Project Name:
Reference No:
Table of Contents
1. Purpose......................................................................................................................................3
2. Scope of Work...........................................................................................................................3
3. Definition...................................................................................................................................3
1.1 Abbreviation..........................................................................................................................3
1.2 “Approved” or “Approval”.....................................................................................................3
1.3 “Shop Drawings”....................................................................................................................3
1.4 “Final Inspection”..................................................................................................................3
1.5 “Materials”............................................................................................................................3
1.6 “Method Statements”............................................................................................................4
4. Reference Documents – Specifications, Drawings. Etc..............................................................4
5. Manpower.................................................................................................................................4
Staff:..................................................................................................................................................4
Labour...............................................................................................................................................4
6. Responsible Personnel on Site...................................................................................................5
7. Material Inspection / Storage....................................................................................................5
8. MATERIALS................................................................................................................................6
9. HANDLING & STORAGE..............................................................................................................6
10. Installation General Requirements........................................................................................6
11. INSTALLATION PROCEDURE GENERAL FOR INSTALLATION OF LIGHT FITTINGS LUMINARY’S
EXTERIOR INTERIOR...........................................................................................................................6
12. INSPECTION...........................................................................................................................8
13. ATTACH MENTS.....................................................................................................................8
1. Purpose
The purpose of this Method Statement for Installation of light fittings luminary’s
exterior interior” to ensure that it complies to Project requirements, specifications
and standards.
2. Scope of Work
This Method Statement applies to all installation of light fittings luminary’s exterior
interior. Manpower and equipment shall be organized to meet the schedule as per
the approved construction program.
3. Definition
1.1 Abbreviation
QAQC - Quality Assurance Quality Control
MS - Method Statement
MEP - Mechanical, Electrical, Plumbing
RFIA - Request for Inspection & Approval
MIR - Materials Inspection Request
ITP - Inspection and Test Plan
TBT - Tool Box Talk
1.5 “Materials”
“Materials” means all items covering the materials or equipment delivered to the
site that must be incorporated in the project.
Following tools shall be required for the installation of light fittings & fixtures.
5. Manpower
Staff:
1. Construction Manager
2. Site Engineer
3. Supervisor
4. QC Engineer / Inspector
5. Quantity Surveyor
6. Safety Officer
Labour
1. Foreman
2. Trade workers
3. Helpers / Labours
4. Drivers
8. MATERIALS
T HE Iinstallation of light fittings luminary’s exterior interior accessories shall be in line with the
approved material submittal and approved drawings as per rules and standards.
3. The site Engineer (Electrical) has to ensure that all the lighting fixtures are
received at the site as per approved material submittal and as per approval.
4. Ensure all finishing works in all related areas are completed for the area of
installation and released/cleared by the civil section to proceed with the
installation of lighting fixtures.
5. The type of lighting fixtures is to be selected as per the approved schedule of
lighting and approved shop drawing.
6. 6. Lighting fixtures installed in exposed external areas shall be of weatherproof
type.
7. Lighting fixtures are to be installed inline and parallel with another line of fixtures
as per approved shop drawings and false ceiling drawings.
8. Heavy lighting fixtures shall be supported from the ceiling using galvanized caddy
clip and heavy gauge G.I. wire.
9. Lighting fixtures fixed in service areas, where there is no false ceiling, fittings are
to be fixed firmly using anchor bolts. minimum 6mm bolt and metal expansion
anchor rods.
10. Fixing of lighting fixtures above ducts, pipes, trays and trunking shall be avoided.
11. The connection between lighting fixtures and ceiling roses are to be made only
using heat resistance 3 core, 2.5 SQ mm or 1.5 SQ mm flexible / wires. wires.
12. Ceiling rose location shall be easily accessible and should be avoided installation
above AC ducts and cable trays.
13. All lighting fixtures shall be connected with earthing cable.
14. Before fixing lamps, all lighting fixtures are to be cleaned.
15. Gloves shall be used in works.
16. Correct lamps are to be fixed in lighting fixtures.
17. Installation of louvres shall be installed and protected by polyethene sheets.
18. Care should be taken in fixing the fitting louvres and avoiding fingerprints or dust
on the louvre
19. Before installation all wires should be tested, meggered and schedules should be
submitted to Engineers for approval and records shall be maintained.
20. GI boxes, round PVC boxes in concrete must be treated after plaster and the
edges shall be finished good and clean. Wall finish shall be done uniformly
around the box edges.
21. Test results should be submitted to the consultant for the records.
22. Ensure that where luminaries are fixed directly to conduit boxes the final circuit
connections are adequately protected against the heat transfer from the
luminaries
23. Fix a label at each luminary which is connected to more than one circuit to read
this luminary is connected to 'X' number of circuits and is supplied from
distribution board Ref. 'Y'. Isolate each circuit before working on the luminaire.
Agree on label location and format on site.
12.INSPECTION
Inspection for Installation of installation of light fittings luminary’s exterior interior ”.
13.ATTACH MENTS
1. Risk Assessment
2. Inspection &Test Plan
3. Quality Control Procedure.