1.0 Introduction
A. Water Cycle
i. Water cycle also called hydrologic cycle, cycle that involves the continuous
circulation of water in the Earth atmosphere system
ii. Of the many processes involved in the water cycle, the most important are
evaporation, transpiration, condensation, precipitation, and runoff
iii. Although the total amount of water within the cycle remains essentially constant,
its distribution among the various processes is continually changing
)
Question 1
Calculate total PE
Answer 1:
One development of Health Clinic with Quarters (4 units) in Bandar Inderasakti was
assigned to Rahmat Construction. The scope of the project is as follows
● i) Health Clinic (Floor Area - 4,300 m2)
● ii) Staff Quarters (4 unit)
Calculate the total PE and area of the land required to develop the treatment
systems
Question 4
Calculate DWF value for 10,000 people if water consumption rate is 250
liter/capita.Day
Question 5
Calculate DWF value for 25,700 people if water consumption rate is 200
liter/capita.Day and ratio wastewater / water supply is 0.75
Question 6
As an engineer, determine and specify the best number and location for inspection
chamber (IC) if sewage from this house will be discharge to the Individual Septic Tank
(IST)
Answer
IST
Question 7
As an engineer, determine and specify the best number and location for inspection
chamber (IC) if sewage from this house will be discharge to the IWK Centralized
Treatment System.
Answers
Question 8
Upgrading works the Emergency Department of Balik Pulau Hospital, Penang will be
conducted soon. Project scope as follows
Guard house
Sewage from this development is drained to the IWK Centralized Treatment System.
b) Propose the appropriate size and type of private sewer that connected all IC
Design Example 1 – Design the sewer pipeline for this residential area
Design Example 2 – Design the sewer pipeline for this residential area
Question 8
Design one septic tank which received wastewater from 150 residential
Question 10
Determine the number of people using a septic tank with the dimension is 10m x 5m x
2m
► ALTERNATIVE STEPS TO DESIGN PUBLIC SEWER
► Step 1 – Calculate PE for all proposed buildings
► Step 2 – Calculate average flowrate (DWF)
► Step 3 – Calculate Peak Factor
► Step 4 – Calculate Qpeak
► Step 5 - Identify d/D ratio (if 70% full, d/D is 0.7)
► Step 6 - Identify qpeak/QFULL value and vpeak/Vfull value from design
chart at d/D value, Example
► qpeak/QFULL = 0.85
► Vpeak/VFULL = 1.14
► Step 7 - From peak flowrate value, qpeak, identify QFULL and VFULL.
so that QFULL = (x) and VFULL = (y)
► Step 8 - Enter QFULL= (x) in Manning’s equation. We get the
sewerage diameter
► Step 9 - Calculate VFULL
► Step 10 - Check real sewer velocity at qPEAK and qMIN and compare
with self-cleansing velocity requirement.
Question 1
Determine sewage velocity in one coated cast iron sewerage with 1.8m
diameter and 1:600 slope and full flow (for this example only)
Question 2
Determine sewage velocity in one coated cast iron sewerage with 1.8m
diameter and 1:600 slope and flows 60% full
Question 3
Design a separate sewerage flowing a 70% full at a peak flowrate
of0.42m3/s and minimum flowrate of 0.047m3/s. Take hydraulic gradient as
1:600 and type of sewerage is bad coated cast iron (n = 0.013)
Question 4
Design a bad condition ductile iron separate sewer which flows 30% empty
at Qmaximum for a town with 20,500 houses and 120 shop houses with an
average area of 900 m2 each. An allowable slope is 1:600
Question 5
As a civil engineer, you are required to design public sewerage pipeline using the ductile
iron pipe to cater the listed populations. With standard water consumption rate, propose
the diameter of the pipe
Table 1: Population
Type of premises Quantity
Residential 12000 houses
School - Day school 2000 students
School – boarding school 1000 students
Hospital 500 beds
Market (wet type) 1500 stall
Question 1
One wastewater treatment plan is planned to cater 50,000 people. Determine width
of screens chamber and appropriate number of blade, based on these design
criteria. Calculate also the quantity of screenings should the storage period is 7 days
Volume = 0.9m/s
Depth of wastewater at peak flowrate = 0.85m
Question 3
One grit chamber is designed for a domestic wastewater treatment plant. This
plant receives waste from 8000 people. If Qpeak is used in this design, calculate
length, width and depth of this chamber. Given, SOR per day is 1500 m3/m2 and
horizontal velocity is 25 cm/s.
Question 4
A peak flow from 25 000 PE flows into a rectangular, horizontal flow grit chamber.
If the width of the tank is 1.5m, determine
Building Nos
○ A rectangular tank
A sedimentation tank with the retention time equal to 2 hours is needed for treating
wastewater from a residential area based on the data as given below and also
population data in Table 1. Assume depth of tank is 1.5 m.
Design One circular primary tank with slope 7.5° that received influent from one
housing area with 100,000 people. Using this design data:
● SOR is 30m3/m2.day,