67 1 0

STIRRUPS set1 set2 set3


DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos
0 250 19.00 10 0.76 1 0 0.06 1 0
0 250 19.00 10 0.76 1 0 0.06 1 0
0 250 22.00 10 0.76 1 0 0.06 1 0

STIRRUPS
set1 set2 set3
DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos
0.00 250 1262.00 10 0.86 1 0 0.86 0 0
0.00 250 595.00 10 0.86 1 0 0.86 0 0
0.00 250 2.00 0 -0.16 1 0 -0.16 0 0

BOTTOM SHORT BAR TOP LONG BAR TOP SHORT BAR

ONE ROD DIA MM ONE ROD DIA MM ONE ROD


LENGTH M LENGTH M LENGTH M
set3
length m nos

1.27 1
1.24 1
1.02 0
1.32 0
0.62 0
1.17 0
0.76 0
0.61 0
-0.15 0
set3
length m nos

9.47 1
14.95 1
14.16 1

13.04 1
21.93 1
20.94 1

set3
length m nos

0.00 1
12.24 1

13.53 1
2.39 1
5.40 1

17.12 1

5.88 1

set3
length m nos

0.25 1
0.25 1
0.25 1

set3
length m nos

0.86 0
0.86 0
-0.16 0
RHD STANDARD
ANALYSIS OF CAST IN-SITU PILES
:
Selected Office : Chittagong
Item Type : Foundation Works

Item Name : Bored cast in place piles dia = 400 mm

Unit of Estimation : Lin. Metre

Quantity for Estimation : 25

Breakdown of Input Items : (All prices are in Taka)

Specification Item Components


Input Items Unit Of Qty for Price for Qty for Price for
Item Name Unit Price
Estimation Estimation Estim. Qty Estimation Estim. Qty

Item Type : Equipment

Bored pile equipment (750 mm) day 1 4200 1 4,200.00 168.00

Concrete Mixer (7/5) day 1 750 1 750.00 30.00

Item Type : Labour

foreman day 1 300 1 300.00 12.00

masons day 1 200 6 1,200.00 48.00

semi-skilled labourer day 1 120 8 960.00 38.40

Item Type : Material

Bentonite (50kg) bag 1 500 3 1,500.00 60.00

Cement OPC tonne 1 7,440.00 1.2 8,928.00 357.12

Coarse Sand FM>2.5 cu. metre 1 990 1.28 1,267.20 50.69

crushed boulder/gravel aggregate cu. metre 1 3,670.00 2.57 9,431.90 377.28


<25mm
Total Price of Specification Item : 28537.10

Basic Unit Price of Specification Item : 1141.48


Plus Profit at 10.00% : 114.15

Sub-Total : 1255.63

Plus Tax & VAT at 9.2896% : 116.64

Total Unit Price of Specification Item : 1372.28


tk 418.38 /ft
6 BRICKS AND SCREEN BLOCKS
1st class/Picked jhama bricks Tk 5000.00 Per % 0 Nos.
Automatic Machine Made 1st class Bricks Tk 5250.00 Per % 0 Nos.
10 holes machine made ceramic brick Tk 9750.00 Per % 0 Nos.
9.5" x 4.5" x 2.75" size machine made solid klinker facing bricks Tk 9000.00 Per % 0 Nos.
9.5" x 4.5" x 2.75" size 10 hole machine made Rock-face/textured klinker Tk 10600.00 Per % 0 Nos.
facing bricks

9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing Tk 9700.00 Per % 0 Nos.
bricks

200 x 100 x 50 mm/8" x 4" x 2" machine made hard pressed klinker facing Tk 10625.00 Per % 0 Nos.
bricks

200 x 50 x 50 mm/8" x 2" x 2" machine made klinker facing strips Tk 7000.00 Per % 0 Nos.

200 x 62 x 50 mm/8" x 2.5" x 2" machine made klinker red strips Tk 7750.00 Per % 0 Nos.

4" x 4" x 4" fancy screen block Tk 13200.00 Per % 0 Nos.

6.5" x 4.75" x 4" fancy screen block Tk 16500.00 Per % 0 Nos,

6.5" x 6' x 4" fancy screen block Tk 21400.00 Per % 0 Nos,

190 x 190 mm size glass bricks Tk 250.00 each


7 CEMENT
Ordinaiy Portland Cement, ASTM C-150 Type-I / BDS-EN -197-1-CEM-1 Tk 396.00 Per bag
(32.5 - 42.5): 50 kg bag
Portland Composite Cement CEM-II/A - M (6-20% constituents other Tk 370.00 Per bag
than clinker): 50 kg bag
White Cement Tk 18.00 Per kg
STONE / BOULDER / MOSAIC CHIPS, BITUMEN ADMIXTURE
8
MEMBRANE
Uncruhed boulder
Tk 7000.00 Per % cit.

19mm (3/4") down crushed stone chips Tk 7500.00 Per % oft.


12 mm(1/2") down stone chips Tk 7500.00 Per % cft.
stone shingles Tk 5500.00 Per % cft.
Pea-gravel Tk 4000.00 Per % cft.
Slaked lime Tk 15.00 Per kg
1 Surki from 1st class brick Tk 40.00 Per cft.
Pakistan origin (onix) mosaic chips Tk 15.00 Per kg
Indian origin (deradun) mosaic chips Tk 10.00 Per kg
Pumice stone for finishing mosaic work Tk 22.00 each
Minar stone for finishing mosaic work Tk 290.00 each
Color pigment Tk 45.00 Per lbs
20 mm x 50 mm glass strip Tk 5.00 Per ft
80/20 Bitumen for road work Tk 40000.00 Per M, ton
Water-proofing PVC membrane Tk 475.00 Per sqm.
Primer for laying PVC membrane on wall Tk 450.00 Per litre
Water reducing admixture in concrete: Type - A Tk 146.25 Per litre
Retarding admixture in concrete. Type - B t Tk 151.50 Per litre
Accelerating admixture in concrete: Type - C Tk 150.00 Per litre
Water-reducing and retarding admixture in concrete: Type - D Tk 143.00 Per litre
Water-reducing and accelerating admixture in concrete-, Type - E Tk 157.00 Per litre
Water-reducing high range admixture in concrete: Type - F Tk 154.00 Per litre
Water-reducing high range retarding admixture in concrete: Type - G Tk 140.00 Per litre
Fibre mesh Tk 580.00 Per kg
9 EARTH/SAND
Royalty of earth Tk 300.00 Per % 0 cft.
Royalty of sand Tk 5000.00 Per % 0 cft.
Royalty of turf Tk 6.00 Per % A
Sand (F.M. 0.8) Tk 750.00 Per % cft.
Sand (F.M. 1.2) Tk 1300.00 Per % cft.
Sand (F.M. 2.2) Tk 2200.00 Per % cft.
10 STEEL
40 grade deformed M.S. rod J Tk 64000.00 Per M. ton
60 grade deformed M.S. rod Tk 67000.00 Per M. ton ✓
M.S sheet/plate Tk 85000.00 Per M. ton
M.S. angle, T and Z-section, Channel etc. Per M. ton
Tk 65000.00

M.S. plain bar and F.I. bar (non-structural use) Tk 59000.00 Per M. ton
Solid square bar Tk 64000.00 Per M. ton
0.45 mm thick C.I. sheet:/ G.P. sheet Tk 79000.00 Per M. ton
0.45 mm thick colored C.I. sheet: Tk 100000.00 Per M. ton
0.27 mm thick 6'-0" x 18" ridging: Tk 400.00 Per pc.
0.27 mm thick 6'-0" x 18" colored ridging: Tk 450.00 Per pc.
11 TIMBER/BOARD/TIMBER PRODUCT
Garjan/Jam/local Sal Tk 1300.00 Per cft.
Mehgani Tk 1350.00 Per cft.
Silkarai/Chikrashi Tk 1800.00 Per cft.
Teak-Chambal Tk 2500.00 Per cft.
Chittagong teak Tk 3600.00 Per cft.
Kathal Tk 1500.00 Percft.
Gamari Tk 1500.00 Per cft.
Chapalish Tk 1600.00 Per cft.
Timber for form work Tk 350.00 Per cft,
Bamboo Tk 6.00 Per rft.
Shal ballah (avg. dia 6") for driving Tk 50.00 Per rft.
Burma teak veneered flush door shutter Tk 252.00 Per sft.
Champ veneered flush door shutter Tk 174.00 Per sft.
Chapalish veneered flush door shutter Tk 174.00 Per sft.
Garjan veneered flush door shutter Tk 152.00 Per sft.
12 mm thick Plain Particle board Tk 40.00 Per sft.
Melamine board (8 mm thick): 8' -0" x 4'-0" size Tk 1800.00 Per pc.
9 mm thick gypsum board Tk 20.00 Per sft.
9 mm thick perforated gypsum board Tk 23.00 Per sft.
12 mm thick laminated vinyl board Tk 31.00 Per A,
9 mm thick B.T. veneered board Tk 84.00 Per sit.
Burma teak Tk 3750.00 Per cft.
50 mm thick glass wool Tk 173.00 Per sft.
Rubber gum Tk 500.00 Per kg.
PVC water stopper Tk 175.00 Per rft.
12 PROPS PIPES I-SECTION BOX CHANNEL FOR CONCRETING WORK
Bamboo prop in/c top supports Tk 80.00 each
Salballah prop in/c top supports Tk 625.00 each
50 mrn/2"dia M.S. pipe Tk 146.00 Per rft.
38 mm/1.5" dia M.S. pipe Tk 110.00 Per rft.
50 mm/2" dia G.I. pipe Tk 165.00 Per rft.
38 mm/1.5" dia G.I. pipe Tk 120.00 Per rft.
19 mm/3/4" dia G.I. pipe Tk 50.00 Per rft.
13 mm/1/2" dia G.I. pipe Tk 30.00 Per rft.
Adjustable mechanism in/c top and bottom plate Tk 450.00 Per set
I-section joist to support inclined prop Tk 115.00 Per rft.
4" x 2" M.S. box channel with 1/8" thick ms sheet Tk 125.00 Per rft.
Steel prop with adjustable rnechanism in/c top & bottom plate Tk 2235.00 Per set
Turn-buckle ink tie rod Tk 300.00 Per set
13 GLAZED/MARBLE[TERAZZO TILES
18 mm thick marble stone, Black/white (Indian) Tk 290.00 Per sft.
16 mm thick marble stone, Black/white (Indian) Tk 260.00 Per MI.
12 mm thick marble stone, Black/white (Indian) Tk 240.00 Per sft.
18 mm thick colored/ grey marble stone (Indian) Tk 300.00 Per sft.
16 mm thick colored/ grey marble stone (Indian) Tk 270.00 Per sft.
12 mm thick colored/ grey marble stone (Indian) Tk 250.00 Per sft.
18 mm thick colored/ grey marble stone (Italian) Tk 460.00 Per sft.
White wall tiles of different sizes ,/ Tk 42.00 Per sft.
Colored wall tiles of different sizes Tk 44.00 Per sft.
Special design colored wall tiles of different sizes Tk 46.00 Per sft.
GP (Glazed homogeneous) 300x300 mm floor tiles Tk 48.00 Per sft.
GP (Glazed homogeneous) 400x400 mm floor tiles Tk 52.00 Per sft.
GP (Mirror polished) 300 x 300 mm floor tiles Tk 100.00 Per sft.
GP (Mirror polished) 400 x 400 mm floor tiles Tk 111.00 Per sft.
GP (Mirror polished) 600 x 600 mm floor tiles Tk 130.00 Per sft.
GP 300 x 300 mm stair tiles Tk 52.00 Per sft.
unglazed homogeneous Floor Tiles 300 x 300 mm Tk 51.00 Per sft.
unglazed homogeneous Floor Tiles 400 x 400 mm Tk 56.00 Per sft.
pasting tiles adhesive Tk 14.00 Per kg.
tiles grout / joint filler Tk 80.00 Per kg.
acid stone Tk 300.00 each
water proofing paper 12 size Tk 15.00 each
water proofing paper 320 size Tk 18.00 each
ADDITIONAL COST CHART
Sheet1
1. Saline zone, to use concrete of min f'c = 25 mpa 1.00 % of PLAR

2. Wind (other than coastal area) & earth-quake 2.00 % of PLAR


resisting structure : to use concrete of min f'c = 21 mpa

3. Coastal area : affected by cyclone & water 3.00 % of PLAR


concrete of min f'c = 25 mpa

4. Roof top RCC parapet : Tk 1800.00 per sqm

5. Roof-top R.C.C. water tank in/c beams & supports etc. Tk 100.00 per gallon

6. Internal sanitary and water supply


(i) Residential building
Standard Tk 500.00 per sqm
Super Tk 750.00 per sqm
Superior Tk 1100.00 per sqm
(ii) Non-residential building
Standard Tk 400.00 per sqm
Super Tk 550.00 per sqm
Superior Tk 850.00 per sqm
7. Internal electrification
(i) Residential building
Standard Tk 1100.00 per sqm
Super Tk 1300.00 per sqm
Superior Tk 1550.00 per sqm

(ii) Non-residential building


Standard Tk 800.00 per sqm
Super Tk 1000.00 per sqm
Superior Tk 1200.00 per sqm
8. Gas Connection
(1) Ground floor: Tk 250.00 per sqm
(ii) Other floors Tk 100.00 per sqm
9. External Water Supply:
(i) Underground water reservoir : Tk 50.00 per gallon
(ii) Distribution line, water pump, pump house,
WASH/ Municipal charge as per requirement. estimate Tk 0.00
10. External Electrification:
(i) Sub-station building estimate Tk 0.00
(ii) Sub-station Equipment/ Transformer estimate Tk 0.00
(iii) Pump & motor set including installation estimate Tk 0.00
(iv) H.T./LT Line estimate Tk 0.00
(v) PUB / DESA / REB charge estimate Tk 0.00
(vi) Stand by Power & Source estimate Tk 0.00
(vii) Earthing System estimate Tk 0.00
(viii) Over head Transmission estimate Tk 0.00
(ix) Under ground Cable Laying estimate Tk 0.00
(x) Compound light, wiring system & other safety system estimate Tk 0.00

11. Boundary Wall


(i) Boundary wall 125 mm thick with 2--!;0 x 250 min brick pillar:
Tk 3160.00 Per rm

Construction of 125 mm thick boundar wall with 250mmx250mm


y

size brick pillar @ 2.44 meter c/c, of height 1.52 meter above G.L and
0.76 m below G.L. and R.C.C. coping of 75 mm thick and 375 mm
width, 12 mm thick plaster (1:6) in both sides of the wall inc

(ii) Boundary wall in R.C.C. frame :


Tk 4880.00 Per rm

Construction of R.C.C. boundary wall of height 1.52 meter above G.L.


and one meter below G.L. with column 250 mm x 250 mm size and tie
beam 250 x 250 mm at ground level, 75 mm thick
and 375 mm width R.C.C. coping and 125 mm (1:4) brick work in
between th

(iii) Barbed wire fencing over Boundary wall


Tk 585.00 Per rm

Supplying , fitting and fixing 12BWG barbed wire (2 ply. 4 points )


in fencing work @ 150 mm in both horizontally and vertically,
supported by 38 x 38 x 6 mm M.S. angle post (300 mm embedded in
R.C.C. or in brick work with a cement concrete base of 75 x 7

12. Road Work :


(i) R.C.C. Road:

Construction of R.C.C. road with 250 mm thick guide wall of height


0.30 meter, 150 mm thick R.C.C. work over one layer 1st class brick
Tk 1775.00 Per sqm
'T flat soling and polythene sheet including the cost of reinforcement
10mm dia MS rod 175 mm c/c in both direction.

(ii) Bituminous
Carpeting Road
Tk 1472.00 Per rm

Construction of 38 mm thick compacted bituminous carpeting


over 150 min thick sand surface with 75 mm thick end edging,
62 mm - 37 mm size brick bats khoa consolidation and compacted
water bound macadam of 150 mm thickness, providing tack coat
07.32 kg of

13. Semi Permanent Structure :


Plinth area rates for standard semi-permanent building with C .I.
sheet roofing on metal truss, supported on brick pillars & walls in
1:4 cement sand mortar having 75 mm thick D.P.C., in/c earth work,
back filling in foundat

Tk. 7165.00 per sqm

14. Structure constructed departmentally :


Any construction work executed departmentally, 18% of the Total
18 %
Cost to be deducted from the calculated gross cost.
ITEM
DESCRIPTION QUANTITY UNIT RATE
No
(in Taka)
1 RCC cast-in-situ piling works : Approximately 85
numbers of Piles of 500mm dia, 50' long, 1:1.5:3
mixproportion of cement , sand (FM 2.5) and 20mm -
8mm graded stone chips. The works include site
cleaning,providing labour shed,cement godown,material
stac 1326.22 RM 1925

2 40 grade Reinforcement cost in/c supplying,


fitting ,fixing, bending, binding etc. all complete in piles 23.00 mt 62000
excluding concrete cost
3 Pile head breaking in/c removal of devrishes to a safe
9.00 m3 1650
distance as per instruction.
4 Site cleaning, layout giving & mobilization 456.04 m2 15

GT =
AMOUNT

(in Taka)

2,552,972.56

1,426,000.00

14,850.00
6,840.61

4,000,663 Tk 920 /ft


SL Description of works Quantity Unit Rate/Unit Amount
No. (In Taka) (In Taka)
01 LAYOUT WITH PREPARATION
Site preparation, Cleaning, Layout for
pile and foundation trenches in/c
necessary of tools, plants
etc.Theodolite/Levelling instrument
wherever neceassary for estabilishing
centre line/alignment of column as per
drawing and specification of Kreativ
Build

556.32 sqm 22.00 12239.04


02 EARTH WORK IN EXCAVATION
Earth work in excavation of all kinds of
soils of Foundation trenches including
leveling. Ramming and preparing the
base, bailing out of water if necessary,
providing center line and bench mark
pillers, removing the spoils etc. to a
lead not exceeding 12

a) Up to 2.2 M 1356.88 cum 120.00 162825.28


03 EARTH FILLING
Earth filling in foundation trenches and
plinth in 150 mm layer with earth
avail-able within 12m of the building
site, watering, leveling and
consolidation each layer up to finished
level as per design direction of the
Engineer-in-charge.
169.61 cum 87.00 14756.05
04 SAND FILLING
Sand filling in floor& plinth with fine
local sand having minimum F. M.-.80
in 150 mm layers including leveling,
watering and consolidating each layer
up to finished level as per direction of
the Engineer-in-charge
104.31 cum 460.00 47982.58
05 POLYTHENE SHEET

Page 156 of 180


SL Description of works Quantity Unit Rate/Unit Amount
No. (In Taka) (In Taka)
Providing single layer polythene sheet
below cement concrete work or where
necessary with required overlapping as
per direction of the Engineer-in-charge
650.00 sqm 20.00 13000.00

06 BRICK FLAT SOLING


Providing single layer brick flat soling
as per design, drawing & direction of
the Engineer-in-charge. 500.00 sqm 255.00 127500.00
07 LEAN CEMENT CONCREATE
Providing 1:3:6 mass concrete in floor
with cement, sand(FM-1.2) and picked
jhama chips inciuding breaking chips
etc. as per design, drawing & direction
of the Engineer-in-charge.
40.00 Cum 5025.00 201000.00
08 R.C.C WORK (1:2:4)
Reinforced cement concrete work with
proportion 1:2:4 made of Portland
cement (Made in Bangladesh) of 1 part,
50% Sylhet sand (F.M-2.5) & 50%
local sand (F.M-1.5) of 2 parts and 20
mm down graded picked jhama brick
chips of 4 parts. Screening and
watering

a) In pile cap 52.00 cum 6,750.00 351000.00


b) In short Column 13.00 cum 8,380.00 108940.00
c) In Grade Beam 30.00 cum 8,350.00 250500.00
d) In ground Floor 85.00 cum 6,200.00 527000.00
e) lift core wall 7.00 cum 8,380.00 58660.00
f) In basement 85.00 cum 6,200.00 527000.00
g) In retaining wall 52.00 cum 8,380.00 435760.00
09 DEFORMED BAR

Page 157 of 180


SL Description of works Quantity Unit Rate/Unit Amount
No. (In Taka) (In Taka)
Supplying, fabrication and fixing of
deformed bar reinforcement to detail as
per design in concrete in accordance
with BSTI standard including
straightening, cleaning the rust if any,
bending and binding in position
including supply of GI wires
etc.comple
a) 40 grade (fy-276 M pa) 38.40 Ton 62000.00 2380936.40

10 250 mm THICK BRICK WORK


250 mm thick brick work with 1st class
bricks in cement mortar (1:6) interstices
with mortar, racking out joints, cleaning
and soaking the bricks before use, curing
for at least 7 days in ground floor etc.
complete as per direction of the Engineer-
in-char 1.00 cum 4,450.00 4450.00
11 Minimum 12 mm thick cement plaster
work (1:4) in wall,column,GB,
without neat cement finishing
including cleaning and watering to
surface, before application and curing
at least for 7 days etc. complete as per
direction of the Engineer in-charge. 500.00 sqm 149.00 74500.00
12 PLASTER WITH N.C.F : Minimum
12 mm thick
Minimum 12 cement
mm thickplaster workplaster
cement (1:4)
in wall
work (1:4)with neat with
in wall cementneatfinishing
cement
including cleaning and watering
finishing including cleaning and to
surface, before application and curing
watering to surface, before application
at least
and for 7 atdays
curing etc.for
least complete
7 daysas etc.
per
direction of the Engineer in-charge.
complete as per direction of the
Engineer in-charge. 730.00 sqm 156.00 113880.00
13 RENTED CENTERING & SHUTTERING

COST WITH LABOUR COST ,WOODEN 510.00 sqm 29.00 14790.00


Total = 5426719

Page 158 of 180


SL Description of works Quantity Unit
No.

01 R.C.C WORK (1:2:4)


Reinforced cement concrete work with proportion 1:2:4 made
of Portland cement (Made in Bangladesh) of 1 part, 50%
Sylhet sand (F.M-2.5) & 50% local sand (F.M-1.5) of 2 parts
and 20 mm down graded picked jhama brick chips of 4 parts.
Screening and watering

a) In Column 1.00 cum


b) In 1ST Floor 85.00 cum
c) In Lintel/drop wall 5.00 cum
d) In RCC Stair 3.00 cum
e) lift core 7.00 cum
02 DEFORMED BAR
Supplying, fabrication and fixing of deformed bar

reinforcement to detail as per design in concrete in accordance

with BSTI standard including straightening, cleaning the rust if

any, bending and binding in position including supply of GI

wires etc.comple
a) 40 grade (fy-276 M pa) 10.00 Ton
03 250 mm THICK BRICK WORK
250 mm thick brick work with 1st class bricks in cement
mortar (1:6) interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for at least 7
days in ground floor etc. complete as per direction of the
Engineer-in-char 1.00 cum
04 125 mm THICK BRICK WORK with 1st class bricks in cement

mortar (1:4) interstices with mortar, racking out joints, cleaning and

soaking the bricks before use, curing for at least 7 days in ground

floor etc. complete as per direction of the Engineer-in-char 800.00 sqm


04 PLASTER WITH N.C.F

Page 159 of 180


SL Description of works Quantity Unit
No.

Minimum 12 mm thick cement plaster work (1:4) in wall with

neat cement finishing including cleaning and watering to

surface, before application and curing at least for 7 days etc.

complete as per direction of the Engineer in-charge. 10.00 sqm

05 CEMENT PLASTER (12 mm th)


Minimum 12 mm thick cement plaster work (1:6) in all brick

wall surface cleaning and watering to surface, before

application and curing at least for 7 days etc. complete as per

direction of the Engineer in-charge. 2230.48 sqm

06 PAINTING WORKS
Painting work with Plastic paint (Berger/Elite) of approved

colour to inside of wall, Enamel pain of steel surface and

Cement painting of outside of wall etc. where necessary 2

coats over a coat of priming including preparing the surface

with sand paper 1931.69 sqm


07a WOODEN DOOR FRAME :Supplying and making door
frames with seasoned wood of required size including painting
two coats of coalter to the surface in contact with wall, fitted
and fixed in position and mending good the damages if any
(All sizes of wood are fi
1. Teak chamble
1.00 cum

Page 160 of 180


SL Description of works Quantity Unit
No.

07b WOODEN DOOR SHUTTER :Supplying, fitting and fixing

38mm thick well matured (minimum 10 inch. wide plunk)

solid wood door shutter having top rail style of sections

100mm x38mm lock rail 125mm x38mm and bottom rail

225mmx38mm closed joints and provided with


1. Teak chamble
60.00 sqm
08 WINDOW GRILL
Supplying, fabrication and fixing to window grills of any

design made with 20 mm x 3 mm F.I. bar in/c. necessary

fabrication, welding etc. all complete as per direction of the

Engineer-in-charge. 75.00 sqm


09 Supplying fitting and fixing of 8"x2.5"x1" THICK bricks
cladding 1.00 sqm
10 THAI ALUM SLIDING WINDOW
Supplying fitting and fixing of Aluminium Sliding windows

Bronze colour U.S. Architectural Aluminium Manufactuer’s

Association (AAMA) standard specification having 1.5 mm

thick outer bottom (size 75.50 mm, 32 mm), 1.5 mm thick

outer top (size 75.50 mm, 1

Page 161 of 180


SL Description of works Quantity Unit
No.

of all Aluminium members will be anodized to Aluminium

Bronze/Silver colour with a coat not less than 15 micrones in

thickness and density of 4 mg per square cm etc. including all

accessories like handle, locks (Japan), auto-closure(USA),

stopper, flush, 75.00 sqm


11

WALL TILES WORK: Supplying, fitting and fixing


homogeneous quartz/ embossed WALL tiles (200X200) RAK
or equivalent(local made) on 20 mm thick cement mortar (1:3)
base and raking out the joints with white cement including
cutting and laying the tiles in pr 95.00 sqm
12 FLOOR TILES WORK N: Supplying, fitting and fixing

homogeneous quartz/ embossed floor tiles (300X300) RAK or

equivalent(local made) on 20 mm thick cement mortar (1:3)

base and raking out the joints with white cement including

cutting and laying the tiles i 510.00 sqm


13 Rented Centering & Shuttering Cost With Labour
Cost ,Wooden 560.00 sqm

Page 162 of 180


Rate/Unit Amount
(In Taka) (In Taka)

8,280.00 8280.00
7,500.00 637500.00
8,350.00 41750.00
8,580.00 25740.00
8,580.00 60060.00

63000.00 630000.00

4,450.00 4450.00

580.00 464000.00

Page 163 of 180


Rate/Unit Amount
(In Taka) (In Taka)

156.00 1560.00

140.00 312267.66

145.00 280095.27

137036.00 137036.00

Page 164 of 180


Rate/Unit Amount
(In Taka) (In Taka)

6600.00 396000.00

1076.00 80700.00

1090.00 1090.00

Page 165 of 180


Rate/Unit Amount
(In Taka) (In Taka)

2591.00 194325.00

960.00 91200.00

940.00 479400.00

29.00 16240.00

Total = 3861694

Page 166 of 180


SL Description of works Quantity Unit
No.

01 R.C.C WORK (1:2:4)


Reinforced cement concrete work with proportion 1:2:4 made
of Portland cement (Made in Bangladesh) of 1 part, 50%
Sylhet sand (F.M-2.5) & 50% local sand (F.M-1.5) of 2 parts
and 20 mm down graded picked jhama brick chips of 4 parts.
Screening and watering

a) In Column 1.00 cum


b) In 1ST Floor 85.00 cum
c) In Lintel/drop wall 5.00 cum
d) In RCC Stair 3.00 cum
e) lift core 7.00 cum
02 DEFORMED BAR
Supplying, fabrication and fixing of deformed bar

reinforcement to detail as per design in concrete in accordance

with BSTI standard including straightening, cleaning the rust if

any, bending and binding in position including supply of GI

wires etc.comple
a) 40 grade (fy-276 M pa) 10.15 Ton
03 250 mm THICK BRICK WORK
250 mm thick brick work with 1st class bricks in cement
mortar (1:6) interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for at least 7
days in ground floor etc. complete as per direction of the
Engineer-in-char 1.00 cum
04 125 mm THICK BRICK WORK with 1st class bricks in cement

mortar (1:4) interstices with mortar, racking out joints, cleaning and

soaking the bricks before use, curing for at least 7 days in ground

floor etc. complete as per direction of the Engineer-in-char 800.00 sqm


04 PLASTER WITH N.C.F

Page 167 of 180


SL Description of works Quantity Unit
No.

Minimum 12 mm thick cement plaster work (1:4) in wall with

neat cement finishing including cleaning and watering to

surface, before application and curing at least for 7 days etc.

complete as per direction of the Engineer in-charge. 10.00 sqm

05 CEMENT PLASTER (12 mm th)


Minimum 12 mm thick cement plaster work (1:6) in all brick

wall surface cleaning and watering to surface, before

application and curing at least for 7 days etc. complete as per

direction of the Engineer in-charge. 2230.48 sqm

06 PAINTING WORKS
Painting work with Plastic paint (Berger/Elite) of approved

colour to inside of wall, Enamel pain of steel surface and

Cement painting of outside of wall etc. where necessary 2

coats over a coat of priming including preparing the surface

with sand paper 1931.69 sqm


07a WOODEN DOOR FRAME :Supplying and making door
frames with seasoned wood of required size including painting
two coats of coalter to the surface in contact with wall, fitted
and fixed in position and mending good the damages if any
(All sizes of wood are fi
1. Teak chamble
1.00 cum

Page 168 of 180


SL Description of works Quantity Unit
No.

07b WOODEN DOOR SHUTTER :Supplying, fitting and fixing

38mm thick well matured (minimum 10 inch. wide plunk)

solid wood door shutter having top rail style of sections

100mm x38mm lock rail 125mm x38mm and bottom rail

225mmx38mm closed joints and provided with


1. Teak chamble
60.00 sqm
08 WINDOW GRILL
Supplying, fabrication and fixing to window grills of any

design made with 20 mm x 3 mm F.I. bar in/c. necessary

fabrication, welding etc. all complete as per direction of the

Engineer-in-charge. 75.00 sqm


09 Supplying fitting and fixing of 8"x2.5"x1" THICK bricks
cladding 1.00 sqm
10 THAI ALUM SLIDING WINDOW
Supplying fitting and fixing of Aluminium Sliding windows

Bronze colour U.S. Architectural Aluminium Manufactuer’s

Association (AAMA) standard specification having 1.5 mm

thick outer bottom (size 75.50 mm, 32 mm), 1.5 mm thick

outer top (size 75.50 mm, 1

Page 169 of 180


SL Description of works Quantity Unit
No.

of all Aluminium members will be anodized to Aluminium

Bronze/Silver colour with a coat not less than 15 micrones in

thickness and density of 4 mg per square cm etc. including all

accessories like handle, locks (Japan), auto-closure(USA),

stopper, flush, 75.00 sqm


11

WALL TILES WORK: Supplying, fitting and fixing


homogeneous quartz/ embossed WALL tiles (200X200) RAK
or equivalent(local made) on 20 mm thick cement mortar (1:3)
base and raking out the joints with white cement including
cutting and laying the tiles in pr 95.00 sqm
12 FLOOR TILES WORK N: Supplying, fitting and fixing

homogeneous quartz/ embossed floor tiles (300X300) RAK or

equivalent(local made) on 20 mm thick cement mortar (1:3)

base and raking out the joints with white cement including

cutting and laying the tiles i 510.00 sqm


13 Rented Centering & Shuttering Cost With Labour
Cost ,Wooden 560.00 sqm

Page 170 of 180


Rate/Unit Amount
(In Taka) (In Taka)

8,280.00 8280.00
7,500.00 637500.00
8,350.00 41750.00
8,580.00 25740.00
8,580.00 60060.00

63000.00 639453.15

4,450.00 4450.00

580.00 464000.00

Page 171 of 180


Rate/Unit Amount
(In Taka) (In Taka)

156.00 1560.00

140.00 312267.66

145.00 280095.27

137036.00 137036.00

Page 172 of 180


Rate/Unit Amount
(In Taka) (In Taka)

6600.00 396000.00

1076.00 80700.00

1090.00 1090.00

Page 173 of 180


Rate/Unit Amount
(In Taka) (In Taka)

2591.00 194325.00

960.00 91200.00

940.00 479400.00

29.00 16240.00

Page 174 of 180


Ref. BD/01/013 Date : 23.02 2009
BILL OF QUANTITIES PL AREA 4200 SFT
Name of Project: MONOLOVA
Project Area:
25,200.00 Sft 25,200.00 Sft
Item Description Quantity Unit Rate Amount Unit Rate WT % actual Unit Rate Amount Unit Rate WT
No. with wastage (in Tk.) (in Tk.) (per Sft) KG wastage quanity (in Tk.) (in Tk.) (per Sft) KG
SUPER STRUCTURE SUPER STRUCTURE
1 Gable Frame with Pre-engineered I-Section with 113,397 Kg 85.00 9,638,725 8 104997 Kg 85.00 8924745
2 M. S. Plate
12 mm (ASTM
dia Cable A570-50)
Bracing for Column
for Roof (6 bay) and 1,442 Kg 90.00 129,780 3 1400 Kg 90.00 126000
Rafter
3 M. S. Purlin (Z20016) for Roof. 0 Kg 85.00 - 3 0 Kg 85.00 0
4 M. S. Girt (Z20016) for Side. 0 Kg 85.00 - 3 0 Kg 85.00 0
5 Purlin & Girt Cleat. 0 Kg 85.00 - 3 0 Kg 85.00 0
Galvanized Nut Bolts and Washer for Purlin & Girt
6
Cleat.
0 Kg 100.00 - 3 0 Kg 100.00 0
7 12mm thick M. S. Plate for Joint. 12,978 Kg 85.00 1,103,098 3 12599.64 Kg 85.00 1070969
8 Galvanized Nut Bolts and Washer for Joint. 2,336 Kg 90.00 210,238 3 2267.94 Kg 90.00 204114
9 25 mm thick Base Plate. 1,224 Kg 80.00 97,920 2 1200 Kg 80.00 96000
10 Anchor Rod (25 mm Dia.) 1,046 Kg 150.00 156,825 2 1025 Kg 150.00 153750
11 Sag rod(12 mm Dia.) 0 Kg 90.00 - 3 0 Kg 90.00 0
12 4mm thick Template. 41 Kg 100.00 4,120 3 40 Kg 100.00 4000
Sub-Total cost for Superstructure
Sub-Total cost for Superstructure = Tk. 11,340,706 450.03 132,463 = Tk. 10579579 420 123,530
SHEETING & ACCESSORIES: SHEETING & ACCESSORIES:
1 Supply of color coated zinc alume 0.47mm thick
Profile Roofing Sheet . 0 Sft. 54.00 - 0 2 - Sft. 54.00 0 0
2 Supply of Hi-Tensile Color coated 0.47mm thick
Profile sheets for Wall & End Gable. (considering 0 Sft. 54.00 - 0 3 0 Sft. 54.00 0 0
Brick Wall height up to 2440mm).
3 Color coated 0.6mm thick 600 mm girth Ridge 0 Rft. 125.00 - 0 5 0 Rft. 125.00 0 0
4 Capping.
Color coated 0.6mm thick 750 mm girth 0 Rft. 150.00 - 0 5 0 Rft. 150.00 0 0
longitudinal end Capping.
5 Color coated 0.6mm thick 457 mm girth
longitudinal facia capping
0 Rft. 125.00 - 0 5 0 Rft. 125.00 0 0
6 Color coated 0.6mm thick 457 mm girth External 0 Rft. 125.00 - 0 5 0 Rft. 125.00 0 0
Corner Capping.
7 Color coated 0.6mm thick 457 mm girth Internal 0 Rft. 95.00 - 0 5 Rft. 95.00 0 0
Corner Capping.
8 Color coated 0.6mm thick 457 mm girth gable 0 Rft. 125.00 - 0 5 0 Rft. 125.00 0 0
trim
9 Decking 0.70 mm thick 0 Sft. 85.00 - 0 5 0 Sft. 85.00 0 0
10 Color coated 0.6mm thick 800 mm girth Eave 0 Rft. 125.00 - 0 5 0 Rft. 125.00 0 0
Gutter.
11 Color coated 0.6mm thick 1000 mm girth valley 0 Rft. 160.00 - 0 5 0 Rft. 160.00 0 0
Gutter.
12 Bottom flash 300 mm girth 0.6 thick 0 Rft. 65.00 - 0 5 0 Rft. 65.00 0 0
13 Down Pipe 400 mm girth 0.6 thick 0 Rft. 95.00 - 0 5 Rft. 95.00 0 0
14 Down Pipe(PVC) 100mm dia 0 Rft. 100.00 - 0 5 0 Rft. 100.00 0 0
15 End Stop. 0 Nos. 650.00 - 0 0 0 Nos. 650.00 0 0
16 Gable Runner(75x75x1.6) 0 Rft. 70.00 - 0 2 0 Rft. 70.00 0 0
Item Description Quantity Unit Rate Amount Unit Rate WT % actual Unit Rate Amount Unit Rate WT
No. with wastage (in Tk.) (in Tk.) (per Sft) KG wastage quanity (in Tk.) (in Tk.) (per Sft) KG
16 Silicon Sealant.
0 Tube 230.00 - 0 0 Tube 230.00 0

17 Silicon Dispenser. 0 No. 265.00 - 0 0 No. 265.00 0


18 FASTENERS : a) -12-14 x 55 HGS (For
Roofing)
0 Nos. 4.00 - 0 0 0 Nos. 4.00 0 0
b) -12-14 x 20 HWF (For Cladding) 0 Nos. 4.00 - 0 0 0 Nos. 4.00 0 0
c) -14-14 x 22 RP HWF (For Stitching) 0 Nos. 3.00 - 0 0 0 Nos. 3.00 0 0
d) -14-14 x 22 RP HWF (For Decking) 0 Nos. 4.00 - 0 0 0 Nos. 4.00 0 0
Sub-Total cost for Sheeting &
Sub-Total cost for Sheeting & Accessories = Tk. - - 132,463 Accessories = Tk.
0 - 123,530

Item Description Quantity Unit Rate Amount Unit Rate Quantity Unit Rate Amount Unit Rate

No. (in Tk.) (in Tk.) (per Sft) (in Tk.) (in Tk.) (per Sft)
1
Transportation charge from our Factory to the
- L. S. - 185,294 L. S. - 185,294
Project Site will be borne by us at actual (approx).

2 Erection of Pre-engineered welded steel Column,


Rafter, Floor Beam, Purlin, Girt etc. and Fitting &
fixing charge of Gable Wall & Roof sheeting in/c 25,200 Sft. 22.00 554,400 25,200 Sft. 22.00 554,400
Capping, Flashing, Gutter, Down Pipe, Door,
Canopy, Translucent Sheet for Roof etc. (basis on Sub-Total cost for Sheeting &
floor area) Sub-Total cost for Sheeting & Accessories = Tk. 739,694 29.35 Accessories = Tk. 739,694 29.35
12,080,400 479.38 11,319,273 449.18
Total coverd area 25,200 Sft. Total coverd area 25,200 Sft.
Item Description Quantity Unit Rate Amount Unit Rate Quantity Unit Rate Amount Unit Rate
No. (in Tk.) (in Tk.) (per Sft) (in Tk.) (in Tk.) (per Sft)
1 DS door (3.0 m x 3.0 m ) 01no 97 Sft. 450.00 43650 0 97 Sft. 450.00 43,650
2 Canopy 02 no 0 Sft. 350.00 0 0 Sft. 350.00 -
Sub-Total cost of 0Accessories =
Sub-Total cost of Accessories =Tk. 43650 1.73 Tk. 43,650 1.73
Grand total 12124050 481.11 Grand total 11,362,923 450.91 4.90
TOTAL COST OF THE BUILDING

PILING COST
BASEMENT COST ( UPTO GFL ) 1 X 4907 sft = 4907 sft
GF COST 1 X 4907 sft = 4907 sft
TYPICAL FLOOR 5 X 4907 sft = 24535 sft
Total Floor area = 34349 sft
Extra cost for Rooftop & Chilakotha. @ Tk. 160.00
Cost of roof top RCC water tank 2000 IG @ Tk. 95.00
Sanitary Works 31896 /sft @ TK 100.00 /ft2
Electrical Works 31896 /sft @ TK 122.00 /ft2
Labour above
Machine Charge
Construction of under ground reservoir : 10000 IG @ Tk. 40.00
Gate (MS,GI PIPE,) 1.00 nos 150.00 sft @ Tk. 700.00

Compound drain. 300x300mm in bricks 130.00 ft long @ Tk. 250.00

Boundary wall (without B.W. fencing) R.C.C. frame 300.00 ft long @ Tk. 1500.00

Gas Connection. @ 23.00 @ Tk. 9.00

TOTAL CIVIL COST Tk. 1258 /sft Tk. 43,221,909

TOTAL STEEL COST Tk. 353 /sft Tk. 12,124,050

TOTAL (CIVIL + STEEL) COST Tk. 1611 /sft Tk. 55,345,959


BUILDING

Tk. 4000663 = Tk. 4,000,663 Tk. 815 /sft


Tk. 5426719 = Tk. 5,426,719 Tk. 1106 /sft
Tk. 3861694 = Tk. 3,861,694 Tk. 787 /sft
Tk. 3871147 = Tk. 19,355,735 Tk. 789 /sft

Tk. 785,120 = Tk. 0


Tk. 190,000 = Tk. 0
Tk. 3189550 = Tk. 0
Tk. 3891251 = Tk. 0
Tk. 400,000 = Tk. 400,000
Tk. 200,000 = Tk. 200,000
Tk. 400,000 = Tk. 0
Tk. 105,000 = Tk. 0
Tk. 32,500 = Tk. 0
Tk. 450,000 = Tk. 0
Tk. 333,676 = Tk. 0
Tk. 9,977,097
Tk. 43,221,909 = Tk. 33,244,812 Tk. 968 /sft

Tk. 12,124,050 = Tk. 12,124,050 Tk. 353 /sft

Tk. 55,345,959 = Tk. 45,368,862 Tk. 1321 /sft


1 Sanitary & water supply cost(OF CIVIL & STEEL COST) 6 %
2 Electrical cost(OF CIVIL & STEEL COST) 7 %

3 Lift cost 1 no.


4 Generator cost 1 no.
5 Transformer cost 1 no.

6 Extra cost Roof top RCC PARAPET 3' ht 840.60 sft @


7 Extra cost for Rooftop & Chilakotha. 4907.00 sft @
8 Capacity of roof top RCC water tank 2000 IG @
9 Construction of under ground reservoir : 9000 IG @
10 Length & size of Compound drain. 300x300mm in bricks 130.00 ft long @ tk
11 Boundary wall (without B.W. fencing) R.C.C. frame 300.00 ft long @ tk
12 Gate (MS,GI PIPE,) 1.00 nos 150.00 sft
13 Gas Connection. 23.00
14 Others ls

SANITARY WORKS' COST( PWD ) 2736 M2 Tk. 102 /sft

ELECTRICAL WORKS' COST ( PWD ) 2736 M2 Tk. 144 /sft

5" brick work 933.33 rft 4907.0 sft


total plaster times of covered area per story
bricks 800.00 m2 456.04
45553982 = 2733239
45553982 = 3188779

1300000 = 1300000
300000 = 300000
150000 = 150000

150.00 = 126090
140.00 = 686980
95 = 190000
40 = 360000
250.00 = 32500
1500.00 = 450000
TK 700.00 /sft = 105000
9.00 = 333676
100000 = 100000
GT = 10056264

TK 1100.00 /M2 3009870

TK 1550.00 /M2 4241180

9.00' = 103 psf


mes of covered area per story = 4
43040.00 no = 8.77 nos/sft

You might also like