Professional Documents
Culture Documents
Quarter 2
EHS OBJECTIVE AND KEY RESULTS
Make PAM a place where people feel safe and their wellbeing is a priority
01 02 03 04 05
9 EHS Stories 80% transition of Roll out of a H&S 6 New registers built and
100% completion of site
Communicated across the Occupational Health behavioural/psychological implemented across all
planned EHS action plans
business Records climate survey sites
1
05/05/2023
Performance Summary
March
Objective PAM UK Holwell Ilkeston Telford
Health & Safety
TF 1-3 Occurred 2 1 1 0
TF 4 Raised
TF 5 Raised
SMATs Conducted
EvE 1-3 0 0 0 0
2
05/05/2023
PIPE EUROPE
Pipe Europe
Accident & Incident Statistics
Where have we hurt? Type of Incident Contact with
Month YTD Gaia Slip, Trips & Machinery
Falls 1
Leg Arm 1 14%
1 1
14%
14% 14%
TF 1 0 0 1.2
Face
1
14%
TF 2 0 0 2.4 Hand
2
29% Hit by moving
Fingers
1 object
TF 3 2 7 32 Foot 14% 5
72%
1
14%
25 TF3 5th April Ilkeston face. Root cause identified worn tooling as the major factor.
face
Graze to IP was knocking the ingate off a BT triple side section when the TF 5 33 122
2 TF3 25th April Holwell section below fell off the pallet and struck him on the foot
foot causing a graze to his left foot
TF 4 11 47
Ilkeston
TF 5 48 251
3
05/05/2023
Pipe Europe
SMATs
Monthly SMATs Conducted Activity Observed SMATs Conducted
120
33
22% 100 7%
Holwell 80
Ilkeston 60
Negative
40
50% Ilkeston Flange
Plant
Positive
20
20% Ilkeston
Stockground 0
419
93%
8%
SMATs Conducted
120
SMATs Month YTD Target
100
Holwell 56 222 60
80
60 HQ 11 33 N/A
40
CSG 22 97 14
20
0
FPP 22 89 10
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Pipe Europe
Environment
0
EvE 4 - 5 Environmental Incidents
0%
Month YTD
Date Site Details
EvE 1 0 0
EvE 2 0 0
7
EvE 3 0 2 100%
Holwell Ilkeston
4
05/05/2023
Pipe Europe
Energy (Electricity & Gas KWh)
Energy Performance
3500000
15% Performance
Targeted Result Target against 2022
3000000 Reduction
2500000
2,367,921
2000000 Month 2,686,605 KWH
KWH
1500000
1000000
YTD 8,064,901 KWH 6,095,401 KWH
500000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Energy Breakdown
Monthly Commentary 3500000
3000000
2500000
2000000
1500000
1000000
500000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Pipe Europe
CO2
Pipe Europe - Tonnes of CO2 produced
Rolling 12 month average CO2
Month YTD
1,200 Produced
1,000
400
200
Holwell 734 4,216
0
Dec-17
Apr-18
Dec-18
Jun-18
Aug-18
Apr-19
Dec-19
Apr-20
Dec-20
Apr-22
Dec-22
Oct-18
Jun-19
Aug-19
Oct-19
Jun-20
Aug-20
Apr-21
Dec-21
Oct-20
Jun-21
Aug-21
Oct-21
Jun-22
Aug-22
Oct-22
Feb-18
Feb-19
Feb-20
Feb-21
Feb-22
Feb-23
Ilkeston 37 201
Holwell Ilkeston CSG/HQ/Operations
CO2 Monthly
Holwell Natural gas Energy Consumed
Holwell Diesel
18.4% 7000000
1.1%
Holwell
LPG/Propane 6000000
0.0%
5000000
Ilkeston Natural
gas 4000000
2.6%
3000000
Ilkeston
LPG/Propane 2000000
0.8%
1000000
Ilkeston Diesel 0
Holwell Coke
75.8% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10
5
05/05/2023
SYSTEM CONFORMITY
Audit Findings
Date Site Type of Audit
14
12
10
06-08/03 CSG BSI Surveillance
8
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
External Communications
11
COSHH
The list of chemicals has been rationalised and confirmation of the of the inventory list is with the team leaders to confirm if still in use,
once this is completed the list will be finalised
RCS & RD
All documentation for this has now been brought together and a review of further actions of high risks areas
Further testing by Validate are taking place in week 18 in all areas for dust levels
A face-fit testing programme has started
TRAPS
The process of removing old documents has started (JSA's / Obsolete TRAPS) and the prioritising of TRAPS for review to start
Training for TRAP creation / review is in progress
Environmental
Landfill waste acceptance criteria being developed.
12
6
05/05/2023
13
PAM BUILDING
14
7
05/05/2023
PAM Building
Accident & Incident Statistics
25
20
No Accidents Recorded in April 15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
15
PAM Building
Environment
EvE 1-5 Environmental Incidents
Month YTD
Date Site Details
EvE 2 0 0
DISA
2
EvE 3 0 0
16
8
05/05/2023
PAM Building
Energy
Energy Performance 5% Result Target
Performance
1800000 Reduction against 2022
1600000
1400000 1,538,214 1,435,853
Month
1200000 KWH KWH
1000000
800000
4,103,405 3,938,448
600000 YTD
KWH KWH
400000
200000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Energy Breakdown
Monthly Commentary
1800000
1600000
1400000
1200000
1000000
800000
600000
400000
200000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
17
PAM Building
CO2
Tonnes of CO2 produced each month
Rolling 12 Month Average
120
100
80
60
40
20
0
Apr-18
Jun-18
Jul-18
Aug-18
Apr-19
Apr-20
Oct-18
Jun-19
Jul-19
Aug-19
Oct-19
Jun-20
Jul-20
Aug-20
Apr-21
Apr-22
Oct-20
Jun-21
Jul-21
Aug-21
Oct-21
Jun-22
Jul-22
Aug-22
Oct-22
Mar-18
Mar-19
Mar-20
Mar-21
Mar-22
Dec-17
Jan-18
Nov-18
Dec-18
Jan-19
Nov-19
Dec-19
Jan-20
Nov-20
Dec-20
Jan-21
Nov-21
Dec-21
Jan-22
Nov-22
Dec-22
Jan-23
Feb-18
May-18
Sep-18
Feb-19
May-19
Sep-19
Feb-20
May-20
Sep-20
Feb-21
May-21
Sep-21
Feb-22
May-22
Sep-22
Telford Diesel
(12month Average)
42.9%
R12m 72 (per month)
18
9
05/05/2023
SYSTEM CONFORMITY
Audit Findings
6 Date Type of Audit
5
1-3/03 BSI IMS Audit (9001, 14001, 45001)
4
3
30/03 BSI Audit (BES 6001)
2
1
31/03 BSI Kitemark Audit (BS EN 877, BS 437, BS 416, BS 6087)
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
External Communications
19
My Compliance Vision has been delayed so the project to transition over is currently on hold. Work will continue to expand the use of My C on site and build further registers and modules
where it has been identified and planned.
Following an internal meeting it has been decided that Arco are to be removed from site, along with the current vending machines and contract. Work is now underway to switch the PPE
to a different supplier whilst also trialling new PPE to replace the Arco branded PPE that is currently approved. The plan at site is to still use vending machines on site. However, these will
be through the new supplier and what appears to be a better system than what we currently have.
The new HAVs system has been trialled and approved for site. The order has been placed and the information required is being gathered. This is scheduled to be installed during the May
Shutdown with training and a go live date in June.
The site is behind with regards to COSHH, there is an inventory completed and in place, however, the elements for Safhear still need to be completed for the HICE Chemical Saint-Gobain
system. The minimum inventory for Safhear is planned to be completed in May and if possible, an audit against each of the HSE COSHH sheets on site will be conducted before the May
shutdown. If not, this will be done in June at the latest.
20
10
05/05/2023
ACCIDENT
STATISTICS
21
50.0 48.2
46.0
45.0 45.0 44.2
43.8 44.1 43.8 43.8
42.7 42.9 42.7 42.6
40.7 40.5 40.6 40.8
38.5 38.8 38.3 38.2
40.0 37.3 37.2
37.0 36.7 37.0 36.6
36.2 35.9
35.0 34.7 34.8
33.3 33.0
32.3 31.96
30.0
20.0
10.0
6.2 6.2 6.2 6.3
4.7 5.2 5.2 5.1 5.0 4.7 4.8 4.6 4.6 4.6
3.8 3.9 3.9 3.9 3.9 3.9 3.8 3.7 3.6 3.5 3.6 3.6 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
2.5 2.5 2.5 2.5 2.5 2.6 2.6 2.6 2.4 2.4 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.34 2.37
1.2 1.17 1.18
0.0
12rm TF1 – SG + Temp + Permanent Contractor 12rm TF2 – SG + Temp + Permanent Contractor 12rm TF3 – SG + Temp + Permanent Contractor
22
11
05/05/2023
20.0
6.1 6.2 6.2 7.8 5.9 5.9 6.0
10.0 4.3 4.4 4.4 3.1 3.1 3.1 3.1 4.7
3.2 3.2 3.2 3.2 4.8
3.2 4.8
3.2 4.8
3.2 4.7
3.1 3.0 4.5
3.0 4.5
3.0 3.0 3.0 3.0 2.9 2.9 2.9 4.4 4.4 4.4 4.4 3.0 3.0 3.0 4.5
3.0 4.5 4.5 4.5 4.5
3
1.4 1.5 1.5 1.6 1.6 1.6 1.5
0.0
PAM Building
50.0 46.5
45.0 38.2 39.0 38.7
40.0 36.4
32.5 32.9 33.4 32.2 32.5
35.0
30.0 26.2 25.6 23.8 22.5 22.6 23.3
25.0
17.4 17.7 16.3 16.2 16.3 15.9
20.0 15.6 15.4
15.0 11.5 11.4 11.4 11.1 10.9 10.2 10.2 10.2 10.2 10.2 10.2
10.0 6.1 6.4 6.5 6.4 6.6 6.7 6.4 6.5 6.6 6.4 6.0 5.6 5.7 5.8 5.9 5.8 5.0
5.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
12rm TF1 – SG + Temp + Permanent Contractor 12rm TF2 – SG + Temp + Permanent Contractor 12rm TF3 – SG + Temp + Permanent Contractor
23
Global Comparison
TF1 TF 2
TF2 12rm
Pipe & Building
24
12
05/05/2023
ACCIDENT / INCIDENT
25
The Details
The injured party was cutting banding from municipals ready to load them for shot blasting. As he cut the banding, it
struck him on the cheek causing a deep wound. An initial first aid review was completed and the First aider
advised that the injury requires hospital treatment.
The incident has been downgraded from TF2 to 3 due to the treatment received (wound glued)
26
13
05/05/2023
The Details
IP was knocking the ingate off a BT triple side section when the section below fell off the pallet and struck
him on the foot causing a graze to his left foot
27
28
14
05/05/2023
COMMUNICATIONS
29
CSG
A customer came to site to collect goods. He was observed driving the wrong
way through the Weighbridge so Martyn spoke to him so he would be aware of
this for future use. Whilst speaking to him, Martyn noticed that the loads wasn’t
strapped down and the truck appeared overweight, instead of ignoring this,
Martyn spoke to the drive about this and asked to weight the truck. The truck as
in fact 35% overweight so 2 pallets were offloaded.
If it wasn’t for Martyn taking the time to speak to the driver and ensure that the
load was correct and strapped, the truck would likely have left site and been a
real danger to the driver and other road users and pedestrians.
30
15
05/05/2023
FPP
Unfortunately, in April an operator within the area had an accident when
cutting banding, a part flew up and cut his face. A first aider was called to
the scene to provide first aid treatment to the injured operator.
The first aider that provided the treatment was a new first aider and had
only been on training 2 weeks prior to the accident occurring. However, he
had a rapid response and acted calmly and professionally whilst providing
treatment and advice.
Thank you Lee for being well prepared and acting with professionalism and
compassion whilst providing the treatment. If you have an EHS story to share, please get in
touch with your site EHS team
31
TELFORD
A new piece of equipment was purchased for use on site, the equipment was
installed in an area where the work was done before, however, this may not have
been the safest place for this.
Instead of leaving this where it had been originally placed, it was raised as a
concern and the individual arranged for a group of people to come together to
discuss all elements of the equipment, specifically the health and safety concerns.
When bringing people together, changes were made to improve the safety of use.
This shows how important it is for consultation and participation of all
stakeholders when changes made. If you have an EHS story to share, please get in
touch with your site EHS team
32
16
05/05/2023
Quarter 1
EHS OBJECTIVE AND KEY RESULTS
Make PAM a place where people feel safe and their wellbeing is a priority
01 02 03 04 05
Create a gap analysis approach
Identify a Behavioural /
Develop a positive and proactive EHS Identify a provider and/or Roll out My Compliance
to be used within PAM UK for Psychological safety
communication pack to be shared system for occupational across PAM UK site and
evaluation of compliance and programme to be used
regularly with the wider company embed 4 modules / systems
health surveillance trialled on one site
within PAM UK
The pack will be put into the connector but it The tender is now at it’s final stages A gap analysis has been conducted at There needs to be an understanding of My Compliance has been rolled out
is heavy on data and graphs. Holwell and now at Ilkeston. Both the resources within the business and within Ilkeston and a review needs to
with 2 companies remaining. Both
A template for EHS stories is in development the priorities we have. look at who is using this and how
assessments have highlighted areas of
are attending site for a meeting and
to be included within this pack or other
concerns, some areas highlighted were embedded the training is.
communications. discussion around this in April (17th
Nothing has happened on this as it was
known and some were not known. Holwell is still not rolled out, it is
If successful it would be nice to see this as a & 18th). If one of these is successful raised within the PAM EHS team to
separate message, similar to Connexions.
Work has taken place at Holwell to put being used by Quality & Health &
the aim is to have SLA in place and understand the priorities. I meeting will
We want to celebrate our people that have in place a gap analysis and action plan Safety but not yet live across leaders.
notice to current providers by start take place in March to review the
gone out of their way to embody our values to improve compliance in the Positive feedback has been given on
programmes we have and this will look
of May. highlighted areas.
within Environment, Health and Safety.
to launch a review wider within Q2. the modules used currently.
33
17