The Meccah network node went down on March 30th due to a POE license not being applied to the Siklu equipment. It took over 5 hours to resolve the issue by uploading the missing POE license. The root cause was determined to be POE licenses being sent to an unmanned email address. Actions were assigned to prevent future issues including checking email routing, management site setup, and project tracking procedures.
The Meccah network node went down on March 30th due to a POE license not being applied to the Siklu equipment. It took over 5 hours to resolve the issue by uploading the missing POE license. The root cause was determined to be POE licenses being sent to an unmanned email address. Actions were assigned to prevent future issues including checking email routing, management site setup, and project tracking procedures.
The Meccah network node went down on March 30th due to a POE license not being applied to the Siklu equipment. It took over 5 hours to resolve the issue by uploading the missing POE license. The root cause was determined to be POE licenses being sent to an unmanned email address. Actions were assigned to prevent future issues including checking email routing, management site setup, and project tracking procedures.
30/03/2022 13:07 – Node holder contact attempt no answer. 30/03/2022 14:01 – Yasser asks if a call out is going to be required. 30/03/2022 14:02 – Checked for power outages. 30/03/2022 15:03 – Yasser makes contact with node holder and confirms internet working but via old connection. 30/03/2022 15:21 – Yasser asks about license on POE out. NOC confirmed that they hadn’t received it. 30/03/2022 16:49 – Rofiq confirms engineer on route ETA 1 Hour. 30/03/2022 18:37 – PoE license uploaded. Meccah issue resolved.
Diagnosis / Fix / Root Cause Analysis:
POE Out license not applied to the Siklu PoE license’s where sent to an unmanned email address box
What did we do well?
Yasser identified the issue quickly
What can we do better, next time?
Make sure all POE out licenses are done and Siklu’s are not left of Trial. Project/install wasn’t closed out correctly, leaving small yet important step of the PoE licence’s unconfirmed as completed. Any other key takeaways? Delay getting hold of the Node holder. Review of in-hours contact method as NOC tried to call a number of times with no success, yet engineering got through immediately.
Follow-on Actions:
Action Owner Due Date Status
Check email address routing RF Check Management site setup for Meccah nodes JS Telephone with UPS required (Josh) LP Review MS provisioning steps and ownership / JS/LP Project tracking Look to include Yasser in Network CR meeting LP