You are on page 1of 1

Pier

Pier setting out point

Track reference level

Bearing

Pier head (precat shell,


Pier cap joint in situ infill)
line
Pier cast column height varies

Flexible robust cables and weatherproof 2200


box for stray current monitoring where (D)
required. Typical drainage arrangement

3000 or top of
column if less
Waterproof
coating
Removable cap
1000 × 500 × 300
Existing stone (to prevent
scour) Invert level varies
ground level
100 min

(typically)
500
Top of pile
cap Waterproof membrane

Level varies

2050
Pile cut-off 50
level
C.J.
Pile length varies

75 blinding

Rockhead (varies)

1400ø 1400ø
piles piles
Pile toe level varies

Figure 10. Typical four-pile pile group arrangement for internal piers (dimensions in mm)

Typically, class C32/40 was used for the pier and pile cap calculation methods introduced into the automated procedures
concrete. Class C32/40 concrete was also used for the piles, but to optimise the designs for the foundations yet to be
to account for possible weakening during the placement (under constructed.
bentonite or polymer-modified suspension fluid) the cube
strength design value used was reduced by 10 MPa. All The design programme capitalised on the locations of the UK-
reinforcement used in the substructure design was high yield, based structures team and the Dubai-based alignment team,
type 2 deformed bars with a yield stress of 460 MPa. The which handled setting out and local issues such as utility
aggressive ground conditions meant that durability considera- diversions. Advantage was made of the staggered weekends
tions were paramount. As a result, additional waterproofing was between Dubai and the UK; the alignment of a given section was
applied to the top 5 m of all piles to improve resistance to distributed at the start of the UK week and the appropriate design
chloride attack and pile cover to reinforcement of 120 mm was data added and sent back to Dubai at the end of the UK week.
used to improve resistance to sulfate attack. Generally crack Coupled with the automation process developed, this allowed a
widths (under combination 1 loads) were limited to 0?2 mm. peak output of 100 bespoke designs per week to be achieved.
Fatigue of reinforcement was also a critical design consideration
in some locations (see Section 8 below).
5. DESIGN DURING CONSTRUCTION: GANTRY
The construction programme called for the initial design of over LOADING
1200 unique foundations in the first 9 months of design to take The majority of the simply supported decks and two-span
the viaduct construction off the critical path. This was achieved continuous decks were constructed by overhead gantries
through automation of the bulk of the design process and the (illustrated in Figures 11 and 12). The temporary loading from
use of conservative simplifying assumptions in the early stages the various gantries used on the scheme was defined by the
of design. As the team got ahead of the programme, the temporary works subcontractor, VFR (a consortium comprising
conservatism was removed from the process and more refined VSL, Freyssinet and Rizzani De Eccher), appointed to undertake the

68 Bridge Engineering 162 Issue BE2 Design of the Dubai Metro light rail viaducts—substructure Smith N Hendy

You might also like