Professional Documents
Culture Documents
OP - AS19 - Wiring Harness-Layout - 20200702 - V0 - MWA
OP - AS19 - Wiring Harness-Layout - 20200702 - V0 - MWA
OP : AS-19
Wiring harness & Layout Status : 07.2020
Page : 1/5
Scope
This document is to describe the end user about the proper procedure on removal and refitment of
the EATS wiring harness and its connectors.
Description
FO Q01 / 09.2016
Operating procedure
OP : AS-19
Wiring harness & Layout Status : 07.2020
Page : 2/5
ATS Harness
FO Q01 / 09.2016
Operating procedure
OP : AS-19
Wiring harness & Layout Status : 07.2020
Page : 3/5
Pin Configuration
Procedure
FO Q01 / 09.2016
Operating procedure
OP : AS-19
Wiring harness & Layout Status : 07.2020
Page : 4/5
• To mate the male and female connectors, the male keys and female keyways must align as
shown in figure (1). Once aligned, it is pushed until it reaches the inner base of the connector
and the Coupling Ring is screwed until the guides are observed through the holes in the Cou-
pling Ring as shown in figure (2).
• Polarized indicators serve as guides to make the connection between the connectors, each
connector has an internal guide that makes the holes of the cavities aligned.
Proper Mounting:
• At the beginning of mounting, a tilt of
maximum ±15 degree is allowed to find
the right track.
• When the slide is engaged by approx.
5mm to 10mm in the housing, it may
only be pushed into the locked position
with a tilt of max ± 2 degree.
Improper Mounting:
FO Q01 / 09.2016
Operating procedure
OP : AS-19
Wiring harness & Layout Status : 07.2020
Page : 5/5
FO Q01 / 09.2016