Lifting Plan Procedure
Lifting Plan Procedure
for
OVERHAUL HHP BOILER-III
Contractor by
PT. INDOBOILER
99.953.2023 008/KPI48000/2023-S0
Total or partial reproduction and/ or utilization of this document is forbidden without prior written authorization from
Indoboiler
TABLE OF CONTENT
Description Page
Cover Page 1
Table of Content 2
Revision Records 3
1. Lifting Plan Procedure 4
2. Load chart 5
Project No.
PT INDOBOILER 99.953.2023
Total or partial reproduction and/ or utilization of Document No.
this document is forbidden without prior written
authorization from Indoboiler
IB.PS.PRJ.08
REVISION RECORDS
REV. NO DATE DESCRIPTION REVISION PAGES
0 05-Sep-23 Initial Issue All
Project No.
PT INDOBOILER 99.953.2023
Total or partial reproduction and/ or utilization of this Document No.
document is forbidden without prior written
authorization from Indoboiler
IB.PS.PRJ.08
LIFTING PLAN
PT. INDOBOILER
PROYEK RETUBING HHP-3 PT. KPI RU V-BALIKPAPAN
Hari/tanggal : Perusahaan : Area Deskripsi Pekerjaan :
Total Load 4. Sesuai Load Chart crane radius 20 Meter beban yang bisa diangkat 3600 Kg
Safety factor :
3240 dengan panjang Boom 78 Meter
= 1,91
5. Safety Factor : 1,91 disesuaikan dengan DAF berarti Pengangkatan dikategorikan AMAN
1700