Professional Documents
Culture Documents
Soil data PL 3.00 ft design/est footing 16 '' dia 18 '' dia 20 '' dia
Soil capac 1.00 tsf -5.00 ft 0.95 tsf 35.00 ton 49.00 ton 59.00 ton
Soil capac 1.25 tsf -7.50 ft -6.50 ft 48.00 ton 63.00 ton 77.00 ton
Soil capac 1.50 tsf -10.00 ft 2.0 ft sand copm 60.00 ton 74.00 ton 89.00 ton
L1=101.00 ft B1=59.00 ft 5959.00 bay spacing 17.29 17.5 13.75 17.54X2 17.38
L2=79.50 ft B2=38.50 ft 3060.75 bay spacing 18.7 17.5 19.58 23.58
L=0.00 ft B=0.00 ft 0.00 gable end col s
1 10 5.75 deg gable end col s
roof extension all around= 0.00 ft 0.00 ft
Depth(ft) L2-L1 SPT value Correcte Average SPT Soil type qu=2Cd tsf Nc
d SPT
0 0 0 0
5 5 12 12 6 cohesive 0.75 9
10 5 18 16.5 15 cohesive 2 9
15 5 7 7 12.5 cohesive 1.7 9
20 5 6 6 6.5 cohesive 0.63 9
25 5 9 9 7.5 cohesive 1 9
30 5 13 13 11 cohesionless
35 5 15 15 14 cohesionless
40 5 16 15.5 15.5 cohesionless
45 5 18 16.5 17 cohesionless
50 5 21 18 19.5 cohesionless
55 5
60 5
N 0 4 10 30 50 favg = 40
φ 28 30 36 41
moist ∂ < 100 95-125 110-130 110-140 >130 favg = 20 Nc
submerged ∂ < 100 95-125 110-130 110-140 >130
= 23.59 kn
= 5.30 kips
* IF THE SOIL & THE FILL ARE ABOVE THE WATER TABLE ∂effective =∂moist
PILE
Qp = Ap * qp = Ap (c Nc' + q' Nq' + ∂ D N∂' ) ≈ Ap (c Nc' + q' Nq' ) ≈ Ap q' N
1. Meyerhof method:
CON. PILE LENGTH , L = 50 FT ULTIMATE POINT LOAD ?
SOIL TYPE SANDY = 0 =c
X - SEC 16 = 16 INCH Qp = 537.78 kips
UNIT WT SOIL = 110 PCF Qp =Ap ql= 56.42 kips
for φ =30 ,Nq' = 55
φ = 30 DEG design ult Qp= 56.42 kips
2. Vesics method :
Lc = 50 ft ULTIMATE POINT LOAD ?
for φ =30 & Lc=50 , Nq' = 36 Qp = 234.72 kips
3. Janbu's method :
n' 90 deg ULTIMATE POINT LOAD ?
for φ =30 & n'=90 , Nq' = 19 Qp = 185.78 kips
COYLE METHOD :
FS = 4 Qp= 244.44
L/D = 37.5 Qs= 65.26
for φ =30 & L/D=37.5 , Nq' = 25 FIG 9.16 Qu=Qp+Qs= 309.71 kips
K = 0.2 FIG 9.19 Qa =Qp+Qs= 77.43 kips
s = c+ ∂' tan φ COHES
concrete
s= qu / 2 timber
Cc = .009 ( LL - 10 ) soft
medium
Cc = .30 (eo - .27 ) stiff
consistancy
S = Cc/(1+eo) * H Log((po + ∆p)/po)
N
φ = 25 + .15Dd
qu (t/sft)
φ = 30 + .15Dd
unit weight
N = 15 + .5*(N'-15)
GRANU
N = N' ( .77 LOG10 20/p' ) p' => .25 tsf compactness
relative
pile : density Dd
Qp = Ap ( c Nc' + q' Nq' )
N
Qs = ∑p ∆L f φ
moist ∂
f avg (psf) = 40 N‾c for high displacement driven pile submerged ∂
9.17 ft
" c/c
6.2
d (in) =
@
20
D
15
20
"c/c
5.39
D @
20
Effetive length
36.00 ft
Ps
52.89 kip
0.0350
s
4.2ft
3.3ft
8.4ft
Ps + Pe, kip
s = c+ ∂' tan φ
s= qu / 2
Cc = .009 ( LL - 10 )
clay
40 ñ psf
favg = 20 Nc psf
= 140.74 kn
= 31.64 kips
≈ Ap (c Nc' + q' Nq' ) ≈ Ap q' Nq'
K = 1.3
DELTA 0.8 φ = 24
L 15 D = 20 ft
at 0.00ft f = 0
at 20.00ft gama L' = 2.2 kip/ft2
at 20.00ft f = 1.27 kip/ft2
Qs = 271.4936 kips
ALLOWABLE LOAD CARRYING CAPACITY ?
FS = 4
Qp ult avg. = 158.9719 kips
Qallow = Qp+Qs = 107.6164 kips
COHESIVE clay
0 2 4 8 16 32
0 0.25 0.5 1 2 4
0% 15 % 35 % 65 % 85 % 100 %
0 4 10 30 50
28 30 36 41
< 100 95-125 110-130 110-140 >130
< 100 95-125 110-130 110-140 >130
LOAD PER BORE
PILE HOLE
119 11 1
128 11 2
143 11 3
152 12 4
153 12 5
152 12 6
153 12 7&8
148 12 9
151 5 10
150 5 11
151 5 12
143 5 13
175 5 14
165 5 17
109 11 21
122 11 22
172 11 23
194 12 24
191 12 25
189 12 26
180 12 27&28
167 12 29
170 5 30
168 5 31
170 5 32
164 5 33
169 5 34
190 O-4 38
190 O-4 39
173 O-8 40
175 O-3 41
133 13 42
132 13 43
142 13 44&45
136 13 46
138 14 47
137 14 48
138 14 49
138 14 50
124 14 51
150 O-5 52
194 O-5 53
190 O-7 54
208 O-2 55
256 O-2 56
157 O-6 57
160 O-6 58
162 O-7 59
192 O-7 60
123 11 15
125 11 16
98 11 19
131 11 20
107 11 18
125 11 35
123 11 36
120 11 37
size
2 20
38
ft
9.17
DESIGN OF SPREAD FOOTING-ULTIMATE, RECTANGULAR
DATA : Solution :
Fc' ksi 2.50 ¢Vc PS 170.0 psi
Fy ksi 60.00 ¢Vc BS 85.0 psi
Qa ksf 3.00 Pressure at 5ft depth 750.00 psf
Column size-long inch 18.00 Eff bearing pressure 2,250.00 psf
Column size-short inch 18.00 Required footing area 176.89 ft2
As # 0.31 long side 13.30 ft
DL kips 250.00 kips short side 13.30 ft
LL kips 148.00 kips Let long side of sq. footing 13.50 ft
BASE ,below 6.00 ft Let short side of sq. footing 13.50 ft
avg. unit wt of fill soil/conc 125.00 pcf A-provided 182.25 ft2
Ratio of sides=l/s 1.00 Upward pressure by f.c.l. 3.30 ksf
punching shear at d/2 beam shear at d
let d 27.0 long short
bo 180.0
V - kips 555.2 167.1 167.1
Vc -kips 826.2 371.8 371.8
ok ok ok
BENDING moment at col face long short
Mu 9,625.6 Kip" 9,625.6 Kip"
LET a 1.11 inch 1.11 inch
As = M/(PHI *Fy(d-a/2)) 6.74 in² 6.74 in²
a 1.17 1.17
As total 6.75 6.75
As(min) 10.94 in² 10.94 in²
As(min)=200/fy 14.58 in² NLT 14.58 in² NLT
# 4 72.9 nos @
Mat foundation : for a max raft settlement 2", diff sett would be .75", Fd=1
q net = Q/A - ∂ Df
N = 15 + .5*(N'-15)
11.1 " c/c
8.8 " c/c N = N' ( .77 LOG10 20/p' ) p' => .25 tsf
6.7 " c/c
4.9 " c/c
3.4 " c/c
11.25
13.5
15.75
18
OK
"
in² na
NOT OK
inch
inch
ff settlement
be .75", Fd=1
A. COST OF CONCRETE FOR 100 CFT : 1 1.5 3 COST OF MATERIALS 165 /ft3 5810 /m3
A-1 COST OF MATERIALS COST OF LABOUR & EQUIPMENT 16 /ft3 547 /m3
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.) AMOUNT (Tk.) without 20.0 % markup 180 /ft3 6357 m3
a) stone CHIPS I/C BREAKING 82 CFT 85 6970 with 20.0 % markup 216 /ft3 7629 m3
b) 100 % sylhet sand 42 CFT 27 1134 1 IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB .
c)CEMENT 22 BAG 380 8360 2 IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL
f) SKILLED LABOUR 6 nos. 200 1200 1 IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB .
g) LABOUR 34 nos. 150 5100 2 IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL
h) MIXTURE MACHINE 1 DAY 800 800 3 RCC IN TIE BEAMS & LINTEL
I) VIBRATOR 1 DAY 400 400 4 RCC IN TEE, ELL, RECTANGULAR BEAMS
j) FULE & LUBRICANTS 1 DAY 500 500 5 RCC IN FLOOR/ROOF SLAB
FOR 600CFT : 9300 6 RCC IN SUNSHED, CORNICE, RAILING, DROPWALL
SO FOR 100CFT COST IS Total 1550 7 RCC IN STAIR CASE SLAB & STEPS
1 COST ANALYSIS FOR 100 CFT RCC (1:1.5:3) IN FOOTINGS OF COLUMN, STEEL SHUTTER IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB AT
RAFT & FLOOR SLAB AT PLINTH LEVEL WITH STONE CHIPS. COST OF SHUTTERING( for 36 cft )
Sl.No Description of Works Quantity Unit
CONCRETE 16464 1 PLATE 83.88 LBS
LABOUR,EQIP. 1550 2 ANGLE 157.39 LBS
SHUTTERING 2367.52 3 FI BAR 47.6 LBS
TOTAL 20382 4 FRAME 24.67 SFT
Contractors profit 0.1 2038.152 5 NUTS BOLTS 1 KG
Over head expences 0.025 509.5381
VAT & IT 0.075 1528.614 TAKING USE FOR 16 TIMES
COST FOR 100 CFT GRAND TOTAL 24458 6 LABOUR FOR SHUTTERING 24.67 SFT
SO COST PER CUM = TK. 8631 SO FOR 100CFT
2 RCC IN PADESTALS, COLUMN,COLUMN CAPITAL,LIFT WALL & WALL STEEL SHUTTER FOR RCC IN PADESTALS, COLUMN,COLUMN CAPITA
A. CONCRETE 16464 COST ANALYSIS OF SHUTTERING (FOR
B. LAB/EQIP 1550 SL. NO.DESCRIPTION OF WORKS QTY UNIT
C. SHUTTER 15216 1 PLATE 158.68 LBS
33230 2 ANGLE 255.2 LBS
Contractors profit 0.1 3322.966 3 FI BAR 68 LBS
Over head expences 0.025 830.7414 4 FRAME 46.67 SFT
VAT & IT 0.075 2492.224 5 NUTS BOLTS 1.5 KG
COST FOR 100 CFT GRAND TOTAL 39876
SO COST PER CUM = TK. 14072 TAKING USE FOR 16 TIMES
6 PROPS 24 RFT
TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTTERING 40 SFT
FOR 10 CFT
SO FOR 100 CFT TOTAL
3 RCC IN TIE BEAMS & LINTEL STEEL SHUTTER RCC IN TIE BEAMS
COST ANALYSIS OF SHUTTERINGSO( FOR
A. CONCRETE 16464
B. LAB/EQIP 1550 SL. NO.DESCRIPTION OF WORKS QTY UNIT
C SHUTTER 8698.52 1 PLATE 65.86 LBS
26713 2 ANGLE 92.49 LBS
Contractors profit 0.1 2671.252 3 FI BAR 7.96 LBS
Over head expences 0.025 667.8131 4 FRAME 19.37 SFT
VAT & IT 0.075 2003.439 5 NUTS BOLTS 1 KG
GRAND TOTAL FOR 100 CFT 32055
TAKING USE FOR 16 TIMES
SO COST PER CUM = TK. 11312 6 PROPS 7 RFT
TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTT 19.37 SFT
SO FOR 6.94 CFT
SO FOR 100 CFT
4 RCC IN TEE, ELL, RECTANGULAR BEAMS STEEL SHUTTER RCC IN TEE, ELL, RECTANG
COST ANALYSIS OF SHUTTERING( FOR
A. CONCRETE 16464 SL. NO.DESCRIPTION OF WORKS QTY UNIT
B. LAB/EQIP 1550 1 PLATE 294.44 LBS
C SHUTTER 9401.3958 2 ANGLE 425.32 LBS
27415.396 3 FI BAR 147.22 LBS
4 FRAME 86.6 SFT
5 NUTS BOLTS 4 KG
Contractors profit 0.1 2741.53958
Over head expences 0.025 685.384896 TAKING USE FOR 16 TIMES
VAT & IT 0.075 2056.15469 6 PROPS 14 RFT
COST FOR 100 CFT GRAND TOTAL 32898.475 TAKING USE FOR 30 TIMES
7 LABOUR FOR SHUTT 86.6 SFT
SO COST PER CUM = TK. 11610 SO FOR 30 CFT
SO FOR 100 CFT
Tk 1003 /m3 Tk. 28 /ft3 Tk 802 /m3 Tk. 23 /ft3 Tk 628 /m3
Tk 6444 /m3 Tk. 183 /ft3 Tk 5155 /m3 Tk. 146 /ft3 Tk 147 /m3
Tk 3684 /m3 Tk. 104 /ft3 Tk 2947 /m3 Tk. 84 /ft3 Tk 2146 /m3
Tk 3981 /m3 Tk. 113 /ft3 Tk 3185 /m3 Tk. 90 /ft3 Tk 3761 /m3
Tk 3503 /m3 Tk. 99 /ft3 Tk 2803 /m3 Tk. 79 /ft3 Tk 2593 /m3
Tk 5454 /m3 Tk. 155 /ft3 Tk 4363 /m3 Tk. 124 /ft3 Tk 2718 /m3
Tk 2572 /m3 Tk. 73 /ft3 Tk 2057 /m3 Tk. 58 /ft3 Tk 2697 /m3
OF COLUMN,RAFT & FLOOR SLAB AT PLINTH LEVEL Analysis of wooden Shuttring in individual and continuous footings of column Considering 100 cft.
Cost of shuttering
Rate Amount ( Tk.) Considering Base 6'x6'x14" to 10"
25 2097 Volume of concrete: 6'-0" x 6' x 1'-0" (approx.) =
25 3934.75 i) Cost of shuttring wood:
25 1190 Planks required:
65 1603.55 add 15 %
75 75
8900.3
556.26875 ii) Labour for shuttring in /c making,placing & removing:
12 296.04
852.30875 iii) Supplying, fitting and fixing, rupban /equivalent sheet & heassian tape (where necessary) & remov
2367.52431 same for making shutter water-tight.
RATE (Tk.) AMOUNT (Tk.) iii) Labour for shuttring in /c making,placing & removing:
25 5100 2.00 10.00
25 6699 1.00 3.00
25 1105
65 3900
75 0 iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
16804 (where necessary) for making shutter water-tight sufficiently
Total 1050.25
v) Nails and wires
12 720
FOR 7.5 CFT TOTAL 1770.25 Cost for 100.00 cft of co
SO FOR 100 CFT TOTAL 23603.33
iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
(where necessary) for making shutter water-tight sufficiently
iv) Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape
(where necessary) for making shutter water-tight sufficiently
Tk. 18 /ft3 Tk 523 /m3 Tk. 15 /ft3 in individual and continuous footings of column
L.S. = tk 500.00
Total of Cost = tk 2280.41
Cost for 100.00 cft of conc work = tk 5067.59
0.83 = 16.66
0.83 = 2.50
19.16 6 tk 114.95
10.00 = 100.00
0.38 = 15.00
115.00 6 tk 690.00
nt sheet & heassian tape
4.00 = 35.00
0.50 = 18.00
1.13 = 19.69
72.69 6 tk 436.13
nt sheet & heassian tape
b) SAND fm 1.8
c)CEMENT
g) LABOUR
h) MIXTURE MACHINE
I) VIBRATOR
j) FULE & LUBRICANTS
FOR 600CFT :
TOTAL LABOUR & EQUIPMENT COST FOR
Analysis of wooden Shuttring in R.C.C. work in i
Considering 100 cft. of work , Cost of shuttering
Considering Base 6'x6'x14" to 10
Volume of concrete: 6'-0" x 6' x 1'-0" (approx.)
i) Cost of shuttring wood:
Planks required:
24.00 ' 1.00 '
add 15% for batten, supports & wastage
Using
ii) Labour for shuttring in /c making,
placing & removing:
iii) Supplying, fitting and fixing, rupban /
equivalent sheet & heassian tape
(where necessary) & removing the
same for making shutter wate
COST OF CONCRETE FOR 100 CFT : 1 1.5 3 A. COST OF CONCRETE FOR 100 CFT : 1
COST OF MATERIALS A-1 COST OF MATERIALS
QTY UNIT RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORK QTY UNIT
83 CFT 66 5478 a)COST OF brick CHIPS 83 CFT
42 CFT 17 714 b) SAND fm 1.8 42 CFT
22 BAG 375 8250 c)CEMENT 22 BAG
TAL MATERIAL COST FOR 100 CFT concrete : 14442 TOTAL MATERIAL COST FOR 100 CFT concrete :
COST OF LABOUR & EQUIPMENTS( for 600 cft) : A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) :
QTY UNIT RATE (Tk.) AMOUNT (Tk.) SL. NO. DESCRIPTION OF WORKS QTY UNIT
1 NOS. 350 350 d) H. MASON 1 NOS.
4 NOS. 300 1200 e) MASON 4 NOS.
6 nos. 200 1200 f) SKILLED LABOUR 6 nos.
34 nos. 180 6120 g) LABOUR 34 nos.
1 DAY 1000 1000 h) MIXTURE MACHINE 1 DAY
1 DAY 600 600 I) VIBRATOR 1 DAY
1 DAY 500 500 j) FULE & LUBRICANTS 1 DAY
FOR 600CFT : 10970 FOR 600CFT :
TAL LABOUR & EQUIPMENT COST FOR 100 CFT WORKS : 1828.33 TOTAL LABOUR & EQUIPMENT COST FOR 100 CFT WORKS :
ysis of wooden Shuttring in R.C.C. work in individual and continuous footings of column at plinth level. Analysis of wooden Shuttring
sidering 100 cft. of work , Cost of shuttering R.C.C. work IN Padestals, column capitals, lift walls and wall
6.00 ' 6.00 ' 1.00 ' Considering 100 cft. of work Cost of shuttering
ume of concrete: 6'-0" x 6' x 1'-0" (approx.) = 36 cft Assuming column size 10.00 ' 1.00 '
Volume of concrete: (approx.) =
i) Cost of shuttring wood:
0.08 ' = 2 cft Planks & batten required:
d 15% for batten, supports & wastage = 0.3 cft 2 10.00 ' 1.25 0.125 =
2.30 cft tk 500.00 2 10.00 ' 1.00 ' 0.125 =
6 times = Tk. tk 191.67 4 3 0.25 0.125 =
abour for shuttring in /c making, =
24 sft @ tk 11.00 tk 264.00 add wastage 5.00 % =
Supplying, fitting and fixing, rupban /
uivalent sheet & heassian tape Using 6.00 times
ere necessary) & removing the ii) Bamboo Props in / c incli 4.00 nos
24 sft @ tk 1.00 tk 24.00 Using 6.00 times
L.S. tk 25.00 iii) Labour for shuttring in /c making,placing & removing:
Total of Cost = tk 504.67
st for 100.00 cft of conc work = tk 1401.85 iv)Supplying, fitting and fixing, rupban or equivalent sheet & heassian tape(where necessary
40.00 sft @ tk 1.00 /sft
EL SHUTTER IN FOOTINGS OF COLUMN,RAFT & FLOOR SLAB AT PLINTH LEVEL v) Nails and wires L.S. =
ST OF SHUTTERING( for 36 cft ) Total of
Quantity Unit Rate Amount ( Tk.) Cost for 100.00 cft of conc work =
83.88 LBS 25 2097
157.39 LBS 25 3934.75 STEEL SHUTTER IN RCC IN PADESTALS, COLUMN,COLUMN CAPIT
47.6 LBS 25 1190 COST ANALYSIS OF SHUTTERING (FOR 10 CFT)
24.67 SFT 60 1480.2 SL. NO. DESCRIPTION OF WORK QTY UNIT
1 KG 80 80 1 PLATE 158.68 LBS
8781.95 2 ANGLE 255.2 LBS
16 TIMES 548.871875 3 FI BAR 68 LBS
24.67 SFT 8 197.36 4 FRAME 46.67 SFT
746.23 5 NUTS BOLTS 1.5 KG
st for 100.00 cft of conc work = 2072.866319444
TAKING USE FOR 16 TIMES
6 PROPS 24 RFT
TAKING USE FOR 16 TIMES
A. CONCRETE 11665
B. LAB/EQIP 1103.33
C SHUTTER 5141.44
17909.77
tk 616.81
tk 894.30
tk 74.53
tk 500.00
tk 2085.63
tk 4634.74
At site cost of materials :
Cost of bricks per no. Tk 6.00 brick chips cft Tk 50.00
Viti sand cft Tk 9.00 stone chips cft Tk 80.00
Sand fm 1:8 cft Tk 15.00
B. Labour cost
H. mason nos 0.06 Tk 350.00
mason each 0.25 Tk 250.00
skilled labour each 1.00 Tk 200.00
local carriage sundries
tools & Plants etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
Total
RATE PER SFT
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
BW(1:6) in foundation
100 CFT unit Qty u. rate
A.Material cost
bricks nos 1,100.00 Tk 6.00
sand fm-1.5 cft 36.00 Tk 15.00
cement bag 4.00 Tk 380.00
B. Labour cost
head mason each 0.10 Tk 250.00
mason each 1.00 Tk 180.00
s. labour each 1.00 Tk 120.00
or. labour each 1.50 Tk 100.00
curing7days@1/4 lab each 1.75 Tk 100.00
local carriage,storage
sundries, T&P etc ls
Total
RATE PER CFT
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
A. + B.
Contractors profit
Over head expences
VAT & IT
COST FOR 100 CFT(GRAND TOTAL) =
CC 1:3:6 Found/flr
unit Qty u. rate
A.Material cost
bricks 90cft chips nos 765.00 Tk 6.00
sand fm-1.5 cft 45.00 Tk 15.00
cement bag 12.00 Tk 280.00
breaking/screening cft 90.00 Tk 6.00
B. Labour cost
head mason each 0.25 Tk 200.00
mason each 0.75 Tk 160.00
s. labour each 2.00 Tk 100.00
or. labour each 2.00 Tk 90.00
curing7days@1/4 lab each 1.75 Tk 90.00
local carriage,storage
sundries, T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
RATE PER CFT 4196.47506
hire charge
mixture machine ls 100.00 100.00
vibrator ls 60.00 60.00
fuel & lubricant ls 50.00 50.00
miscellaneous ls 30.00 30.00
total Tk 2,091.21
C. cost of shattering
Let beam 20×1.5×.83
concrete vol=25cft
1 shuttering wood
planks 40.00 1.50 0.13
20.00 1.08 0.13
butten 11.25 0.25 0.13
10.80 0.17 0.13
total
using 6 times total
2 bamboo post 6times
3 slbullah10nos×10ft 8times
4 nails
5 labour for shuttering 20.00 1.50 2.00
20.00 0.83 1.00
FOR 25cft total cost
FOR 100cft total cost
miscellaneous cost
overhead&sundries 10%
contractor's profit 10%
FOR 100CFT
COST PER CFT GF
COST PER CFT 1ST F
COST PER CFT 2nd F
Suppling,fabrication etc MS
1.00 cwt
cost of mat unit qty rate
ms rod DB cwt 1.00 3,400.00
GI wire seer 1.00 90.00
labour cost
rod binder each 0.20 200.00
helper-skilled each 0.75 140.00
local carriage,T&P ls
total
Misce. cost
overhead&sundries 7.00 %
contractor's profit 6.00 %
Rate per cwt
Rate per ton
/cft %
RCC beam/girder 8.50 lbs 1.73
(no slab in/c) 9.00 lbs 1.84
10.00 lbs 2.04
11.00 lbs 2.24
12.00 lbs 2.45
5.00 1.02
labour cost
rod binder each 0.20 160.00
helper-skilled each 0.75 80.00
local carriage,T&P ls
total
Misce. cost
overhead&sundries 10%
contractor's profit 10%
Rate per cwt
Rate per ton
/cft %
Rec beam/girder lbs 8.50 1.73
no slab in/c lbs 9.00 1.84
lbs 10.00 2.04
lbs 11.00 2.24
lbs 12.00 2.45
PLASTER
1/4"th (1:4) cp on cealing,col,beam
100sft unit Qty u. rate
A. Material cost
B. Labour cost
C. Miscellaneous cost
PLASTER
min 1/2"th (1:6) cp on outer wall
100sft unit Qty u. rate
A.Material cost
B. Labour cost
C.Miscellaneous cost
PLASTER
min 3/4"th1:6cp inner wall
100sft unit Qty u. rate
A.Material cost
sand fm-1.5 cft 8.00 Tk 15.00
cement bag 1.00 Tk 380.00
B. Labour cost
head mason each 0.25 Tk 250.00
mason each 1.25 Tk 150.00
or. labour each 1.25 Tk 100.00
scaffolding,curing
local carriage etc. ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
VAT4.5%
GT
CBW(1:4)GF 10holes
unit Qty u. rate
A.Material cost
bricks nos 1,100.00 Tk 6.00
sand fm-1.5 cft 40.00 Tk 15.00
cement bag 6.50 Tk 380.00
B. Labour cost
head mason each 0.10 Tk 180.00
mason each 1.00 Tk 150.00
s. labour each 3.00 Tk 100.00
or. labour each 1.50 Tk 90.00
curing7days@1/4 lab each 1.75 Tk 90.00
local carriage,storage
sundries, T&P etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100CFT
RATE PER CFT
A.Material cost
slaked stone lime kg 18.66 Tk 4.00
gum cha 1.00 Tk 10.00
blue cha 1.00 Tk 5.00
B. Labour cost
mason each 1.50 Tk 160.00
or. labour each 1.00 Tk 90.00
scaffolding,curing
local carriage etc. LS
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
B. Labour cost
painter each 0.50 Tk 160.00
helper each 0.50 Tk 100.00
scaffolding,sundries etc ls
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT
B. Labour cost
mason each 1.00 Tk 140.00
or. labour each 1.00 Tk 70.00
sand paper,putty,thinner
etc LS
Total
C.Miscellaneous cost
overhead & sundries 10%
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT
Supplying , fitting and fixing alluminium sliding door with 75.5mm wide section & locking arran
Considering 6.00 '
A. Alluminium shutter
B. Fittings
sliding door key lock
sliding door wheel
sliding door mohiar
sliding door neoprene
bolts & screws in/c sealants
Skilled technechian
Semi-Skilled technechian
Machineries charges
D. Labour charge
1 labour charges for fabrication of alluminium sections in/c cutting,fitting & fixing etc
Skilled technechian
Semi-Skilled technechian
2 labour cost for civil work in dismantling ,installation,levelling,fitting/fixing in positio
Mason
Labour
With VAT
TILES SFF6"×6"white gt foreign on cm 1:3
100sft unit Qty u. rate
A.Material cost
w.glazed tile3sft/doz doz 33.33 Tk 195.00
base:3/4"avg. 1:3
cement bag 1.88 Tk 250.00
sand cft 7.03 Tk 8.00
white cement bag 0.09 Tk 900.00
B. Labour cost
head mason each 2.00 Tk 160.00
mason each 2.00 Tk 140.00
skilled labour each 3.00 Tk 80.00
ord. labour in/c curing each 3.00 Tk 70.00
L.carriage,sundries,t&p LS
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT
B. Labour cost
head mason each 2.00 Tk 160.00
mason each 2.00 Tk 140.00
skilled labour each 3.00 Tk 80.00
ord. labour in/c curing each 3.00 Tk 70.00
L.carriage,sundries,t&p LS
Total
C.Miscellaneous cost
overhead & sundries 10% vat-4.5% in/c
contractor's profit 10%
RATE PER 100SFT
RATE PER SFT
A. Steel Materials
1 Z-section 0.75''
Chowkat
Shutter fr 2
2
With wastage
Shutter fr 2 2
With wastage
3 FI bar
chowkat
With wastage
B. Fittings
stopper handle
12" long iron cleats
6" long clamp for chowkat
2" long pin hinges
Mason
Skilled labour
Screws
E. Carriage
F. Glass panes
3 mm glass panes in/c wastage
fitting/fixing with iron pins/pucca putty
With VAT
Supplying , fitting a
3/4" x
A. Materials
1 outer frame
3/4" x 3/16" 0.478
2 inner frame
3/4" x 3/16" 0.478
horijontal 3.50 '
vertical 4.50 '
diagonal 2.00 '
Mason
Skilled labour
Screws
D. Carriage
With VAT
:
Unit of : Tonne
Tk 60.00 Estimation
Quantity for : 1
Estimation
Tk 4,623.00 Breakdown of Input Items (All prices are in Taka)
Item Type :
Labour
Tk 5,593.83 semi-skilled labourer day 1 150
Tk 1,520.00 Sub-Total :
Tk 25.00
Tk 180.00
Tk 120.00
Tk 150.00
Tk 175.00
Tk 30.00
Tk 9,340.00
Tk 93.40
Tk 934.00
Tk 934.00
Tk 11,301.40
TK 113.01
R STRUCTURE (1:6 )
10277
10% 1027.7
3% 256.925
8% 770.775
TK. 12332.4
TK. 4352.104
cost
Tk 4,590.00
Tk 675.00
Tk 3,360.00
Tk 540.00
Tk 50.00
Tk 120.00
Tk 200.00
Tk 180.00
Tk 157.50
Tk 37.00
Tk 9,909.50
Tk 990.95
Tk 990.95
Tk 11,891.40
TK 118.91
WORKS
2 : 4
118.71 TK/CFT
TK 4,155.87
TK 24,935.21
TK 249.35 /cft
lifting & hoisting 3.00 TK 252.35
Tk 255.35
cost
3,400.00
90.00
40.00
105.00
7.00
Tk 3,642.00
254.94
218.52
Tk 4,115.46
Tk 82,309.20 gf
floor 60DB-Fy415MPa
cost
1,200.00
70.00
32.00
60.00
7.00
Tk 1,369.00
136.90
136.90
Tk 1,642.80
Tk 32,856.00
cost /cft
Tk 126.68
Tk 134.13
Tk 149.03
Tk 163.94
Tk 178.84
am
cost
Tk 45.00
Tk 190.00
Tk 50.00
Tk 150.00
Tk 90.00
Tk 72.00
Tk 597.00
Tk 59.70
Tk 59.70
Tk 716.40
TK 7.16
all
cost
Tk 90.00
Tk 285.00
Tk 62.50
Tk 150.00
Tk 100.00
Tk 60.00
Tk 747.50
Tk 74.75
Tk 74.75
Tk 897.00
TK 8.97
cost
Tk 120.00
Tk 380.00
Tk 62.50
Tk 187.50
Tk 125.00
Tk 60.00
Tk 935.00
Tk 93.50
Tk 93.50
Tk 1,122.00
TK 11.22
1,000.00
100.00
35.00
1,135.00
51.08
1,186.08
tk 148.26
cost
Tk 4,097.50
Tk 80.00
Tk 875.00
Tk 40.00
Tk 420.00
Tk 80.00
Tk 140.00
Tk 122.50
Tk 35.00
Tk 75.00
Tk 5,965.00
Tk 596.50
Tk 596.50
Tk 7,158.00
TK 71.58
cost
Tk 3,000.00
Tk 90.00
Tk 80.00
Tk 90.00
Tk 24.00
Tk 3,284.00
Tk 328.40
Tk 328.40
Tk 3,940.80
TK 39.41
cost
Tk 6,600.00
Tk 600.00
Tk 2,470.00
Tk 18.00
Tk 150.00
Tk 300.00
Tk 135.00
Tk 157.50
Tk 30.00
Tk 10,460.50
Tk 1,046.05
Tk 1,046.05
Tk 12,552.60
TK 125.53
cost
Tk 636.00
Tk 45.00
Tk 90.00
Tk 810.00
Tk 36.00
Tk 112.50
Tk 100.00
Tk 90.00
Tk 157.50
Tk 44.00
Tk 2,121.00
Tk 212.10
Tk 212.10
Tk 2,545.20
TK 25.45
cost
Tk 65.31
Tk 10.00
Tk 5.00
Tk 67.50
Tk 210.00
Tk 70.00
Tk 32.00
Tk 459.81
Tk 45.98
Tk 45.98
Tk 551.77
TK 0.552
oat
cost
Tk 74.64
Tk 10.00
Tk 5.00
Tk 240.00
Tk 90.00
Tk 40.00
Tk 459.64
Tk 45.96
Tk 45.96
Tk 551.57
TK 0.552
cost
Tk 297.00
Tk 80.00
Tk 50.00
Tk 40.00
Tk 467.00
Tk 46.70
Tk 46.70
Tk 560.40
TK 5.60
cost
Tk 257.40
Tk 140.00
Tk 70.00
Tk 44.00
Tk 511.40
Tk 51.14
Tk 51.14
Tk 613.68
TK 6.137
f 1.5mm thick
x 5.75 = 5.75 rft @ tk 42.52
E of 1.5mm thick
x 7.00 ' = 7.00 rft @ tk 34.00
Wastage
Sub total (A)
LS
10 %
3.50 %
4.50 %
on cm 1:3
cost
Tk 6,499.35
Tk 468.75
Tk 56.25
Tk 81.00
Tk 7,105.35
Tk 320.00
Tk 280.00
Tk 240.00
Tk 210.00
Tk 78.00
Tk 8,233.35 Tk 1,128.00
Tk 823.34
Tk 823.34
Tk 9,880.02
TK 98.80
n cm 1:3
cost
Tk 4,199.58
Tk 468.75
Tk 56.25
Tk 81.00
Tk 4,805.58
Tk 320.00
Tk 280.00
Tk 240.00
Tk 210.00
Tk 78.00
Tk 5,933.58 Tk 1,128.00
Tk 593.36
Tk 593.36
Tk 7,120.30
TK 71.20
grey
cost
Tk 1,080.00
Tk 250.00
Tk 1,181.25
Tk 180.00
Tk 360.00
Tk 781.71 Tk 3,832.96
Tk 120.00
Tk 60.00
Tk 52.50
Tk 17.50
Tk 105.00
Tk 52.50
Tk 75.00
Tk 200.00
Tk 80.00
Tk 70.00
Tk 480.00
Tk 70.00
Tk 5,215.46
Tk 521.55
Tk 521.55
Tk 6,258.55
TK 62.59
gc=9:1
cost
Tk 1,935.00
Tk 50.00
Tk 1,181.25
Tk 180.00
Tk 360.00
Tk 781.71 Tk 4,487.96
Tk 120.00
Tk 60.00
Tk 52.50
Tk 17.50
Tk 105.00
Tk 52.50
Tk 75.00
Tk 200.00
Tk 80.00
Tk 70.00
Tk 480.00
Tk 70.00
Tk 5,870.46
Tk 587.05
Tk 587.05
Tk 7,044.55
TK 70.45
, fitting and fixing steel glazed window with Z-section,T-section & FI bars etc.
4 1.5 24.00rft
With wastage 5% 25.20rft 8.04lbs @ tk 7.71
15 sft @ tk 24.00
elding,cutting,finishing in/c supply of electrode)
xing in position
1 no @ tk 15.00
15 sft @ tk 20.00
15 sft @ tk 6.00
Sub total
10 %
3.50 %
4.50 %
wastage 5%
lbs/rft
x 5 = 17.5 rft
x 4 = 18 rft
x 30 = 60 rft
100.275 rft
47.93145 lbs @ tk 7.71
xing in position
1 no @ tk 15.00
10 %
3.50 %
4.50 %
B. Fittings cost
Iron tower bolt 1 1.00 each ### Tk 24.00
socket bolt 9"lo 1.00 each ### Tk 22.00
hinges 4" long 4.00 each ### Tk 40.00
nickle plated ha 2.00 each ### Tk 26.00
iron screw 1/2" 2.00 dzn Tk 7.00 Tk 14.00
hinged cleats and
buffer block LS Tk 37.75
C. Labour cost
carpenter 3.00 each ### Tk 480.00
helper 5.00 each ### Tk 400.00
Total Tk 3,434.25
C. Miscellaneous cost
overhead & sund 10% Tk 343.43
contractor's prof 10% Tk 343.43
Total cost ###
RATE PER SFT Tk 201.13
LOCAL CARRIAGE 1 LS 50
LOCAL CARRIAGE 1 LS 80
COST ANALYSIS FOR 100 SFT 140 MM DEPTH CONCRETE CEILING BLOCK IN R
A-2 COST OF LABOUR & EQUIPMENTS FOR 100 SFT FLOOR AREA
SL. NO. DESCRIPTION OF WORKS QTY UNIT RATE (Tk.)
1 FOREMAN 0.1 NOS. 300
2 TECHNITION 0.25 NOS. 250
3 SKILLED LABOUR 1 NOS. 120
4 LABOUR 1 NOS. 100
TOTAL
SO COST FOR 100 SFT OF SHUTTERING : TK. 2325.94
MATERIALS
LABOUR,EQIP.
SHUTTERING
TOTAL
Contractors profit 10%
Over head expence 2.50%
VAT & IT 7.50%
COST FOR 100 SFT GRAND TOTAL
COST OF EACH BLOCK WITH LABOUR AND SHUTTERING WHEN USED IN CEILING AND ROOF TK.
R.C.C. work in individual and continuous footing
level.
60DB-Fy415MPa A. COST OF CONCRETE FOR 100 CFT :
A-1 COST OF MATERIALS
cost SL. NO. DESCRIPTION OF WORKS
2,650.00 a)COST OF brick CHIPS
52.50 b) SAND fm 1.8
c)CEMENT
70.00
187.50
60.00 A-2 COST OF LABOUR & EQUIPMENTS( for 600 cft) :
Tk 3,020.00 SL. NO. DESCRIPTION OF WORKS
d) H. MASON
0.00 e) MASON
302.00 f) SKILLED LABOUR
Tk 3,322.00 g) LABOUR
Tk 66,440.00 gf h) MIXTURE MACHINE
I) VIBRATOR
70,550.26 CONCRETE
LABOUR,EQIP.
wooden SHUTTER
TOTAL
Contractors profit 0.1
Over head expences 0.025
VAT & IT 0.075
COST FOR 100 CFT GRAND TOTAL
tk 4738.12
03.00% tk 142.14
= tk 4880.26 tk 116.20 /sft
each = tk 250.00
each = tk 60.00
each = tk 78.20
each = tk 78.00
ls = tk 40.00
= tk 506.20
each = tk 125.00
each = tk 80.00
L.S = tk 100.00
= tk 305.00 tk 7.26 /sft
each = tk 250.00
each = tk 160.00
each = tk 75.00
each = tk 50.00
tk 535.00 tk 12.74 /sft
each = tk 49.50
each = tk 39.60
doz = tk 18.00
Sub total (labour f/f) = tk 107.10 tk 7.14 /sft
= tk 369.55
each = tk 49.50
each = tk 39.60
doz = tk 18.00
Sub total (labour f/f) = tk 107.10 tk 6.80 /sft
h seasoned wood
g
sft- single leaf
AMOUNT (Tk.)
1728
153
676
20
75
100
100
175
25
125
20
3197
319.7
79.925
239.775
3836.4
LOCK WORK
AMOUNT (Tk.)
2062.25
299
51.3
200
175
100
50
2937.55
293.755
73.43875
220.31625
3525.06
LOCK WORK
AMOUNT (Tk.)
3446.5
455
77.4
400
175
100
80
4733.9
473.39
118.3475
355.0425
5680.68
AMOUNT (Tk.)
2850
2850
FLOOR AREA
AMOUNT (Tk.)
30
62.5
120
100
312.5
AMOUNT (Tk.)
1146.6396
14872.96
18660.8448
9600
720
45000.4444
2812.527775
1400
400
1800
113400
14400
127800
4260
2240
7443
2850
313
2325.94
5488.94
548.894
137.2235
411.6705
6586.728
87.82304
dividual and continuous footings of column at plinth
level.
E FOR 100 CFT : 1 1.5 3
83 CFT 75 6225
42 CFT 18 756
22 BAG 380 8360
L.S. tk 25.00
Total of Cost = tk 466.33
cft of conc work = tk 1295.37
7819.43272444 7835.1498448148
1.2 1.28 2.57 3900
2.2 2.31 4.62 3900
1.2 1.25 2.53 4000
1.15 1.19 2.39 4100
1.3 1.36 2.73 4100
CIVIL WORK Estimate for a 3-storied Building at Gazipur
Subject : Ground Floor i/c. Foundation,gb,col,1fb,1fs(p),dw.
1 R.C.C Work(1:1.5:3) with 50% Sylhet &50%Local Sand. a)With stone Chips
column 11.14 cum 0.50 % Cement 0.22 1,671 Bag 380.00 635,092.09
lintel/beam 9.66 cum 3.00 % Sylhet Sand 0.20 1,606 Cft 24.00 38,539.56
cft
lift core 14.79 cum 4.00 % Local Sand 0.20 1,621 Cft 16.00 25,942.49
7,621.99
stair1 3.03 cum 2.00 % Stone Chips 0.82 6,361 Cft 90.00 572,480.89
stair2 5.07 cum
messanine floor 172.29 cum
R.C.C Work(1:2:4) with 50%Sylhet &50%Local Sand.b)With Brick Chips
0.10 cum 0.50 % Cement 0.17 1 Bag 380.00 231.04
cum 3.00 % Sylhet Sand 0.16 1 Cft 24.00 14.02
3.53 cft
cum 4.00 % Local Sand 0.16 1 Cft 16.00 9.44
5.00 % Brick Chips 0.64 2 Cft 70.00 166.75
2 Re-inforcement work
60-Grade D. bar for col. 13.30 Ton 2.00 % 13.30437763 ton Rebar 1.00 13.57 Ton 60,000.00 814,227.91
40-Grade D. bar for gf slab. 0.00 Ton 2.00 % 0.10 ton Rebar 1.00 0.102 Ton 50,000.00 5,100.00
3 Shuttering work 586.43 Sqm. 1.00 % 6,312.365 sft
4 10" & above Brick works (1:6)
0.31 Cum 2.00 % 10.94 cft Cement 0.043 0.48 Bag 380.00 182.33
2.00 % Local Sand 0.32 3.58 Cft 15.00 53.73
2.00 % Bricks 11.00 123 Nos. 6.50 797.85
5 5"Brick work (1:5)
2.00 % Cement 0.05 0.05 Bag 380.00 20.86
0.1 Sqm. 1.08 Sft
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.35 0.38 Cft 15.00 5.76
2.00 % Bricks 5.00 5.49 Nos. 6.50 35.68
6 1/2" cement plaster (1:4) with NCF
2.00 % Cement 0.0100 1.10 Bag 380.00 417.21
10 Sqm. 107.64 Sft
2.00 % Local Sand 0.08 8.78 Cft 15.00 131.75
7 3/4"Cement plaster (1:6)
2.00 % Cement 0.01 0.01 Bag 380.00 4.17
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.08 0.09 Cft 15.00 1.32
2.00 % S.Paper 0.50 Doz. 22.00 11.00
8 Window/verandah Grill 0.1 Sqm. 5.00 % 1.0764 Sft steel 1.00 1.13 Kg 120.00 129.17
9 Dismantling works 1 L.S
10 Repairing works/others 1 L.S
TOTAL tk 2093595
azipur
tk 180197 tk 2273992
CIVIL WORK Estimate for a 3-storied Building at Gazipur
Subject : Ground Floor i/c. Foundation,gb,col,1fb,1fs(p),dw.
Materials Detail Mat. Cost La. Rate La. Cost Total Cost Remarks
SL Item of works Qty Unit wastage Qty Unit
Type Quantity Unit Rate Tk. Tk Tk Tk
1 Lay out & site preparation 1,560.00 Sqm. 16791.84 sft L.S 8,000.00
2 Earth Work 937.46 cum 33,082.96 cft 2.50 cft 82,707.41 82,707.41 tk2.50/cft
3 Soling in fdn. & floor Sqm. 2.00 % sft Bricks/Sft 3.00 15,155.36 No 6.50 98,509.83
460.12 4952.73 2.00 sft 9,905.46 111,446.37 tk22.50/sft
2.00 % sand(cft/Sft) 0.06 303.11 cft 10.00 3,031.07
4 Polythine Laying 3,252.50 Sqm. 4.00 % 35,009.91 sft Polythene 36,410.31 Sft 0.75 27,307.73 0.25 sft 8,752.48 36,060.21 tk1.03/sft
5a Sand & Khoa compaction below footing:
40 : 60 507.00 cum 5.00 % 17,892.03 cft khoa 0.40 7,514.65 cft 70.00 526,025.68 4.00 cft 71,568.12 707,093.03 tk39.52/cft
2.00 % sand 0.60 10,949.92 cft 10.00 109,499.22
5b Sand & Khoa filling for compaction below Slab:
1 :30 :20 5.00 % khoa 0.39 5,332.94 cft 70.00 373,305.92
tk44.84/cft
367.00 cum 2.00 % 12,951.43 cft sand 0.59 7,770.86 cft 10.00 77,708.58 4.00 cft 51,805.72 580,792.91
1.00 % cement 0.01569 205.19 bag 380.00 77,972.69
6 C.C Work in foundation & floor
0.50 % Cement 0.12 0.34 Bag 380.00 129.38
tk126.57/cft
0.08 cum 2.00 % 2.82 cft L/Sand 0.45 1 Cft. 10.00 12.96 10.00 cft 28.23 357.33
5.00 % B/Chips 0.90 3 Cft 70.00 186.75
7 R.C.C Work(1:1.5:3) with 50% Sylhet &50%Local Sand. a)With stone Chips
footing 169.00 cum 0.50 % Cement 0.22 1,630 Bag 380.00 619,343.57
short col 13.50 cum 2.00 % Sylhet Sand 0.20 1,551 Cft 24.00 37,219.00
cft 11.00 cft 81,762.87 1,259,634.65 tk169.47/cft
GB 11.01 cum 3.00 % Local Sand 0.20 1,566 Cft 16.00 25,055.93
7,432.99
lift core 16.90 cum 2.00 % Stone Chips 0.82 6,203 Cft 80.00 496,253.29
stair 0.214 cum 2.00 %
cum 2.00 %
R.C.C Work(1:2:4) with 50%Sylhet &50%Local Sand.b)With Brick Chips
GF 161.90 cum 0.50 % Cement 0.17 984 Bag 380.00 374,060.44
cum 2.00 % Sylhet Sand 0.16 937 Cft 24.00 22,478.89
5,713.59 cft 11.00 cft 62,849.47 744,488.68 tk130.30/cft
cum 3.00 % Local Sand 0.16 946 Cft 16.00 15,132.85
5.00 % Brick Chips 0.64 3,857 Cft 70.00 269,967.03
8 Re-inforcement work
60-Grade D. bar for col. 18.95 Ton 2.00 % 18.95208943 ton Rebar 1.00 19.33 Ton 60,000.00 1,159,867.87 1,500.00 ton 28,428.13 1,188,296.01 tk61.47/kg
40-Grade D. bar for gf slab. 12.06 Ton 2.00 % 0.10 ton Rebar 1.00 0.102 Ton 50,000.00 5,100.00 1,500.00 ton 150.00 5,250.00 tk51.47/kg
9 Shuttering work 595.70 Sqm. 1.00 % 6,412.134 sft 12.00 sft 76,945.61 76,945.61
10 Sand filling with vitty sand. 1 cum 3.00 % 35.29 cft V.Sand 1.20 43.62 Cft 9.00 392.57 3.00 cft 105.87 498.44
11 10" & above Brick works (1:6)
0.31 Cum 2.00 % 10.94 cft Cement 0.043 0.48 Bag 380.00 182.33
4.50 cft 49.23 1,083.14
2.00 % Local Sand 0.32 3.58 Cft 15.00 53.73 4.50 cft 49.23 1,083.14 tk 99.01 /cft
2.00 % Bricks 11.00 123 Nos. 6.50 797.85
12 5"Brick work (1:5)
2.00 % Cement 0.05 0.05 Bag 380.00 20.86
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.35 0.38 Cft 15.00 5.76 4.00 cft 4.31 66.61 tk 61.89 /sft
2.00 % Bricks 5.00 5.49 Nos. 6.50 35.68
13 1/2" cement plaster (1:4) with NCF
2.00 % Cement 0.0100 0.01 Bag 380.00 4.17 3.50 Sft 3.77 9.26 tk 8.60 /sft
0.1 Sqm. 1.08 Sft
2.00 % Local Sand 0.08 0.09 Cft 15.00 1.32
14 3/4"Cement plaster (1:6)
2.00 % Cement 0.01 0.01 Bag 380.00 4.17
0.1 Sqm. 2.00 % 1.08 Sft Local Sand 0.08 0.09 Cft 15.00 1.32 3.50 Sft 3.77 20.26 tk 18.82 /sft
2.00 % S.Paper 0.50 Doz. 22.00 11.00
15 Window/verandah Grill 0.1 Sqm. 5.00 % 1.0764 Sft steel 1.00 1.13 Kg 120.00 129.17 25.00 Sft 26.91 156.08
16 Dismantling works 1 L.S 100.00
17 Repairing works/others 1 L.S 100.00
2852.70 0.00
847 2852.70 1.515 % 1.515 % 0.000 % 2274.31 sft
lift core 2
204.22 407.67 0.898 % 407.67 0.00 70.87 sft BASE
174.14 282.36 0.730 % 282.36 0.00 432.59 sft WALL UPTO PL
4654.26 0.00
1315 4654.26 1.592 % 1.592 % 0.000 % 3344.28 sft
SECOND FLOOR
175.83 18542.82 547.92 19090.74 7539.77 2% 7690.57
THIRD FLOOR
175.83 18542.82 547.92 19090.74 7539.77 2% 7690.57
TOTAL
516.88 55422.38 1651.02 57073.40 22540.80 2% 22991.61
SUB TOTAL IN KG
1.12 % TOTAL IN KG
Y
above pl
rod shutter
0.00 kg 0.00 sft
0.00 kg 0.00 sft
0.00 kg 0.00 sft
2486.45 kg 1930.28 sft
3964.23 kg 2840.82 sft
1152.29 kg 936.55 sft
1819.03 kg 1176.50 sft
0.00 kg 0.00 sft
4713.30 kg 7079.40 sft
2786.21 kg 4966.51 sft
22991.61 kg
RCC
Clear cover casting rod BOTTOM LONG BAR
Width (ft) T (ft) t (ft) S (ft) DIA MM spacing
wastage wastage mm c/c
2.952 2.46 0 0 75.00 mm 0.00 % 0.00 % 20 96
11 1.25 0 0 75.00 mm 0.00 % 0.00 % 20 150
9 1 0 0 75.00 mm 0.00 % 0.00 % 16 175
10 1 0 0 75.00 mm 0.00 % 0.00 % 16 150
10.5 1.25 0 0 75.00 mm 0.00 % 0.00 % 16 125
8 0.833 0 0 75.00 mm 0.00 % 0.00 % 16 200
8 1 0 0 75.00 mm 0.00 % 0.00 % 16 200
0 0 0 0 75.00 mm 0.00 % 0.00 % 16 200
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 250
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 300
0 0 0 0 75.00 mm 0.00 % 0.00 % 20 250
REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod MAIN BAR
wastage wastage
corner bar DIA MM
REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage
TOP bar DIA MM
REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage MAIN BAR
NO OF bott DIA MM
bar long
1 9.25 8.04 1.33 75.00 mm 1.00 % 2.00 % 12 16
1 24.15 0.82 5.91 45.00 mm 1.00 % 2.00 % 70 10
1 22.67 0.67 41 20.00 mm 1.00 % 2.00 % 70 10
3
REINFORCEMENT
Clear cover casting rod
No. Length (ft) Width (ft) H (ft)
wastage wastage MAIN BAR
REINFORCEMENT
rebar_length
rebar_width length1 length2
47 30 1387.5 877.2
45 30 1078.92 701.76
45 28 251.748 151.928
47 28 259 151.928
47 33 305.25 212.289
45 31 278.721 190.867
47 94 869.5 1750.75
47 58 536.5 668.392
45 33 293.04 212.289
45 30 532.8 350.88
55 30 327.9 175.44
51 30 303.54 175.44
48 28 263.284 151.928
45 18 158.58 62.28
47 13 120.25 32.214
47 8 74 11.856
45 5 44.955 4.815
21 33 137.61 212.289
13 30 77.22 175.44
subtotal 7300.318 6269.985
total 13570.3 m
T Weight of rod 12058.9 KG
0.95 %
REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod
wastage wastage MAIN BAR
REINFORCEMENT
No. Length (ft) Width (ft) H (ft) Clear cover casting rod
wastage wastage
corner bar DIA MM
RCC REINFORCEMENT
Clear cover casting rod BOTTOM LONG BAR BOTTOM SHORT BAR
Width (ft) T (ft) DIA MM spacing DIA MM spacing
wastage wastage mm c/c mm c/c
131.04 0.416 20.00 mm 1.00 % 2.00 % 20 150 20 150
0.82 0.416 20.00 mm 1.00 % 2.00 % 20 150 20 150
20.11 0.416 20.00 mm 1.00 % 2.00 % 16 175 16 175
11.11 0.416 20.00 mm 1.00 % 2.00 % 16 150 16 150
6.46 0.416 20.00 mm 1.00 % 2.00 % 16 125 16 125
0 0 20.00 mm 1.00 % 2.00 % 16 200 16 200
TOTAL
VOLUME OF STEEL RATIO
STEEL (m3)
0.97 0.59
0.98 0.56
0.98 0.56
2.93 0.57
35.60
65.56
18.35
24.60 68700.00 8.00 32.95 16.82 49.77 120.24 37.64 16.45
10.72
8.81
163.64306
77.48
182.49 76200.00 10.00 45.68 40.72 86.41 130.12 41.02
38.52
0.00
298.48172
43.97
79.09 68700.00 4.00 16.48 30.08 46.56 57.26 23.59
16.34
139.40293
601.5277 TOTAL IN CFT 182.7 TOTAL IN SFT
36.64
91.31 57404 11 37.79 21.73 59.52 130.12 53.70 16.45
19.23
10.72
10.41
168.32187
209.28206
345.61534 TOTAL IN CFT 139.1 TOTAL IN SFT
REINFORCEMENT
BOTTOM SHORT BAR TOP LONG BAR TOP SHORT BAR SIDE BAR BOTTOM LONG BAR
1.37195121951 0 0 0 0 0 0
13.48 0 5 16 5.46 0 10 12 1
0 0
7.02256 0 4 16 6.59 0 8 12 0.95
1.37195121951 0 0 0 0 0 0 0 0
4.82 0 5 16 5.012 0 10 12 0.96
MAIN BAR
t long s DIA MM t short s b DIA MM
L m anch/lapp m b L m anch/lapp m L m
315.173780488 18.91 0 0 0.304878 0.00 0 0 0.304878
148.445121951 8.91 0 0 0.304878 0.00 0 0 0.304878
0 0.00 0 0 0 0.00 0 0 0
TOP LONG BAR TOP SHORT BAR SIDE BAR BOTTOM LONG BAR BOTTOM SHORT BAR
DIA MM spacing DIA spacing DIA MM all-around DIA MM ONE ROD DIA MM
mm c/c MM mm c/c no LENGTH M
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
0 100 0 100 0 2
huttering for stair
TOTAL shuttering
sft.
174.33
171.13
80.85
426.3211
sft.
200.27
151.23
351.51
BOTTOM LONG BAR BOTTOM SHORT BAR TOP LONG BAR TOP SHORT BAR
ONE ROD DIA MM ONE ROD DIA MM ONE ROD DIA MM ONE ROD
LENGTH M LENGTH M LENGTH M LENGTH M
0.9 12 0.9 12 0.9 12 0.9
1.5 22 -0.992
1.47 16 -0.75
1.7 16 -1.5
STIRRUPS
set1 set2 set3
DIA MM length m nos DIA MM length m nos DIA MM
anch/lapp m mm/cc str spacing nos
0.00 250 1262.00 10 0.86 1 0 0.86 0 0
0.00 250 595.00 10 0.86 1 0 0.86 0 0
0.00 250 2.00 0 -0.16 1 0 -0.16 0 0
1.27 1
1.24 1
1.02 0
1.32 0
0.62 0
1.17 0
0.76 0
0.61 0
-0.15 0
set3
length m nos
9.47 1
14.95 1
14.16 1
13.04 1
21.93 1
20.94 1
set3
length m nos
0.00 1
12.24 1
13.53 1
2.39 1
5.40 1
17.12 1
5.88 1
set3
length m nos
0.25 1
0.25 1
0.25 1
set3
length m nos
0.86 0
0.86 0
-0.16 0
RHD STANDARD
ANALYSIS OF CAST IN-SITU PILES
:
Selected Office : Chittagong
Item Type : Foundation Works
Sub-Total : 1255.63
9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing Tk 9700.00 Per % 0 Nos.
bricks
200 x 100 x 50 mm/8" x 4" x 2" machine made hard pressed klinker facing Tk 10625.00 Per % 0 Nos.
bricks
200 x 50 x 50 mm/8" x 2" x 2" machine made klinker facing strips Tk 7000.00 Per % 0 Nos.
200 x 62 x 50 mm/8" x 2.5" x 2" machine made klinker red strips Tk 7750.00 Per % 0 Nos.
M.S. plain bar and F.I. bar (non-structural use) Tk 59000.00 Per M. ton
Solid square bar Tk 64000.00 Per M. ton
0.45 mm thick C.I. sheet:/ G.P. sheet Tk 79000.00 Per M. ton
0.45 mm thick colored C.I. sheet: Tk 100000.00 Per M. ton
0.27 mm thick 6'-0" x 18" ridging: Tk 400.00 Per pc.
0.27 mm thick 6'-0" x 18" colored ridging: Tk 450.00 Per pc.
11 TIMBER/BOARD/TIMBER PRODUCT
Garjan/Jam/local Sal Tk 1300.00 Per cft.
Mehgani Tk 1350.00 Per cft.
Silkarai/Chikrashi Tk 1800.00 Per cft.
Teak-Chambal Tk 2500.00 Per cft.
Chittagong teak Tk 3600.00 Per cft.
Kathal Tk 1500.00 Percft.
Gamari Tk 1500.00 Per cft.
Chapalish Tk 1600.00 Per cft.
Timber for form work Tk 350.00 Per cft,
Bamboo Tk 6.00 Per rft.
Shal ballah (avg. dia 6") for driving Tk 50.00 Per rft.
Burma teak veneered flush door shutter Tk 252.00 Per sft.
Champ veneered flush door shutter Tk 174.00 Per sft.
Chapalish veneered flush door shutter Tk 174.00 Per sft.
Garjan veneered flush door shutter Tk 152.00 Per sft.
12 mm thick Plain Particle board Tk 40.00 Per sft.
Melamine board (8 mm thick): 8' -0" x 4'-0" size Tk 1800.00 Per pc.
9 mm thick gypsum board Tk 20.00 Per sft.
9 mm thick perforated gypsum board Tk 23.00 Per sft.
12 mm thick laminated vinyl board Tk 31.00 Per A,
9 mm thick B.T. veneered board Tk 84.00 Per sit.
Burma teak Tk 3750.00 Per cft.
50 mm thick glass wool Tk 173.00 Per sft.
Rubber gum Tk 500.00 Per kg.
PVC water stopper Tk 175.00 Per rft.
12 PROPS PIPES I-SECTION BOX CHANNEL FOR CONCRETING WORK
Bamboo prop in/c top supports Tk 80.00 each
Salballah prop in/c top supports Tk 625.00 each
50 mrn/2"dia M.S. pipe Tk 146.00 Per rft.
38 mm/1.5" dia M.S. pipe Tk 110.00 Per rft.
50 mm/2" dia G.I. pipe Tk 165.00 Per rft.
38 mm/1.5" dia G.I. pipe Tk 120.00 Per rft.
19 mm/3/4" dia G.I. pipe Tk 50.00 Per rft.
13 mm/1/2" dia G.I. pipe Tk 30.00 Per rft.
Adjustable mechanism in/c top and bottom plate Tk 450.00 Per set
I-section joist to support inclined prop Tk 115.00 Per rft.
4" x 2" M.S. box channel with 1/8" thick ms sheet Tk 125.00 Per rft.
Steel prop with adjustable rnechanism in/c top & bottom plate Tk 2235.00 Per set
Turn-buckle ink tie rod Tk 300.00 Per set
13 GLAZED/MARBLE[TERAZZO TILES
18 mm thick marble stone, Black/white (Indian) Tk 290.00 Per sft.
16 mm thick marble stone, Black/white (Indian) Tk 260.00 Per MI.
12 mm thick marble stone, Black/white (Indian) Tk 240.00 Per sft.
18 mm thick colored/ grey marble stone (Indian) Tk 300.00 Per sft.
16 mm thick colored/ grey marble stone (Indian) Tk 270.00 Per sft.
12 mm thick colored/ grey marble stone (Indian) Tk 250.00 Per sft.
18 mm thick colored/ grey marble stone (Italian) Tk 460.00 Per sft.
White wall tiles of different sizes ,/ Tk 42.00 Per sft.
Colored wall tiles of different sizes Tk 44.00 Per sft.
Special design colored wall tiles of different sizes Tk 46.00 Per sft.
GP (Glazed homogeneous) 300x300 mm floor tiles Tk 48.00 Per sft.
GP (Glazed homogeneous) 400x400 mm floor tiles Tk 52.00 Per sft.
GP (Mirror polished) 300 x 300 mm floor tiles Tk 100.00 Per sft.
GP (Mirror polished) 400 x 400 mm floor tiles Tk 111.00 Per sft.
GP (Mirror polished) 600 x 600 mm floor tiles Tk 130.00 Per sft.
GP 300 x 300 mm stair tiles Tk 52.00 Per sft.
unglazed homogeneous Floor Tiles 300 x 300 mm Tk 51.00 Per sft.
unglazed homogeneous Floor Tiles 400 x 400 mm Tk 56.00 Per sft.
pasting tiles adhesive Tk 14.00 Per kg.
tiles grout / joint filler Tk 80.00 Per kg.
acid stone Tk 300.00 each
water proofing paper 12 size Tk 15.00 each
water proofing paper 320 size Tk 18.00 each
ADDITIONAL COST CHART
Sheet1
1. Saline zone, to use concrete of min f'c = 25 mpa 1.00 % of PLAR
5. Roof-top R.C.C. water tank in/c beams & supports etc. Tk 100.00 per gallon
size brick pillar @ 2.44 meter c/c, of height 1.52 meter above G.L and
0.76 m below G.L. and R.C.C. coping of 75 mm thick and 375 mm
width, 12 mm thick plaster (1:6) in both sides of the wall inc
(ii) Bituminous
Carpeting Road
Tk 1472.00 Per rm
GT =
AMOUNT
(in Taka)
2,552,972.56
1,426,000.00
14,850.00
6,840.61
wires etc.comple
a) 40 grade (fy-276 M pa) 10.00 Ton
03 250 mm THICK BRICK WORK
250 mm thick brick work with 1st class bricks in cement
mortar (1:6) interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for at least 7
days in ground floor etc. complete as per direction of the
Engineer-in-char 1.00 cum
04 125 mm THICK BRICK WORK with 1st class bricks in cement
mortar (1:4) interstices with mortar, racking out joints, cleaning and
soaking the bricks before use, curing for at least 7 days in ground
06 PAINTING WORKS
Painting work with Plastic paint (Berger/Elite) of approved
base and raking out the joints with white cement including
8,280.00 8280.00
7,500.00 637500.00
8,350.00 41750.00
8,580.00 25740.00
8,580.00 60060.00
63000.00 630000.00
4,450.00 4450.00
580.00 464000.00
156.00 1560.00
140.00 312267.66
145.00 280095.27
137036.00 137036.00
6600.00 396000.00
1076.00 80700.00
1090.00 1090.00
2591.00 194325.00
960.00 91200.00
940.00 479400.00
29.00 16240.00
Total = 3861694
wires etc.comple
a) 40 grade (fy-276 M pa) 10.15 Ton
03 250 mm THICK BRICK WORK
250 mm thick brick work with 1st class bricks in cement
mortar (1:6) interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for at least 7
days in ground floor etc. complete as per direction of the
Engineer-in-char 1.00 cum
04 125 mm THICK BRICK WORK with 1st class bricks in cement
mortar (1:4) interstices with mortar, racking out joints, cleaning and
soaking the bricks before use, curing for at least 7 days in ground
06 PAINTING WORKS
Painting work with Plastic paint (Berger/Elite) of approved
base and raking out the joints with white cement including
8,280.00 8280.00
7,500.00 637500.00
8,350.00 41750.00
8,580.00 25740.00
8,580.00 60060.00
63000.00 639453.15
4,450.00 4450.00
580.00 464000.00
156.00 1560.00
140.00 312267.66
145.00 280095.27
137036.00 137036.00
6600.00 396000.00
1076.00 80700.00
1090.00 1090.00
2591.00 194325.00
960.00 91200.00
940.00 479400.00
29.00 16240.00
Item Description Quantity Unit Rate Amount Unit Rate Quantity Unit Rate Amount Unit Rate
No. (in Tk.) (in Tk.) (per Sft) (in Tk.) (in Tk.) (per Sft)
1
Transportation charge from our Factory to the
- L. S. - 185,294 L. S. - 185,294
Project Site will be borne by us at actual (approx).
PILING COST
BASEMENT COST ( UPTO GFL ) 1 X 4907 sft = 4907 sft
GF COST 1 X 4907 sft = 4907 sft
TYPICAL FLOOR 5 X 4907 sft = 24535 sft
Total Floor area = 34349 sft
Extra cost for Rooftop & Chilakotha. @ Tk. 160.00
Cost of roof top RCC water tank 2000 IG @ Tk. 95.00
Sanitary Works 31896 /sft @ TK 100.00 /ft2
Electrical Works 31896 /sft @ TK 122.00 /ft2
Labour above
Machine Charge
Construction of under ground reservoir : 10000 IG @ Tk. 40.00
Gate (MS,GI PIPE,) 1.00 nos 150.00 sft @ Tk. 700.00
Boundary wall (without B.W. fencing) R.C.C. frame 300.00 ft long @ Tk. 1500.00
1300000 = 1300000
300000 = 300000
150000 = 150000
150.00 = 126090
140.00 = 686980
95 = 190000
40 = 360000
250.00 = 32500
1500.00 = 450000
TK 700.00 /sft = 105000
9.00 = 333676
100000 = 100000
GT = 10056264