You are on page 1of 14

COMMISSIONING METHOD STATEMENT LEVEL -3

NOIDA – SECTOR 143

COMMISSIONING METHOD STATEMENT


LEVEL 3
ST TELEMEDIA DATA CENTER, NOIDA

LEVEL 3

AHU STARTUP TEST

Page 1 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

CONTENTS
1. INTRODUCTION.......................................................................................................4
2. EQUIPMENT DETAILS.............................................................................................5
3. ON-SITE TEST...........................................................................................................5
4. TESTING & COMMISSIONING EQUIPMENT.........................................................6
5. SAFETY..................................................................................................................... 7
6. PRE-TEST CONDITION............................................................................................7
7. LEVEL 3 START UP TEST: -.....................................................................................8
7.1 GENERAL................................................................................................................8
7.2 AHU START-UP CHECKS.......................................................................................8
8. AHU STARTUP TEST RECORD...............................................................................9
8.1 AHU FUNCTIONAL VERIFICATION WITH BYPASS STARTER.........................9
8.2 AHU FUNCTIONAL VERIFICATION WITH VFD................................................10
8.2.1 VFD @ 50 HZ.......................................................................................................10
8.3 AHU PARAMETER VERIFICATION....................................................................12
8.4 AIR FLOW MEASUREMENT................................................................................13
8.5 AIR BALANCING.................................................................................................. 14
8.6 BMS - POINT VERIFICATION WITH BMS..........................................................16
9. LIST OF DOCUMENTATION TO BE SUBMITTED...............................................19

1. INTRODUCTION
ST Telemedia is in the process of building a new data centre at Noida sector 143. CBRE ICS has
been appointed by STT for providing 3 rd party testing & commissioning services for the project.
This document covers the commissioning requirement and acceptance criteria for the works
covered under the AHU System.

Page 2 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

2. EQUIPMENT DETAILS
General
Unit Make: ZECO
Model Number: ZDCSBD-30
Serial No: 212541-08-01
Manufacturer Source: ZECO
Equipment Label: NOI-DC1-2F-TR10-CSU-1

Design Information
AHU Type: CSAHU-02
AHU Capacity: 2750 CFM
Motor RPM: 1430 RPM
Motor Power: 1.5KW
Rated Voltage: 415 V
Rated Current: 3.47 AMP
dB Level: 72 dBA @ 1 meter

3. ON-SITE TEST
The following tests shall be performed and witnessed for AHU.
Sr. Test SAT Remarks
No. Description
1 Pre-Test Condition

2 Electrical parameter verification

3 Air side parameter verification

4 Chilled Water Flow Verification

5 Parameter verification with BMS

6 Alarm Interfacing with BMS

7 Sound and Vibration Check

4. TESTING & COMMISSIONING EQUIPMENT

Page 3 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

Calibration Date
Equipment Name Serial No.
Model
Issue Expiry
Digital clamp meter CM-2030AC 1310308 04-04-2023 03-04-2024

Tachometer DT-2234C L163216 04-04-2023 03-04-2024

Rotating Vane Anemometer AM-4201 T018682 04-04-2023 03-04-2024

Water flow meter (Ultrasonic) TUF-2000H D12345 04-04-2023 03-04-2024

Sling Psychrometer NA NA 04-04-2023 03-04-2024

dB meter HTC N1041319 04-04-2023 03-04-2024

Vibration meter VB-8205 N978180 04-04-2023 03-04-2024

Calibration requirement: - All equipment’s testing and commissioning shall be performed


with valid calibration certificates. All calibration certificates shall be submitted for CxA review
at least one week prior to each T&C activity being undertaken.

5. SAFETY

The following safety points must be taken care of while performing site acceptance test for AHU.

 GC/Vendor should ensure to provide the Safety helmets and shoes for
individual protection while standing in the perimeter of AHU in
operation.

 Areas of high risk must be properly secured.

 The Site should have First Aid workers. In case of emergency, quick
medical assistance must be provided.

 Before the Testing commences, the host must explain to all


individuals about the evacuation procedure in case of a fire or any
other incident.

 Proper illumination and a dust-free environment should be provided


to carry out the test.

 Lock-Out Tagout shall be provided for the charged equipment’s.

Page 4 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

6. PRE-TEST CONDITION

The following criteria shall be satisfied before the Testing & Commissioning can commence:

Inspection Status Remarks


Level 2 checks completed, and results found satisfactory Yes No N/A
Confirm all major snags highlighted during Level 2
Yes No N/A
testing are rectified
Confirm Level 2 completion tag (Yellow Tag) available
Yes No N/A
on AHU.
Confirm all necessary testing & commission equipment’s
are available on site During startup test. Ensure all T&C Yes No N/A
equipment’s are calibrated.
Confirm space is in good condition and fit for
Yes No N/A
commissioning to commence.
Clean and clear off any debris within the starter
Yes No N/A
compartment.
Confirm all AHU material is removed for the unit and
Yes No N/A
that air inlets and discharges are free from obstruction.
Check power supply available at the incoming of AHU
and verify the Yes No N/A
Voltage and Phase sequence.

7. LEVEL 3 START UP TEST: -

7.1 General

Page 5 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

Undertake all necessary checks and complete the Testing & Commissioning Record as per this
method statement.
 Start Fan as per OEM's Recommendation.

7.2 AHU Start-Up Checks


 Test the AHU by using the AHU by-pass starter, Star Delta or DOL starter. On
activating the motor starter at initial start.

 The direction and speed of rotation of the motor shaft are correct.
 The VCD full open condition.

 The motor, blower, and drive are free from vibration and undue noise.

 The sequence timing adjustment of star-delta starters (≥10s), auto-transformer


starters (≥15s), etc. is set in line of motor starting current.

 The motor running current on all phases are balanced and do not exceed motor
nameplate rating. The discharge valve can be opened slowly and monitoring
the AHU running current is not over of the motor full load current.

 Record the AHU running current, voltage, suction/ discharge.

 There is no overheating of the motor.

 There is no seepage of the lubricant from the housing.

 The motor running current are matching with the speed as specified by manufacturer.

 After tested the AHU by-pass starter, test the AHU with VFD control.

 The VFD setting and all functional should be checked and tested with T&C
consultant during the SAT of MCC panel. The VFD shall be set at maximum
of 50 Hz while testing.

 Run the AHU with at maximum 50Hz, record the AHU running current,
voltage, input power factor, input harmonic at different running frequency.

 Check the motor, AHU and drive are free from vibration and undue noise.

8. AHU STARTUP TEST RECORD


8.1 AHU Functional Verification with bypass starter
Description Units Expected Act Result Remar
ual ks
Volumetric Flow Rate CFM 2750 3285 Pass Fail

Page 6 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

L1-L2 415 401 Pass Fail


(V)
Voltage
L1-L3 415 401 Pass Fail
(V)
L2-L3 415 401 Pass Fail
(V)

(Avg) 415 401 Pass Fail


(V)

L1 (A) 3.47 2.1 Pass Fail

At Design / Max Current L2 (A) 3.47 2.2 Pass Fail


running current of
motor L3 (A) 3.57 2.1 Pass Fail

(Avg) (I) 3.47 2.16 Pass Fail

Supply AIR (CFM) 2750 3197 Pass Fail

Return AIR (CFM) 2750 3285 Pass Fail

Control Panel: -

Description Pass / Fail


Power Healthy indication Lamps (L1/L2/L3) PASS FAIL N/A
Check Running Indication Lamps PASS FAIL N/A

Check Fault Indication Lamps PASS FAIL N/A

Check Motor Start push button PASS FAIL N/A


Check Motor Stop push button PASS FAIL N/A

Check Lamp Test push button PASS FAIL N/A

Check Auto / Off / Manual Switch operation PASS FAIL N/A

Check VFD / Bypass Switch operation PASS FAIL N/A

Fire integration PASS FAIL N/A

8.2 AHU Functional Verification with VFD


8.2.1 VFD @ 50 Hz
Description Units Expected Actual

Page 7 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

Volumetric Flow Rate CFM 2750 3159

L1-L2 415 390


(V)
Voltage
L1-L3 415 390
(V)
L2-L3 415 390
(V)

(Avg) (V) 415 390

L1 (A) 3.47 2.2

At Design / Max running Current L2 (A) 3.47 1.8


current of motor
L3 (A) 3.47 2.2

(Avg) (I) 3.47 2.06

Supply AIR (CFM) 2750 2893

Return AIR (CFM) 2750 3159

VFD

Description Record
Motor kW Setting YES NO NA
Full Load current Setting YES NO NA
Motor Voltage Setting YES NO NA
Maximum Operating frequency setting YES NO NA
Minimum Operating frequency setting YES NO NA
Ramp up Time setting YES NO NA
Ramp down Time setting YES NO NA
VFD Display and control button is normal operation YES NO NA
VFD Ventilation operating in normal condition YES NO NA
Fire integration YES NO NA
VFD modulation on Differential pressure YES NO NA

Page 8 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

8.3 AHU parameter Verification

Parameters Unit Design Data Test Result Remarks

Total Air Quantity CFM 2750 CFM 3159 CFM

Fresh Air Quantity CFM NA NA


Parameters (Air side)
Fan Static Pressure Drop
mm WC 45 35
(Discharge - Inlet)
Entering Air Dry Bulb Temp °C NA 23.5
Entering Air Wet Bulb °C
NA 17
Temp
Leaving Air Dry Bulb Temp °C NA 20.5
Leaving Air Wet Bulb Temp °C NA 16.5
Settings
Overload Setting A 80% 2.8 A
Tripping Time of Overload Sec NA NA
Rated Power kW 1.5 KW .55 KW
Emergency Stop NA NA NA
Filter
Type
Effective Area sq.ft NA 6.22
Velocity FPM NA
Cooling Coil
Inlet Water Temperature °C 19 19.0
Outlet Water Temperature °C 24 23.5
Inlet Water Pressure kg/cm2 NA 6.8
Outlet Water Pressure kg/cm2 NA 6.3
Chilled water flow M3/hr or GPM 10.94 11.5 (As per PICV settings)

Noise & Vibration


Noise Level dB 72 @ 1 57 dBA

Page 9 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

Parameters Unit Design Data Test Result Remarks

Meter
Vibration level mm/s 1.8 mm/s 1.31,0.69,0.88
VFD Modulation (Ramp
NA NA
up/down)
Filter Clog Status YES YES
Fan Running Status YES YES
Fire Tripping YES YES
Limit switch status NA NA
Inspection light status NA NA
UV light status NA NA

8.4 Air Flow Measurement


AHU TAG No NOI-DC1-L2-BR 2-CSU-2 Capacity: 2750 CFM
AHU Model No: ZDCSBD-30 AHU Location BATTERY ROOM

Air Flow Measurement at Return filters (ft/min)


VFD Speed: 50 Hz

517 482 505 535


525 529

510 495 485 497


Air Side
Calculations
508 FPM Voltage (V) Current (A)
Average
velocity : PF

6.22 sq.ft V VYB VBR IR IY IB


Filter Area : R
Y

Air-flow at 3159 cfm 390 390 390 2.2 1.8 2.2


Return(cfm) :

Page 10 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143

Air-flow at
Power
Supply(CFM 2893 CFM 1.176 kW
consumption =
):

Design
2750 CFM % of deviation 5.2 %
Airflow

Result PASS FAIL

8.5 Air Balancing


Grill/
Sr. Velocity - Actual Flow Design Flow -
Diffuser – Area Deviation % Result
No. FPM - CFM CFM
Size

1 1180x280 3.55 815 2893 2750 5.2 %

Page 11 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143
8.6 BMS - Point Verification with BMS
Sr.
I/O Parameters At Field At BMS
No Result Remarks
Status Value Status Value

1 Fan “ON” Command Yes No N/A Yes No N/A Pass Fail

2 Fan “OFF” Command Yes No N/A Yes No N/A Pass Fail

3 Fan Run Status Yes No N/A Yes No N/A Pass Fail

4 Fan Trip status Yes No N/A Yes No N/A Pass Fail

5 Fan “Auto” status Yes No N/A Yes No N/A Pass Fail

6 Fan “Manual” status Yes No N/A Yes No N/A Pass Fail

7 Filter Clean/Clog Status Yes No N/A Yes No N/A Pass Fail


Supply Air Temperature Pass Fail
8 Monitoring Yes No N/A Yes No N/A

Return Air Temperature Pass Fail


9 Monitoring Yes No N/A Yes No N/A

Chilled Water Control Valve Pass Fail


10 Modulation Command Yes No N/A Yes No N/A

Chilled Water Control Valve Pass Fail


11 Feedback Yes No N/A Yes No N/A

Page 12 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143
Sr.
I/O Parameters At Field At BMS
No Result Remarks
Status Value Status Value

12 CHW Inlet Temp. Monitoring Yes No N/A Yes No N/A Pass Fail
CHW Outlet Temp. Pass Fail
13 Monitoring Yes No N/A Yes No N/A

14 Return Air RH Monitoring Yes No N/A Yes No N/A Pass Fail

15 Filter Clean/ Clog Status Yes No N/A Yes No N/A Pass Fail

16 VFD Local/ Remote Status Yes No N/A Yes No N/A Pass Fail

17 VFD Fault Status Yes No N/A Yes No N/A Pass Fail

18 VFD Frequency Monitoring Yes No N/A Yes No N/A Pass Fail


VFD Motor Current Pass Fail
19 Monitoring Yes No N/A Yes No N/A

VFD Motor Voltage Pass Fail


20 Monitoring Yes No N/A Yes No N/A

VFD Power Consumption Pass Fail


21 Monitoring Yes No N/A Yes No N/A

22 VFD cumulative run hours Yes No N/A Yes No N/A Pass Fail

23 VFD Cumulative KWh Yes No N/A Yes No N/A Pass Fail

Page 13 of 14 Independent Commissioning Services


COMMISSIONING METHOD STATEMENT LEVEL -3
NOIDA – SECTOR 143
OBSERVATIONS IF ANY:

9. LIST OF DOCUMENTATION TO BE SUBMITTED


LIST OF DOCUMENTS

Verify that the following documentation has been received and stored with the project
documentation

Measuring Instruments Calibration Certificate Yes No N/A

GFC Drawing Yes No N/A

GA Drawing Yes No N/A

BOM Yes No N/A

FAT Report Yes No N/A

Level 2 Report Yes No N/A

Approved I/O Summary Yes No N/A

Technical Submittals Yes No N/A

Control Drawing Yes No N/A

Comments: if Any: -

Approval Signatures

This Level 3 Startup Test script is submitted for approval.

Vendor Bluestar Ltd Name Virendra P Signature Date 03/06/2023

CBRE
CBRE SAPL Name M Sartaj Signature Date 03/06/2023
PMC

CBRE CBRE SAPL - Name Husain A. Signature Date 03/06/2023


ICS ICS

STT STT GDC Name Rahul S. Signature Date 03/06/2023

Page 14 of 14 Independent Commissioning Services

You might also like