Q1. SB Casting produces cast bronze valves on a 8-person assembly line. On a recent day, 160 valves
were produced during an 10-hour shift.
a) Calculate the labor productivity of the line.
b) Raja Adnan, the manager at SB, changed the layout and was able to increase production to 190 units
per 10-hour shift. What is the new labor productivity per labor-hour?
c) What is the percentage of productivity increase?

Q2. Given the activities whose sequence is described by the following table, draw the appropriate
activity-on-node (AON) network diagram.
a) Which activities are on the critical path?
b) What is the length of the critical path?

Quiz # 1
POM
BBA VI/M.Com IV
Q1. SB Casting produces cast bronze valves on a 8-person assembly line. On a recent day, 160 valves
were produced during an 10-hour shift.
a) Calculate the labor productivity of the line.
b) Raja Adnan, the manager at SB, changed the layout and was able to increase production to 190 units
per 10-hour shift. What is the new labor productivity per labor-hour?
c) What is the percentage of productivity increase?

Q2. Given the activities whose sequence is described by the following table, draw the appropriate
activity-on-node (AON) network diagram.
a) Which activities are on the critical path?
b) What is the length of the critical path?