Activity detail Duration(hr)

Removal of 4"-NG-1314-B51-D1 1
Removal of 4"-NG-1314-B51-D2 4
Day1 Removal of 4"-NG-1314-B51-D3 3
Flow meter FT-330 1
Transfer of the decommissioned spool to laydown area 1
Installation of 3"-HG-1111-001-B01-SP2 3
Day 1night Installation of 6"-HG-1111-002-B01-SP1 4
Installation of FT-330 1
Removal of valve 1 1
Removal of PV-332 1
Removal of 6"-NG-1203-C51_D1 2
Day 2
Removal of 6"-NG-1203-C51_D2 2
Removal of 6"-NG-1203-C51_D3 3
Transfer of the decommissioned spool to laydown area 1
Removal of 6"-NG-1203-C51_D4 3
Installation of 3"-HG-1111-001-B01-SP1 1
Day2 night
Installation of 3"-HG-1111-001-B01-SP1A 1
Flange management system on installed spools 2
Removal of valve 2 1
Removal of 6"-NG-1203-C51_D4 3
Day3 Removal of 6"-NG-1310-C51_D1 3
Removal of 6"-NG-1310-C51_D2 2
Transfer of decommissioned spools 2
Removal of 6"-NG-1310-C51_D3 2
Removal of 8"-FS-1206-B51_D1 2
Day 3 night
Removal of valve 3 2
Continue FMS on installed spools 4
Removal of 8"-FS-1206-B51_D2 2
Removal of 8"-FS-1206-B51_D3 3
Day 4
Installation of cartex plug + pipe edge preparation 0.2
Transfer of the decommissioned spool & new spools 2
Installation of 8"-HG-1111-004-B01-SP1 5
Fit up and welding of 3"-HG-1111-001-B01-SP1A +NDT 3
Day4 night Installation of 6"-HG-1111-002-B01-SP4 1
Installation of 11GV-451 0.5
DRT on welded joint 0.5
Installation of 6"-HG-1111-002-B01-SP3 2
Installation of 11BV-405 2.5
Day5
Installation of 6"-HG-1111-002-B01-SP2 3
Installation of SDV-326 2
Installation of 6"-HG-1111-003-D01-SP6 1
Installation of 11CV-487 1.5
Day5night
Installation of 6"-HG-1111-003-D01-SP6A 0.5
Flange management system on installed spools 4
Installation of PV-332(rigging, position, gasket &bolting) 2.5
Installation of 6"-HG-1111-003-D01-SP5 2
Day 6
Installation of 11BV-402 (rigging, position, gasket &bolting) 2
Glanding and termination of cables on valves + tubing 1
Installation of 6"-HG-1111-003-D01-SP3/4 2.5
Day 6night Rigging & positioning of 6"-HG-1111-003-D01-SP2.1 + 2 4
Erection of scaffold and spark conrainment in prep for welding 1
Fit up and welding of 6"-HG-1111-003-D01-SP2.1 + 2 joint 5
Installation of 6"-HG-1111-003-D01-SP2A 1.5
Day7
Installation of 6"-HG-1111-003-D01-SP1 2
Installation of valve 3 1.5
Day7 night DRT + FMS 10
Fit up and welding of 8"-HG-1111-004-B01-SP1B 6
Day8 fit up and welding of pipe support 2nos (welding) 2
Alignment and insertion of shim and teflon on supports 1
Day8 night DRT + FMS 10
Day9 Tubing and cable work E&I + FMS 10
Day9 night Preparation for leak test 10
Day10 Leak test 10