You are on page 1of 5

LIFTING PLAN PROCEDURE

for
OVERHAUL HHP BOILER-III

0 5-Sep-23 FD Issued for Approval


REV. DATE BY DESCRIPTION CHECKED APPROVED COMPANY
Project Title

OVERHAUL HHP BOILER-III DI AREA POWER PLANT II


Customer/ Owner

PT. KILANG PERTAMINA INTERNATIONAL RU V

Contractor by

PT. INDOBOILER

Document No. Revision Status

IB.PS.PRJ.08 0 For Approval


Project No. Purchase Order No.

99.953.2023 008/KPI48000/2023-S0
Total or partial reproduction and/ or utilization of this document is forbidden without prior written authorization from
Indoboiler
TABLE OF CONTENT

Description Page

Cover Page 1
Table of Content 2
Revision Records 3
1. Lifting Plan Procedure 4
2. Load chart 5

Project No.
PT INDOBOILER 99.953.2023
Total or partial reproduction and/ or utilization of Document No.
this document is forbidden without prior written
authorization from Indoboiler
IB.PS.PRJ.08
REVISION RECORDS
REV. NO DATE DESCRIPTION REVISION PAGES
0 05-Sep-23 Initial Issue All

Project No.
PT INDOBOILER 99.953.2023
Total or partial reproduction and/ or utilization of this Document No.
document is forbidden without prior written
authorization from Indoboiler
IB.PS.PRJ.08
LIFTING PLAN
PT. INDOBOILER
PROYEK RETUBING HHP-3 PT. KPI RU V-BALIKPAPAN
Hari/tanggal : Perusahaan : Area Deskripsi Pekerjaan :

Sep-23 PT. Indoboiler Utilities Install top chimney

Peralatan Pengangkatan Data of Lifting


Hitch Methode ( Metode Ikatan)
Item Size/Capacity Qty › Weight of Material/Berat Material 1500 kg
Web-Sling 6000 kg 2 › Load Capacity (Based of Load Chart) 3600 kg
Shackle 1000 kg 2 › Weight of Lifting Gears 200 kg
› Total Load/Total Berat 1700 kg
CHOCKER HITCH
› Radius 20 m
› Length Boom/Panjang Boom 78 m
› Crane Condition (%) 90%
› Angle/Sudut 40°
LIFTING DATA:

Perhitungan Safety factor Dynamic Amplification Factors (DAF)


Lifting Gross weight,W Onshore
As Offshore Onshore
Capacity (tonnes) Moving Static
: Lifting Capacity W≤100 1,30 1,15 1,00
Safety factor
Total Load 100<W≤1.000 1,20 1,10 1,00
1.000<W≤2.500 1,15 1,05 1,00
: kondisi crane (%) x berat yang diijinkan 2.500<W≤10.000 1,10 1,05 1,00
Lifting : sesuai dengan load chart KESIMPULAN
Capacity : 90% x 3600 = 3240 1. Pekerjaan unloading material TOP CHIMNEY Berat 1500 Kg dan Berat Lifting Gears 200 Kg
2. Kondisi Crane 90 %
Lifting Capacity 3. Radius untuk pengangkatan 20 Meter

Total Load 4. Sesuai Load Chart crane radius 20 Meter beban yang bisa diangkat 3600 Kg
Safety factor :
3240 dengan panjang Boom 78 Meter
= 1,91
5. Safety Factor : 1,91 disesuaikan dengan DAF berarti Pengangkatan dikategorikan AMAN
1700

Dibuat Oleh Diperiksa Oleh Diperiksa Oleh Disetujui Oleh


PT. Indoboiler PT. Indoboiler PT. Indoboiler PT. KILANG PERTAMINA INTERNASIONAL

Irfan Susilohadi Andri Zakaria Zubair …………….. Median


Site manager Construction Manager HSE Officer HSE Dept SSIE