You are on page 1of 2

Doc Ref No: FORM PD 14

VR ENGINEERING UNIT - 2 Rev no:1


Daily process Monitoring(Tempering) Date :29.06.23

Loading Qty per


Loading tray No.of parts per
Sl.No. WO NO Part no Size
no tray
batch Loaded by Monitored by Un-Loaded by Approved by

10

11

12

13

14

15

16

17

18

19

20

21

22

Note: Alarm system is for Set tempering temperature reaching & Set Soaking time finishing
Doc Ref No: FORM PD 14
VR ENGINEERING UNIT - 2 Rev no:1
Daily process Monitoring(Tempering) Date :29.06.23

process Monitoring parameters

Tempering temp(°c)
SL.NO. Date Shift Primary temp Starting time Tempering temp(°c) Soaking time Air Cooling time Temper delay time
Reaching time
(°c) (AM/PM) (as per process spec)
(AM/PM) (AM/PM) (AM/PM) (max 8hr)

10

11

12

13

14

15

16

17

18

19

20

21

22

Note: Alarm system is for Set tempering temperature reaching & Set Soaking time finishing