You are on page 1of 5

Secondary Drawing Tracking list(G2G) 23-10-2023

Letter Ref. & Date of SSD


SL.No Substation name Type of Drawing Priority
Submission Checking by
ATR-3 CRP 4902 - 02/10/2023 1 SE sir
230KV Busbar Protection Panel 5099 - 22/10/2023 1 Mr.Iftekar
1 230/132 KV Comilla(N)
132KV Busbar Protection Panel 5100 -22/10/2023 1 Mr.Iftekar
132kV Incoming 4901 - 02/10/2023 1 SE sir
2 230/132KV Khulna (C) SS CRL 4984 -11/10/2023 1 Mr.K(Civil Dep.)
3 132/33kV Purbasadipur GIS PSLD 5077-18/10/2023 1 Mr.Iftekar
4 132/33kV Noagaon GIS PSLD 5078 - 18/10/2023 1 Mr.Iftekar
5 400/132 KV Shambuganj SS PSLD 4941 - 08/10/2023 1 Mr.Kuratul Ain
6 132/33KV GIS Birulia SS PSLD 5065-17/10/2023 1 Mr.Iftekar
132KV TR1/2 CRP 5000-12/10/2023 Mr.Iftekar
7 132/33KV Jessor AIS TR1/2 33KV Incoming Bay CRP 5001-12/10/2023 Mr.Iftekar
TR3 33KV Incoming Bay CRP 5002-12/10/2023 Mr.Iftekar
132KV BusCouplar CRP 5004-12/10/2023 Mr.Kuratul Ain
132 KV Line CRP Distance Protection 5005-12/10/2023 Mr.Kuratul Ain
132/33KV TR4 33KV incoming CRP 5006-12/10/2023 Mr.Kuratul Ain
8 132/33KV Saidpur AIS
132/33KV TR5 33KV incoming CRP 5007-12/10/2023 Mr.Kuratul Ain
132/33KV TR2/3 33KV incoming CRP 5009-12/10/2023 Mr.Kuratul Ain
132/33KV TR2/3 CRP 5010-12/10/2023 Mr.Kuratul Ain
9 Routine Test Report 48V DC Converter 4986-12/10/2023 1 Mr.Rafi
10 Routine Test Report UPS 4987-12/10/2023 1 Mr.Rafi
11 Routine Test Report BatteryCharger 110V 4988-12/10/2023 1 Mr.Rafi
12 Routine Test Report Control & Protection Equipment of Bogra(S) 230kV 5020-12/10/2023 1 PD office
13 400/230KV EX.Kaliakoir AIS PSLD (Re.sub.) 5085-19/10/2023 1 SE sir
14 Ex.230/132kV Hathazari AIS PSLD 5030-15/10/2023 1 Mr.Iftekar
15 132/33 kV Fenchuganj AIS Busic Design 5036-15/10/2023 1 Mr.Kuratul Ain
16 Test Report Relay of Rampura 230kV AIS SS 5025-15/10/2023 1 SPMC
132KV TR1/2 CRP 5044-16/10/2023 Mr.Kuratul Ain
33KV Incoming TR1/2 CRP 5047-16/10/2023 Mr.Kuratul Ain
17 132/33kV Netrokona SS
132KV BusCouplar 5046-16/10/2023 Mr.Kuratul Ain
Tariff Meter 5045-16/10/2023 Mr.Kuratul Ain
18 GE & Siemens SAS Proposal for FAT and Routine Test Report Format 5055-16/10/2023 1 Mr.Kuratul Ain
19 Patnitola 132/33kV AIS SAS Panel 5067-17/10/2023 1 Mr.Kuratul Ain

Total Volumes: 32
Secondary Drawing Tracking list(G2G) 03-10-2023
Letter Ref. & Date of
SL.No Substation name Type of Drawing Priority
Submission
1
2
3
4
Secondary Drawing Tracking list(G2G) 03-10-2023
Letter Ref. & Date of
SL.No Substation name Type of Drawing Priority
Submission
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

You might also like